Heavy construction wages: Summit, Utah
Wage determination UT20260011 · Active · Standard · verify on SAM.gov
Retrieved from wagepin.com/wd/UT20260011 on July 24, 2026 · latest revision 1 · verify at sam.gov/wage-determination/UT20260011/1
Revision history
| Revision | Published | Compare |
|---|---|---|
| rev 1 | 2026-05-18 | diff vs rev 0 |
| rev 0 | 2026-05-17 | original |
Current rates (rev 1)
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| LINE CONSTRUCTION: LINEMAN | $58.83 | $21.21 | $80.04 |
| OPERATOR: POWER EQUIPMENT: (5) ASPHALT ROLLER, BOBCAT/SKID LOADER, FRONT END LOADER(UNDER 2 CU. YDS.), OILER | $36.55 | $18.62 | $55.17 |
| OPERATOR: POWER EQUIPMENT: (4) ASPHALT PAVER, BULLDOZER, FRONT END LOADER(2 TO 5 CU. YDS.), GRADE SETTER, OIL DISTRIBUTOR, SCRAPER | $37.79 | $18.62 | $56.41 |
| OPERATOR: POWER EQUIPMENT: (3) BACKHOE/EXCAVATOR, FRONT END LOADER(OVER 5 CU.YDS.) | $39.01 | $18.62 | $57.63 |
| OPERATOR: POWER EQUIPMENT: (1)MECHANIC-EXCLUDING NATURAL GAS PIPELINE CONSTRUCTION | $41.71 | $18.62 | $60.33 |
| OPERATOR: POWER EQUIPMENT (6) SCREED | $36.55 | $18.62 | $55.17 |
| OPERATOR: POWER EQUIPMENT ((7) ROLLER(DIRT AND GRADE COMPACTION)) | $34.25 | $18.62 | $52.87 |
| OPERATOR: POWER EQUIPMENT ((2A)BLADE/GRADER) | $40.32 | $18.62 | $58.94 |
| OPERATOR: POWER EQUIPMENT: BACKHOE/EXCAVATOR/TRACKHOE, BLADE/GRADER, BOOM, BULLDOZER, MECHANIC: NATURAL GAS PIPELINE CONSTRUCTION ONLY | $35.68 | $17.57 | $53.25 |
| OPERATOR: POWER EQUIPMENT OILER: NATURAL GAS PIPELINE CONSTRUCTION ONLY | $22.03 | $11.88 | $33.91 |
| IRONWORKER | $32.68 | $27.55 | $60.23 |
| LABORER: POT TENDER AND SAND BLASTER: NATURAL GAS PIPELINE CONSTRUCTION ONLY | $20.85 | $8.65 | $29.50 |
| LABORER: COMMON OR GENERAL, PIPELAYER: NATURAL GAS PIPELINE CONSTRUCTION ONLY | $20.59 | $8.65 | $29.24 |
| LABORER: (5)HAND HELD DRILL | $21.65 | $8.65 | $30.30 |
| LABORER: (3) MASON TENDER (CEMENT/CONCRETE), HAND HELD SAW, JACKHAMMER, POWER SAW) | $20.85 | $8.65 | $29.50 |
| LABORER: (1)FLAGGER | $20.59 | $8.65 | $29.24 |
| LABORER: (1) COMMON OR GENERAL: EXCLUDING NATURAL GAS PIPELINE & WATER/SEWER LINE CONSTRUCTION | $20.59 | $8.65 | $29.24 |
| WATER & SEWER LINES: OPERATOR-BACKHOE/EXCAVATOR/TRACKHOE | $15.57 | $0.00 | $15.57 |
| WATER & SEWER LINES: LABORER, COMMON OR GENERAL | $12.81 | $0.00 | $12.81 |
| TRUCK DRIVER (EXCLUDING NATURAL GAS PIPELINE CONSTRUCTION) | $14.40 | $3.99 | $18.39 |
| OPERATOR: TRACKHOE (EXCLUDING NATURAL GAS PIPELINE AND WATER/SEWER LINE CONSTRUCTION) | $19.98 | $0.00 | $19.98 |
| OPERATOR: CRANE | $28.97 | $9.40 | $38.37 |
| LABORER: PIPELAYER (EXCLUDING NATURAL GAS PIPELINE CONSTRUCTION) | $14.00 | $0.00 | $14.00 |
| LABORER: LANDSCAPE | $7.25 | $0.00 | $7.25 |
| ELECTRICIAN | $23.74 | $7.64 | $31.38 |
| CEMENT MASON/CONCRETE FINISHER | $17.08 | $3.14 | $20.22 |
| CARPENTER, INCLUDES FORM WORK | $14.63 | $0.97 | $15.60 |
| TRUCK DRIVER ZONE 2: GROUP 3 | $41.90 | $15.75 | $57.65 |
| TRUCK DRIVER ZONE 2: GROUP 2 | $46.02 | $15.75 | $61.77 |
| TRUCK DRIVER ZONE 2: GROUP 1 | $46.65 | $15.75 | $62.40 |
| TRUCK DRIVER ZONE 1: GROUP 3 | $40.37 | $15.10 | $55.47 |
| TRUCK DRIVER ZONE 1: GROUP 2 | $40.75 | $15.10 | $55.85 |
| TRUCK DRIVER ZONE 1: GROUP 1 | $41.39 | $15.10 | $56.49 |