Power Equipment Operator prevailing wages: Nevada, county by county
65 current power equipment operator rates across 20 active Nevada wage determinations. Rates differ by county and construction type; click a determination for revision history, diffs, and change alerts.
| County / area | Classification | Rate | Fringe | Total | Determination |
|---|---|---|---|---|---|
| Carson City | OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $20.16 | $0.00 | $20.16 | NV20260041 Residential |
| Carson City | OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $24.11 | $0.00 | $24.11 | NV20260041 Residential |
| Carson City | POWER EQUIPMENT OPERATOR ((6) LOADER) | $63.79 | $36.40 | $100.19 | NV20260041 Residential |
| Carson City | POWER EQUIPMENT OPERATOR ((8) PAVER (ASPHALT, AGGREGATE, AND CONCRETE)) | $63.90 | $36.40 | $100.30 | NV20260041 Residential |
| Clark | Electrician-Lineman/Gourndman/Heavy Equipment Operator: Heavy Equip Op | $47.60 | $20.73 | $68.33 | NV20260071 Heavy |
| Clark | Electrician-Lineman/Gourndman/Heavy Equipment Operator: Lineman | $61.67 | $22.65 | $84.32 | NV20260071 Heavy |
| Clark | OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $20.16 | $0.00 | $20.16 | NV20260042 Residential |
| Clark | OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $24.11 | $0.00 | $24.11 | NV20260042 Residential |
| Clark | POWER EQUIPMENT OPERATOR ((6) LOADER) | $63.79 | $36.40 | $100.19 | NV20260042 Residential |
| Clark | POWER EQUIPMENT OPERATOR ((8) PAVER (ASPHALT, AGGREGATE, AND CONCRETE)) | $63.90 | $36.40 | $100.30 | NV20260042 Residential |
| Clark, Lincoln, Nye | POWER EQUIPMENT OPERATOR GROUP 1 AIR COMPRESSOR, PUMP OR GENERATOR OPERATOR; BLADE OPERATOR, ENGINEER-OILER AND SIGNALMAN; RAIL MOUNTED JLG; ROTARY DRILL TENDER (ROTARY AND CORE); STEAM CLEANER/PRESSURE WASHER; SWITCHMAN OR BRAKEMAN. (ZONE PAY ZONE B (REPORT TO NNSS) - $4.50 ZONE C (REPORT TO NTTR) - $4.50) | $53.79 | $34.00 | $87.79 | NV20260002 Building, Heavy, Highway |
| Clark, Lincoln, Nye | POWER EQUIPMENT OPERATOR GROUP 1 AIR COMPRESSOR, PUMP OR GENERATOR OPERATOR; ENGINEER- OILER AND SIGNALMAN; GUPIE OPERATOR (CEMENT); STEAM CLEANER/PRESSURE WASHER, SWITCHMAN OR BRAKEMAN, BLADE OPERATOR; ROTARY DRILL TENDER (ROTARY AND CORE); STEAM CLEANER/PRESSURE WASHER; SWITCHMAN OR BRAKEMAN. ZONE PAY: ZONE 1 - FREE ZONE $0.00; ZONE 2 - $3.00 32.5-45 MILES; ZONE 3: $4.00 - 45-60 MILES; ZONE 4: $4.50 - OVER 60 MILES | $55.94 | $34.15 | $90.09 | NV20260001 Building, Heavy, Highway |
| Clark, Lincoln, Nye | POWER EQUIPMENT OPERATOR GROUP 2 CONCRETE MIXER OPERATOR (SKID TYPE); CONVEYOR AND BELTMAN; FIREMAN; GENERATOR PUMP OR COMPRESSOR OPERATOR; GENERATOR, PUMP OR COMPRESSOR PLANT OPERATOR; HYDROSTATIC PUMP MOTORMAN (ROTARY AND CORE); PJU SIDEDUMP JACK; SCREENING AND CONVEYOR MACHINE (SIMILAR TYPE); SKIPLOADER (WHEELTYPE, FORD, FERGUSON, JEEP OR SIMILAR TYPE, 3/4 YARDS OR LESS, WITHOUT DRAG-TYPE ATTACHMENTS); TEMPORARY HEATING PLANT OPERATOR; TRUCK CRANE OILER. (ZONE PAY ZONE B (REPORT TO NNSS) - $4.50 ZONE C (REPORT TO NTTR) - $4.50) | $54.74 | $34.00 | $88.74 | NV20260002 Building, Heavy, Highway |
| Clark, Lincoln, Nye | POWER EQUIPMENT OPERATOR GROUP 2 CONCRETE MIXER OPERATOR (SKID TYPE); CONVEYOR OPERATOR AND BELTMAN; FIREMAN; GENERATOR, PUMP OR COMPRESSOR OPERATOR (2 TO 5 UNITS INCLUSIVE, OVER 5 UNITS; $0.10 PER HOUR FOR EACH ADDITIONAL UNIT UP TO 10 UNITS, PORTABLE UNITS); GENERATOR, PUMP OR COMPRESSOR PLANT OPERATOR; HYDROSTATIC PUMP MOTORMAN (ROTARY AND CORE); PJU SIDE DUMP JACK; SCREENING AND CONVEYOR MACHINE OPERATOR (OR SIMILAR TYPE); SKIPLOADER ( WHEELTYPE FORD; FERGUSON; JEEP OR SIMILAR TYPE, 3/4 YARD OR LESS (WITHOUT DRAG-TYPE ATTACHMENTS); TEMPORARY HEATING PLANT OPERATOR. ZONE PAY: ZONE 1 - FREE ZONE $0.00; ZONE 2 - $3.00 32.5-45 MILES; ZONE 3: $4.00 - 45-60 MILES; ZONE 4: $4.50 - OVER 60 MILES | $56.89 | $34.15 | $91.04 | NV20260001 Building, Heavy, Highway |
| Clark, Lincoln, Nye | POWER EQUIPMENT OPERATOR GROUP 3 A-FRAME OR WINCH TRUCK OPERATOR; BOBCAT OR SIMILAR TYPE (SKID STEER); DERRICKMAN (ROTARY AND CORE); DINKY LOCOMOTIVE OR TUNNEL MOTOR OPERATOR; ELEVATOR HOIST OPERATOR; EQUIPMENT GREASER; FORD, FERGUSON OR SIMILAR TYPE (WITH DRAG-TYPE ATTACHMENTS); GLOBAL POSITION SYSTEMS CHAINMAN AND RODMAN; HYDRA-HAMMER (OR SIMILAR TYPE EQUIPMENT); MATERIAL HOIST/OUTSIDE MANLIFT OPERATOR; POWER CONCRETE CURING MACHINE; POWER CONCRETE SAW OPERATOR (OR SIMILAR TYPE); POWER-DRIVEN JUMBO FORM SETTER; RODMAN AND CHAINMAN; ROSS CARRIER OPERATOR; SELF-CLIMBING SCAFFOLD (OR SIMILAR TYPE); SELF-ROPELLED TAR PIPELINING MACHINE OPERATOR; STATIONARY PIPE WRAPPING AND CLEANING MACHINE OPERATOR; TOWBLADE OPERATOR. ZONE PAY: ZONE 1 - FREE ZONE $0.00; ZONE 2 - $3.00 32.5-45 MILES; ZONE 3: $4.00 - 45-60 MILES; ZONE 4: $4.50 - OVER 60 MILES | $57.18 | $34.15 | $91.33 | NV20260001 Building, Heavy, Highway |
| Clark, Lincoln, Nye | POWER EQUIPMENT OPERATOR GROUP 3 A-FRAME OR WINCH TRUCK OPERATOR; BOBCAT OR SIMILAR TYPE (SKIDSTEER); DERRICKMAN (ROTARY AND CORE); DINKY LOCOMOTIVE OR TUNNEL MOTOR OPERATOR; ELEVATOR HOIST OPERATOR; EQUIPMENT GREASER; FORD, FERGUSON OR SIMILAR TYPE (WITH DRAG-TYPE ATTACHMENTS); HYDRA-HAMMER OR SIMILAR TYPE EQUIPMENT; MATERIAL HOIST/OUTSIDE MANLIFT OPERATOR; POWER CONCRETE CURING MACHINE; PPOWER CONCRETE SAW OPERATOR (OR SIMILAR TYPE); POWER DRIVEN JUMBO FORM SETTER OPERATOR; RODMAN & CHAINMAN; ROSS CARRIER OPERATOR; SELF-CLIMBING SCAFFOLD (OR SIMILAR TYPE); SELF-PROPELLED TAR PIPELINING MACHINE OPERATOR; STATIONARY PIPE WRAPPING AND CLEANING MACHINE OPERATOR; STEAM AND WATER PLANT OPERATOR; TOWBLADE OPERATOR. (ZONE PAY NTTR) - $4.50) | $55.03 | $34.00 | $89.03 | NV20260002 Building, Heavy, Highway |
| Clark, Lincoln, Nye | POWER EQUIPMENT OPERATOR GROUP 4 ASPHALT PLANT FIREMAN; BORING MACHINE OPERATOR; BORING SYSTEM ELECTRONIC TRACKING LOCATOR; BOXMAN OR MIXER BOX OPERATOR (CONCRETE OR ASPHALT PLANT); FISHING TOOL ENGINEER; HIGHLINE CABLEWAY SIGNALMAN; HORIZONTAL DIRECTIONAL DRILLING MACHINE; INSTRUMENTMAN; LOCOMOTIVE ENGINEER; MICRO TUNNELING (ABOVE GROUND TUNNEL); MINI-EXCAVATOR; MUD PLANT OPERATOR; POWER SWEEPER OPERATOR; ROLLER OPERATOR (COMPACTING); SCREED OPERATOR; SEEDER; TRENCHING MACHINE OPERATOR (UP TO 6FT. DEPTH); VACUUM TRUCK. ZONE PAY: ZONE 1 - FREE ZONE $0.00; ZONE 2 - $3.00 32.5-45 MILES; ZONE 3: $4.00 - 45-60 MILES; ZONE 4: $4.50 - OVER 60 MILES | $58.67 | $34.15 | $92.82 | NV20260001 Building, Heavy, Highway |
| Clark, Lincoln, Nye | POWER EQUIPMENT OPERATOR GROUP 4 ASPHALT PLANT FIREMAN; BORING MACHINE OPERATOR; BORING SYSTEMS ELECTRONIC TRACKING LOCATOR; BOXMAN OR MIXER BOX OPERATOR (CONCRETE OR ASPHALT PLANT); FISHING TOOL ENGINEER; HIGHLINE CABLEWAY SIGNALMAN; HORIZONTAL DIRECTIONAL DRILLING MACHINE; INSTRUMENTMAN; LOCOMOTIVE ENGINEER; MICO-TUNNELING (ABOVE GROUND TUNNEL); MINI EXCAVATOR OPERATOR; MUD PLANT OPERATOR; POWER SWEEPER OPERATOR; ROLLER OPERATOR (COMPACTING); SCREED OPERATOR; SEEDER; TRENCHING MACHINE OPERATOR, VACCUM TRUCK. (ZONE PAY ZONE B (REPORT TO NNSS) - $4.50 ZONE C (REPORT TO NTTR) - $4.50) | $56.52 | $34.00 | $90.52 | NV20260002 Building, Heavy, Highway |
| Clark, Lincoln, Nye | POWER EQUIPMENT OPERATOR GROUP 5 ASPHALT OR CONCRETE SPREADING MECHANICAL TAMPING OR FINISHING MACHINE OPERATOR- ROLLER (ALL TYPES AND SIZES), SOIL, CEMENT, ASPHALT FINISH; ASPHALT PLANT ENGINEER; DECK ENGINE OPERATOR; GRADE CHECKER; PAVEMENT-BREAKER OPERATOR; PNEUMATIC HEADING SHIELD (TUNNEL); ROAD OIL MIXING MACHINE OPERATOR; FORKLIFT (UNDER FIVE TONS); RUBBER-TIRED, HEAVY DUTY EQUIPMENT OPERATOR (OSHKOSH; DW EUCLID, LETOURNEAU; LAPLANT-CHOATE, OR SIMILAR TYPE EQUIPMENT WITH ANY TYPE ATTACHMENTS); SKIDLOADER (WHEELTYPE, OVER 3/4 YDS., UP TO AND INCLUDING 1 1/2-YARDS); SLIP FORM PUMP OPERATOR (POWER-DRIVEN HYDRAULIC LIFTING DEVICE FOR CONCRETE FORMS); TRACTOR OPERATOR (DRAG-TYPE SHOVEL, BULLDOZER, TAMPER SCRAPER AND PUSH TRACTOR. ZONE PAY: ZONE 1 - FREE ZONE $0.00; ZONE 2 - $3.00 32.5-45 MILES; ZONE 3: $4.00 - 45-60 MILES; ZONE 4: $4.50 - OVER 60 MILES | $59.77 | $34.15 | $93.92 | NV20260001 Building, Heavy, Highway |
| Clark, Lincoln, Nye | POWER EQUIPMENT OPERATOR GROUP 5 ASPHALT OR CONCRETE SPREADING MECHANICAL TAMPING OR FINISHING MACHINE OPERATOR-ROLLER (ALL TYPES AND SIZES), SOIL CEMENT, ASPHALT FINISH; ASPHALT PLANT ENGINEER; DECK ENGINE OPERATOOR; GRADE CHECKER; PAVEMENT-BREAKER OPERATOR; PNEUMATIC HEADING SHIELD- TUNNEL; ROAD OIL MIXING MACHINE OPEREATOR; FORKLIFT (UNDER (5) TONS); RUBBER TIRED, HEAVY DUTY EQUIPMENT OPERATOR; SKIPLOADER (WHEELTYPE, OVER 3-4 YARDS); SLIP FORM PUMP OPERATOR; TRACKOR OPERATOR, DRAG-TYPE SHOVEL, BULLDOZER, TAMPER, SCRAPER, AND PUSH TRACTOR. (ZONE PAY ZONE B (REPORT TO NNSS) - $4.50 ZONE C (REPORT TO NTTR) - $4.50) | $57.62 | $34.00 | $91.62 | NV20260002 Building, Heavy, Highway |
| Clark, Lincoln, Nye | POWER EQUIPMENT OPERATOR GROUP 6 BATCH PLANT OPERATOR; BULK PLANT OPERATOR; CONCRETE MIXER OPERATOR (PAVING); CONCRETE MOBILE MIXER OPERATOR; CONCRETE PUMP OR PUMPCRETE GUN OPERATOR; CRUSHING PLANT ENGINEER; DANDY DIGGER; DRILLER (ROTATRY/CORE); ELEVATING GRADE OPERATOR; FORKLIFT OPERATOR (OVER 5 TIMES); GRADE-ALL OPERATOR; HIGHLINE CABLEWAY OPERATOR; HOIST OPERATOR; JUMBO PIPE CARRIER; KOLMAN BELT LOADER, AND SIMILAR TYPE; LIFT SLAB MACHINE OPERATOR; LOADER OPERATOR; MACHINIST OPERATOR; MICRO TUNNEL SYSTEM (BELOW GROUND); MOTOR PATROL OPERATOR (ANY TYPE OR SIZE); OZZIE PADDER (OR SIMILAR TYPE); PNEUMATIC CONCRETE PLACING MACHINE OPERATOR (OR SIMILAR TYPE); PNEUMATIC PIPE RAMMING TOOL (AND SIMILAR TYPES); ROTOMIL OPERATOR; SEWER PLANT OPERATOR; SHOVEL, CRANE, BACKHOE, DRAGLINE, CLAMSHELL; DERRICK, DERRICK BARGE, PILE DRIVER, AND MUCKING MACHINE OPERATOR; SHUTTLE BUGGY; SKIPLOADER (WHEEL TYPE OVER 1 1/2 YARDS); SURFACE HEATER AND PLANER OPERATOR; TRACTOR LOADER OPERATOR, (CRAWLER TYPE- ALL TYPES AND SIZES); TRACTOR OPERATOR (WITH BOOM ATTACHMENTS); TRAVELING PIPE WRAPPING, CLEANING AND BENDING MACHINE OPERATOR; TRENCHING MACHINE OPERATOR (OVER 6-FT DEPTH); TUNNEL BORING MACHINE; WATER PULL (COMPACTION); WATER WELL DRILLER. (ZONE PAY ZONE B (REPORT TO NNSS) - $4.50 ZONE C (REPORT TO NTTR) - $4.50) | $57.74 | $34.00 | $91.74 | NV20260002 Building, Heavy, Highway |
| Clark, Lincoln, Nye | POWER EQUIPMENT OPERATOR GROUP 6 BATCH PLANT OPERATOR; BULK PLANT OPERATOR; CONCRETE MIXER OPERATOR (PAVING); CONCRETE MOBILE MIXER OPERATOR; CONCRETE PUMP OR PUMPCRETE GUN OPERATOR; CRUSHING PLANTEENGINEER; DANDY DIGGER; DRILLER (ROTARY AND CORE); ELEVATING GRADE OPERATOR; FORKLIFT (OVER (5) TONS); GRADE-ALL OPERATOR; HEAVY DUTY WELDER; HIGHLINE CABLEWAY OPERATOR; HOIST OPERATOR (CHICAGO BOOM AND MINE); JUMBO PIPE CARRIER; KOLMAN BELT LOADER (AND SIMILAR TYPE); LIFT SLAB MACHINE OPERATOR; LOADER OPERATOR (ATHEY, EUCLID, HANCOCK, SIERRA OR SIMILAR TYPE); MACHINIST OPERATOR; MICRO TUNNEL SYSTEM (BELOW GROUND); MOTOR PATROL OPERATOR (ANY TYPE OR SIZE); OZZIE PADDER (OR SIMILAR TYPE); PNEUMATIC CONCRETE PLACING MACHINE OPERATOR ( HACKLEY- PRESSWELL OR SIMILAR TYPE); PNEUMATIC PIPE RAMMING TOOL (AND SIMILAR TYPES); ROTOMILL OPERATOR; SEWER PLANT OPERATOR; SHOVEL, BACKHOE, DRAGLINE, CLAMSHELL, DERRICK, DERRICK BARGE, CRANE PILEDRIVER AND MUCKING MACHINE OPERATOR; SHUTTLE BUGGY; SKIPLOADER (WHEELTYPE, OVER 1-1/2 YDS); SURFACE HEATER AND PLANER OPERATOR; TRACTOR LOADER OPERATOR (CRAWLER TYPE ALL TYPES AND SIZES); TRACTOR OPERATOR (WITH BOOM ATTACHMENTS); TRAVELING PIPE WRAPPING, CLEANING AND BENDING MACHINE OPERATOR; TRENCHING MACHINE OPERATOR (OVER 6 FT. DEPTH); TUNNEL BORING MACHINE OPERATOR; WATER PULL (COMPACTION); WATER WELL DRILLER. ZONE PAY: ZONE 1 - FREE ZONE $0.00; ZONE 2 - $3.00 32.5-45 MILES; ZONE 3: $4.00 - 45-60 MILES; ZONE 4: $4.50 - OVER 60 MILES | $59.89 | $34.15 | $94.04 | NV20260001 Building, Heavy, Highway |
| Clark, Lincoln, Nye | POWER EQUIPMENT OPERATOR GROUP 7 BODY AND FENDER MECHANIC; GLOBAL POSITION SYSTEMS PARTY CHIEF; HEAVY DUTY WELDER AND REPAIRMAN; LIGHT DUTY REPAIRMAN (HYBRID/ALL ELECTRIC); PARTY CHIEF. ZONE PAY: ZONE 1 - FREE ZONE $0.00; ZONE 2 - $3.00 32.5-45 MILES; ZONE 3: $4.00 - 45-60 MILES; ZONE 4: $4.50 - OVER 60 MILES | $60.14 | $34.15 | $94.29 | NV20260001 Building, Heavy, Highway |
| Clark, Lincoln, Nye | POWER EQUIPMENT OPERATOR GROUP 7 HEAVY DUTY REPAIRMAN; HEAVY DUTY WELDER; LIGHT DUTY REPAIRMAN (HYBRID/ALL ELECTRIC). (ZONE PAY ZONE B (REPORT TO NNSS) - $4.50 ZONE C (REPORT TO NTTR) - $4.50) | $57.99 | $34.00 | $91.99 | NV20260002 Building, Heavy, Highway |
| Clark, Lincoln, Nye | POWER EQUIPMENT OPERATOR GROUP 8 COMBINATION HEAVY DUTY REPAIRMAN AND WELDER; EXCAVATOR OPERATOR (TRACK/RUBBER-TIRED-WITH ALL ATTACHMENTS); POWER PRODUCTION MECHANIC; STEAM/HOT WATER BOILER PLANT OPERATOR. ZONE PAY: ZONE 1 - FREE ZONE $0.00; ZONE 2 - $3.00 32.5-45 MILES; ZONE 3: $4.00 - 45-60 MILES; ZONE 4: $4.50 - OVER 60 MILES | $60.39 | $34.15 | $94.54 | NV20260001 Building, Heavy, Highway |
| Clark, Lincoln, Nye | POWER EQUIPMENT OPERATOR GROUP 8 EXCAVATOR/TRACKHOE OR SIMILAR. (ZONE PAY ZONE B (REPORT TO NNSS) - $4.50 ZONE C (REPORT TO NTTR) - $4.50) | $58.92 | $34.00 | $92.92 | NV20260002 Building, Heavy, Highway |
| Clark, Lincoln, Nye | POWER EQUIPMENT OPERATOR GROUP 9 COMBINATION HEAVY DUTY REPAIRMAN AND WELDER; RUBBER-TIRED ANYTANDEM, MULTIPLE ENGINE EARTH-MOVING EQUIPMENT OPERATOR. (ZONE PAY ZONE B (REPORT TO NNSS) - $4.50 ZONE C (REPORT TO NTTR) - $4.50) | $58.74 | $34.00 | $92.74 | NV20260002 Building, Heavy, Highway |
| Clark, Lincoln, Nye | POWER EQUIPMENT OPERATOR GROUP 9 RUBBER TIRED, TANDEM, MULTIPLE ENGINE, EARTH-MOVING EQUIPMENT OPERATOR; WATER TREATMENT/DISTRIBUTION OPERATOR; PLANT OPERATOR; CRANE OILER. ZONE PAY: ZONE 1 - FREE ZONE $0.00; ZONE 2 - $3.00 32.5-45 MILES; ZONE 3: $4.00 - 45-60 MILES; ZONE 4: $4.50 - OVER 60 MILES | $60.89 | $34.15 | $95.04 | NV20260001 Building, Heavy, Highway |
| Clark, Lincoln, Nye | POWER EQUIPMENT OPERATOR: GROUP 10 CRANE OPERATOR $3.00 32.5-45 MILES; ZONE 3: $4.00 - 45-60 MILES; ZONE 4: $4.50 - OVER 60 MILES | $64.48 | $34.15 | $98.63 | NV20260001 Building, Heavy, Highway |
| Esmeralda | Electrician-Lineman/Gourndman/Heavy Equipment Operator: Heavy Equip Op | $47.60 | $20.73 | $68.33 | NV20260085 Building |
| Esmeralda | Electrician-Lineman/Gourndman/Heavy Equipment Operator: Lineman | $61.67 | $22.65 | $84.32 | NV20260085 Building |
| Esmeralda | Electrician-Lineman/Groundman/Heavy Equipment Operator: Heavy Equip Op | $47.60 | $20.73 | $68.33 | NV20260075 Heavy |
| Esmeralda | Electrician-Lineman/Groundman/Heavy Equipment Operator: Heavy Equip Op | $47.60 | $20.73 | $68.33 | NV20260105 Highway |
| Esmeralda | Electrician-Lineman/Groundman/Heavy Equipment Operator: Lineman | $61.67 | $22.65 | $84.32 | NV20260075 Heavy |
| Esmeralda | Electrician-Lineman/Groundman/Heavy Equipment Operator: Lineman | $61.67 | $22.65 | $84.32 | NV20260105 Highway |
| Esmeralda + 12 more | POWER EQUIPMENT OPERATOR (BACKHOE) | $10.50 | $0.00 | $10.50 | NV20260045 Residential |
| Lincoln | Electrician-Lineman/Gourndman/Heavy Equipment Operator: Heavy Equip Op | $47.60 | $20.73 | $68.33 | NV20260080 Building |
| Lincoln | Electrician-Lineman/Gourndman/Heavy Equipment Operator: Lineman | $61.67 | $22.65 | $84.32 | NV20260080 Building |
| Lincoln | Electrician-Lineman/Groundman/Heavy Equipment Operator: Heavy Equip Op | $47.60 | $20.73 | $68.33 | NV20260065 Heavy |
| Lincoln | Electrician-Lineman/Groundman/Heavy Equipment Operator: Heavy Equip Op | $47.60 | $20.73 | $68.33 | NV20260106 Highway |
| Lincoln | Electrician-Lineman/Groundman/Heavy Equipment Operator: Lineman | $61.67 | $22.65 | $84.32 | NV20260065 Heavy |
| Lincoln | Electrician-Lineman/Groundman/Heavy Equipment Operator: Lineman | $61.67 | $22.65 | $84.32 | NV20260106 Highway |
| Nye | Electrician-Lineman/Gourndman/Heavy Equipment Operator: Heavy Equip Op | $47.60 | $20.73 | $68.33 | NV20260082 Building |
| Nye | Electrician-Lineman/Gourndman/Heavy Equipment Operator: Lineman | $61.67 | $22.65 | $84.32 | NV20260082 Building |
| Nye | Electrician-Lineman/Groundman/Heavy Equipment Operator: Heavy Equip Op | $47.60 | $20.73 | $68.33 | NV20260074 Heavy |
| Nye | Electrician-Lineman/Groundman/Heavy Equipment Operator: Heavy Equip Op | $47.60 | $20.73 | $68.33 | NV20260100 Highway |
| Nye | Electrician-Lineman/Groundman/Heavy Equipment Operator: Lineman | $61.67 | $22.65 | $84.32 | NV20260074 Heavy |
| Nye | Electrician-Lineman/Groundman/Heavy Equipment Operator: Lineman | $61.67 | $22.65 | $84.32 | NV20260100 Highway |
| Storey | OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $20.16 | $0.00 | $20.16 | NV20260043 Residential |
| Storey | OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $24.11 | $0.00 | $24.11 | NV20260043 Residential |
| Storey | POWER EQUIPMENT OPERATOR ((6) LOADER) | $63.79 | $36.40 | $100.19 | NV20260043 Residential |
| Storey | POWER EQUIPMENT OPERATOR ((8) PAVER (ASPHALT, AGGREGATE, AND CONCRETE)) | $63.90 | $36.40 | $100.30 | NV20260043 Residential |
| Washoe | Electrician-Lineman/Groundman/Heavy Equipment Operator: Equipment Specialist | $54.50 | $22.88 | $77.38 | NV20260073 Heavy |
| Washoe | Electrician-Lineman/Groundman/Heavy Equipment Operator: Equipment Specialist | $54.50 | $22.88 | $77.38 | NV20260093 Building |
| Washoe | Electrician-Lineman/Groundman/Heavy Equipment Operator: Equipment Specialist | $54.50 | $22.88 | $77.38 | NV20260110 Highway |
| Washoe | Electrician-Lineman/Groundman/Heavy Equipment Operator: Groundman | $41.68 | $22.23 | $63.91 | NV20260073 Heavy |
| Washoe | Electrician-Lineman/Groundman/Heavy Equipment Operator: Groundman | $41.68 | $22.23 | $63.91 | NV20260093 Building |
| Washoe | Electrician-Lineman/Groundman/Heavy Equipment Operator: Groundman | $41.68 | $22.23 | $63.91 | NV20260110 Highway |
| Washoe | Electrician-Lineman/Groundman/Heavy Equipment Operator: Lineman | $72.26 | $26.05 | $98.31 | NV20260073 Heavy |
| Washoe | Electrician-Lineman/Groundman/Heavy Equipment Operator: Lineman | $72.26 | $26.05 | $98.31 | NV20260093 Building |
| Washoe | Electrician-Lineman/Groundman/Heavy Equipment Operator: Lineman | $72.26 | $26.05 | $98.31 | NV20260110 Highway |
| Washoe | OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $20.16 | $0.00 | $20.16 | NV20260044 Residential |
| Washoe | OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $24.11 | $0.00 | $24.11 | NV20260044 Residential |
| Washoe | POWER EQUIPMENT OPERATOR ((6) LOADER) | $63.79 | $36.40 | $100.19 | NV20260044 Residential |
| Washoe | POWER EQUIPMENT OPERATOR ((8) PAVER (ASPHALT, AGGREGATE, AND CONCRETE)) | $63.90 | $36.40 | $100.30 | NV20260044 Residential |
Rates come from the current revision of each active determination; DOL revises these mid-year. Open a determination to watch it, or pin a bid date to lock the revision that legally applies. All Nevada trades.