Current rates (rev 1)
The CSV and the printed sheet are snapshots of rev 1. If DOL revises this determination after you save one, the watch above tells you exactly what moved.
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| LINE CONSTRUCTION: LINEMAN | $58.83 | $21.21 | $80.04 |
| OPERATOR: POWER EQUIPMENT: (5) ASPHALT ROLLER, BOBCAT/SKID LOADER, FRONT END LOADER(UNDER 2 CU. YDS.), OILER | $36.55 | $18.62 | $55.17 |
| OPERATOR: POWER EQUIPMENT: (4) ASPHALT PAVER, BULLDOZER, FRONT END LOADER(2 TO 5 CU. YDS.), GRADE SETTER, OIL DISTRIBUTOR, SCRAPER | $37.79 | $18.62 | $56.41 |
| OPERATOR: POWER EQUIPMENT: (3) BACKHOE/EXCAVATOR, FRONT END LOADER(OVER 5 CU.YDS.) | $39.01 | $18.62 | $57.63 |
| OPERATOR: POWER EQUIPMENT: (1)MECHANIC-EXCLUDING NATURAL GAS PIPELINE CONSTRUCTION | $41.71 | $18.62 | $60.33 |
| OPERATOR: POWER EQUIPMENT (6) SCREED | $36.55 | $18.62 | $55.17 |
| OPERATOR: POWER EQUIPMENT ((7) ROLLER(DIRT AND GRADE COMPACTION)) | $34.25 | $18.62 | $52.87 |
| OPERATOR: POWER EQUIPMENT ((2A)BLADE/GRADER) | $40.32 | $18.62 | $58.94 |
| OPERATOR: POWER EQUIPMENT: BACKHOE/EXCAVATOR/TRACKHOE, BLADE/GRADER, BOOM, BULLDOZER, MECHANIC: NATURAL GAS PIPELINE CONSTRUCTION ONLY | $35.68 | $17.57 | $53.25 |
| OPERATOR: POWER EQUIPMENT OILER: NATURAL GAS PIPELINE CONSTRUCTION ONLY | $22.03 | $11.88 | $33.91 |
| IRONWORKER | $32.68 | $27.55 | $60.23 |
| LABORER: POT TENDER AND SAND BLASTER: NATURAL GAS PIPELINE CONSTRUCTION ONLY | $20.85 | $8.65 | $29.50 |
| LABORER: COMMON OR GENERAL, PIPELAYER: NATURAL GAS PIPELINE CONSTRUCTION ONLY | $20.59 | $8.65 | $29.24 |
| LABORER: (5)HAND HELD DRILL | $21.65 | $8.65 | $30.30 |
| LABORER: (3) MASON TENDER (CEMENT/CONCRETE), HAND HELD SAW, JACKHAMMER, POWER SAW) | $20.85 | $8.65 | $29.50 |
| LABORER: (1)FLAGGER | $20.59 | $8.65 | $29.24 |
| LABORER: (1) COMMON OR GENERAL: EXCLUDING NATURAL GAS PIPELINE & WATER/SEWER LINE CONSTRUCTION | $20.59 | $8.65 | $29.24 |
| WATER & SEWER LINES: OPERATOR-BACKHOE/EXCAVATOR/TRACKHOE | $15.57 | $0.00 | $15.57 |
| WATER & SEWER LINES: LABORER, COMMON OR GENERAL | $12.81 | $0.00 | $12.81 |
| TRUCK DRIVER (EXCLUDING NATURAL GAS PIPELINE CONSTRUCTION) | $14.40 | $3.99 | $18.39 |
| OPERATOR: TRACKHOE (EXCLUDING NATURAL GAS PIPELINE AND WATER/SEWER LINE CONSTRUCTION) | $19.98 | $0.00 | $19.98 |
| OPERATOR: CRANE | $28.97 | $9.40 | $38.37 |
| LABORER: PIPELAYER (EXCLUDING NATURAL GAS PIPELINE CONSTRUCTION) | $14.00 | $0.00 | $14.00 |
| LABORER: LANDSCAPE | $7.25 | $0.00 | $7.25 |
| ELECTRICIAN | $23.74 | $7.64 | $31.38 |
| CEMENT MASON/CONCRETE FINISHER | $17.08 | $3.14 | $20.22 |
| CARPENTER, INCLUDES FORM WORK | $14.63 | $0.97 | $15.60 |
| TRUCK DRIVER ZONE 2: GROUP 3 | $41.90 | $15.75 | $57.65 |
| TRUCK DRIVER ZONE 2: GROUP 2 | $46.02 | $15.75 | $61.77 |
| TRUCK DRIVER ZONE 2: GROUP 1 | $46.65 | $15.75 | $62.40 |
| TRUCK DRIVER ZONE 1: GROUP 3 | $40.37 | $15.10 | $55.47 |
| TRUCK DRIVER ZONE 1: GROUP 2 | $40.75 | $15.10 | $55.85 |
| TRUCK DRIVER ZONE 1: GROUP 1 | $41.39 | $15.10 | $56.49 |