Highway construction wages: Fillmore + 12 more counties, Nebraska
Wage determination NE20260032 · Active · Standard · verify on SAM.gov
Retrieved from wagepin.com/wd/NE20260032 on · latest revision 1 · verify at sam.gov/wage-determination/NE20260032/1
FillmoreJeffersonPolkSalineThayerYorkButlerGageJohnsonNemahaOtoePawneeRichardson
Revision history
| Revision | Published | Compare |
|---|---|---|
| rev 1 | 2026-05-18 | diff vs rev 0 |
| rev 0 | 2026-05-17 | original |
Current rates (rev 1)
The CSV and the printed sheet are snapshots of rev 1. If DOL revises this determination after you save one, the watch above tells you exactly what moved.
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| OPERATOR: TRENCHER | $32.18 | $19.75 | $51.93 |
| TRUCK DRIVER: WATER TRUCK | $13.47 | $0.00 | $13.47 |
| TRUCK DRIVER: SEMI-TRAILER TRUCK | $14.20 | $0.00 | $14.20 |
| TRUCK DRIVER: OIL DISTRIBUTOR TRUCK | $13.25 | $0.00 | $13.25 |
| TRUCK DRIVER: LOWBOY TRUCK | $11.97 | $0.00 | $11.97 |
| TRUCK DRIVER, INCLUDES DUMP AND TANDEM TRUCK (SALINE COUNTY) | $14.20 | $0.00 | $14.20 |
| TRUCK DRIVER, INCLUDES DUMP AND TANDEM TRUCK (BUTLER, FILLMORE, GAGE, JEFFERSON, JOHNSON, NEMAHA, OTOE, PAWNEE, POLK, RICHARSON, THAYER, & YORK COUNTIES) | $13.97 | $0.00 | $13.97 |
| OPERATOR: TRACTOR | $12.45 | $0.00 | $12.45 |
| OPERATOR: SCREED | $12.35 | $0.00 | $12.35 |
| OPERATOR: SCRAPER | $15.23 | $0.00 | $15.23 |
| OPERATOR: ROLLER | $13.02 | $0.00 | $13.02 |
| OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE) | $17.90 | $0.00 | $17.90 |
| OPERATOR: MECHANIC | $14.64 | $0.00 | $14.64 |
| OPERATOR: LOADER | $16.63 | $0.00 | $16.63 |
| OPERATOR: GRADER/BLADE | $15.77 | $0.00 | $15.77 |
| OPERATOR: DISTRIBUTOR | $14.37 | $0.00 | $14.37 |
| OPERATOR: CRANE | $16.17 | $0.00 | $16.17 |
| OPERATOR: COMPACTOR | $10.05 | $0.00 | $10.05 |
| OPERATOR: BULLDOZER | $16.01 | $0.00 | $16.01 |
| OPERATOR: BROOM/SWEEPER | $11.41 | $0.00 | $11.41 |
| OPERATOR: BACKHOE LOADER COMBO | $13.58 | $0.00 | $13.58 |
| OPERATOR: ASPHALT PLANT | $14.09 | $0.00 | $14.09 |
| OPERATING ENGINEERS: (SKID LOADER) | $12.74 | $0.00 | $12.74 |
| LABORER: TRAFFIC CONTROL - FLAGGER AND CONE/BARREL SETTER | $9.00 | $0.00 | $9.00 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $9.75 | $0.00 | $9.75 |
| LABORER: LANDSCAPE & IRRIGATION | $8.30 | $0.00 | $8.30 |
| LABORER: COMMON OR GENERAL, (SALINE COUNTY) | $12.12 | $0.00 | $12.12 |
| LABORER: COMMON OR GENERAL, (BUTLER, FILLMORE, GAGE, JEFFERSON, JOHNSON, NEMAHA, OTOE, PAWNEE, POLK, RICHARDSON, THAYER & YORK COUNTIES) | $11.76 | $0.00 | $11.76 |
| IRONWORKER, REINFORCING | $17.93 | $0.00 | $17.93 |
| FORM WORKER | $11.18 | $0.00 | $11.18 |
| ELECTRICIAN | $20.07 | $0.00 | $20.07 |
| CEMENT MASON/CONCRETE FINISHER | $16.37 | $0.00 | $16.37 |
| CARPENTER, EXCLUDES FORM WORK | $16.39 | $0.00 | $16.39 |
Spot a rate that looks wrong? Email me the details and I’ll check it against the SAM.gov document.