Building construction wages: Atoka, Bryan, Choctaw, Oklahoma
Wage determination OK20260069 · Active · Standard · verify on SAM.gov
Retrieved from wagepin.com/wd/OK20260069 on · latest revision 1 · verify at sam.gov/wage-determination/OK20260069/1
Revision history
| Revision | Published | Compare |
|---|---|---|
| rev 1 | 2026-05-18 | diff vs rev 0 |
| rev 0 | 2026-05-17 | original |
Current rates (rev 1)
The CSV and the printed sheet are snapshots of rev 1. If DOL revises this determination after you save one, the watch above tells you exactly what moved.
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| BOILERMAKER | $33.70 | $24.41 | $58.11 |
| ELECTRICIAN (CHOCKTAW COUNTY ONLY) | $26.60 | $11.92 | $38.52 |
| ELECTRICIAN: LOW VOLTAGE WIRING, ALARM INSTALLATION AND SOUND AND COMMUNICATIONS SYSTEMS INSTALLATION ONLY (CHOCKTAW COUNTY ONLY) | $26.60 | $11.92 | $38.52 |
| ELECTRICIAN (ATOKA COUNTY ONLY) | $38.38 | $12.89 | $51.27 |
| ELECTRICIAN: LOW VOLTAGE WIRING, ALARM INSTALLATION AND SOUND AND COMMUNICATIONS SYSTEMS INSTALLATION ONLY (ATOKA COUNTY ONLY) | $38.38 | $12.89 | $51.27 |
| ELECTRICIAN (BRYAN COUNTY) | $41.40 | $13.14 | $54.54 |
| ELECTRICIAN: LOW VOLTAGE WIRING, ALARM INSTALLATION AND SOUND AND COMMUNICATIONS SYSTEMS INSTALLATION ONLY (BRYAN COUNTY) | $24.26 | $9.76 | $34.02 |
| POWER EQUIPMENT OPERATOR: GROUP 4 CRANES WITH BOOM INCL. JIB LESS THAN 100 FT AND LESS THAN 3 CU. YD.; OVERHEAD MONORAIL CRANE AND BULLDOZER | $34.07 | $19.05 | $53.12 |
| POWER EQUIPMENT OPERATOR: GROUP 3 ALL CRANE TYPE EQUIPMENT 50 TON CAPACITY AND LARGER, AND LESS THAN 100 TON CAPACITY. CRANE EQUIPMENT (AS RATED BY MFG.) 3 CU. YD. AND OVER GUY DERRICK WHIRLEY POWER DRIVEN HOLE DIGGER (WITH 30' AND LONGER MAST) | $35.40 | $19.05 | $54.45 |
| POWER EQUIPMENT OPERATOR: GROUP 2 ALL CRANE TYPE EQUIPMENT 100 TON CAPACITY AND LARGER CRANES, AND LESS THAN 200 TON CAPACITY | $36.14 | $19.05 | $55.19 |
| POWER EQUIPMENT OPERATOR: GROUP 10 OILER | $27.25 | $19.05 | $46.30 |
| POWER EQUIPMENT OPERATOR: GROUP 1 ALL CRANE TYPE EQUIPMENT 200 TON AND LARGER AND INCLUDING 400 TON CAPACITY CRANES. ALL TOWER CRANES | $38.09 | $19.05 | $57.14 |
| IRONWORKER, STRUCTURAL | $30.35 | $16.83 | $47.18 |
| PLUMBER (EXCLUDES HVAC PIPE INSTALLATION) | $41.00 | $16.03 | $57.03 |
| PIPEFITTER (INCLUDING INSTALLATION OF HVAC ELECTRICAL/TEMPERATURE CONTROLS AND HVAC PIPE INSTALLATION) | $41.00 | $16.03 | $57.03 |
| SHEET METAL WORKER (INCLUDING HVAC DUCT INSTALLATION) | $35.49 | $14.60 | $50.09 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | $21.52 | $6.00 | $27.52 |
| ROOFER | $15.00 | $0.29 | $15.29 |
| PAINTER: BRUSH, ROLLER AND SPRAY | $12.32 | $0.00 | $12.32 |
| OPERATOR: FORKLIFT | $18.02 | $0.00 | $18.02 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $16.83 | $0.00 | $16.83 |
| LABORER: PIPELAYER | $11.65 | $0.00 | $11.65 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $13.04 | $0.00 | $13.04 |
| LABORER: MASON TENDER - BRICK | $12.00 | $0.00 | $12.00 |
| LABORER: COMMON OR GENERAL | $11.43 | $0.00 | $11.43 |
| GLAZIER | $15.27 | $1.46 | $16.73 |
| FORM WORKER | $16.79 | $3.12 | $19.91 |
| FLOOR LAYER (HARDWOOD AND CARPET) | $18.74 | $1.10 | $19.84 |
| CEMENT MASON/CONCRETE FINISHER | $14.50 | $0.00 | $14.50 |
| CARPENTER, EXCLUDES ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, AND FORM WORK | $16.82 | $2.82 | $19.64 |
| CARPENTER (DRYWALL HANGING ONLY) | $14.96 | $0.00 | $14.96 |
| CARPENTER (ACOUSTICAL CEILING INSTALLATION ONLY) | $16.24 | $0.00 | $16.24 |
| BRICKLAYER | $20.00 | $0.00 | $20.00 |
Spot a rate that looks wrong? Email me the details and I’ll check it against the SAM.gov document.