Heavy construction wages: Power, Idaho
Wage determination ID20260072 · Active · Standard · verify on SAM.gov
Retrieved from wagepin.com/wd/ID20260072 on · latest revision 2 · verify at sam.gov/wage-determination/ID20260072/2
Revision history
| Revision | Published | Compare |
|---|---|---|
| rev 2 | 2026-05-18 | diff vs rev 1 |
| rev 1 | 2026-05-17 | diff vs rev 0 |
| rev 0 | 2026-01-30 | original |
Current rates (rev 2)
The CSV and the printed sheet are snapshots of rev 2. If DOL revises this determination after you save one, the watch above tells you exactly what moved.
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| ELECTRICIAN | $40.00 | $18.74 | $58.74 |
| POWER EQUIPMENT OPERATOR: GROUP 8 BULLDOZER, SCRAPER (OVER 80 YDS TO 100 YDS) ZONE PAY: ZONE 1 0 - 30 MILES: FREE ZONE 2 30 - 60 MILES: $30.00/PER DAY ZONE 3 MORE THAN 60 MILES: $35.00/PER DAY. IF A PROJECT IS LOCATED IN MORE THAN ONE ZONE THE LOWER ZONE RATE SHALL APPLY ZONES SHALL BE MEASURED FROM THE THE FOLLOWING U.S. POST OFFICES: BOISE: 304 N. 8TH STREET TWIN FALLS: 253 2ND AVE. WEST POCATELLO: CLARK STREET IDAHO FALLS: 875 NORTH CAPITAL AVE | $37.58 | $16.10 | $53.68 |
| POWER EQUIPMENT OPERATOR: GROUP 7 GRADER (FINE), FRONT END LOADER (OVER 7 YDS), HEAVY DUTY MECHANIC, SCRAPERS (OVER 40 YDS TO 60 YDS) ZONE PAY: ZONE 1 0 - 30 MILES: FREE ZONE 2 30 - 60 MILES: $35.00/PER DAY. IF A PROJECT IS LOCATED IN MORE THAN ONE ZONE THE LOWER ZONE RATE SHALL APPLY ZONES SHALL BE MEASURED FROM THE THE FOLLOWING U.S. POST OFFICES: BOISE: 304 N. 8TH STREET TWIN FALLS: 253 2ND AVE. WEST POCATELLO: CLARK STREET IDAHO FALLS: 875 NORTH CAPITAL AVE | $37.35 | $16.10 | $53.45 |
| POWER EQUIPMENT OPERATOR: GROUP 5 ELEVATING GRADER OPERATOR, BACKHOE (UNDER 3/4 YD) ZONE PAY: ZONE 1 0 - 30 MILES: FREE ZONE 2 30 - 60 MILES: $35.00/PER DAY. IF A PROJECT IS LOCATED IN MORE THAN ONE ZONE THE LOWER ZONE RATE SHALL APPLY ZONES SHALL BE MEASURED FROM THE THE FOLLOWING U.S. POST OFFICES: BOISE: 304 N. 8TH STREET TWIN FALLS: 253 2ND AVE. WEST POCATELLO: CLARK STREET IDAHO FALLS: 875 NORTH CAPITAL AVE | $36.81 | $16.10 | $52.91 |
| POWER EQUIPMENT OPERATOR: GROUP 4 FRONT END LOADER (UP TO 4YD) ZONE PAY: ZONE 1 0 - 30 MILES: FREE ZONE 2 30 - 60 MILES: $30.00/PER DAY ZONE 3 MORE THAN 60 MILES: $35.00/PER DAY. IF A PROJECT IS LOCATED IN MORE THAN ONE ZONE THE LOWER ZONE RATE SHALL APPLY ZONES SHALL BE MEASURED FROM THE THE FOLLOWING U.S. POST OFFICES: WEST POCATELLO: CLARK STREET IDAHO FALLS: 875 NORTH CAPITAL AVE | $36.64 | $16.10 | $52.74 |
| POWER EQUIPMENT OPERATOR: GROUP 10 SCRAPER (OVER 100 YDS) ZONE PAY: ZONE 1 0 - 30 MILES: FREE ZONE 2 30 - 60 MILES: $30.00/PER DAY ZONE 3 MORE THAN 60 MILES: $35.00/PER DAY. IF A PROJECT IS LOCATED IN MORE THAN ONE ZONE THE LOWER ZONE RATE SHALL APPLY ZONES SHALL BE MEASURED FROM THE THE FOLLOWING U.S. POST OFFICES: BOISE: 304 N. 8TH STREET TWIN FALLS: 253 2ND AVE. WEST POCATELLO: CLARK STREET IDAHO FALLS: 875 NORTH CAPITAL AVE | $38.06 | $16.10 | $54.16 |
| POWER EQUIPMENT OPERATOR: BLADE OPERATOR, BACKHOE 3/4 YD-3 1/2 YD), FRONT END LOADER (OVER 4 YDS TO AND INCLUDING 7YDS), OILER, SCRAPER (UP TO AND INCLUDING 40 YDS) ZONE PAY: ZONE 1 0 - 30 MILES: FREE ZONE 2 30 - 60 MILES: $30.00/PER DAY ZONE 3 MORE THAN 60 MILES: $35.00/PER DAY. IF A PROJECT IS LOCATED IN MORE THAN ONE ZONE THE LOWER ZONE RATE SHALL APPLY ZONES SHALL BE MEASURED FROM THE THE FOLLOWING U.S. POST OFFICES: WEST POCATELLO: CLARK STREET IDAHO FALLS: 875 NORTH CAPITAL AVE | $36.98 | $16.10 | $53.08 |
| LABORER: GENERAL OR COMMON ZONE DIFFERENTIAL (ADD TO ZONE 1 RATES): ZONE 2 - $2.00 BASE POINTS: SPOKANE ZONE 1: 0-45 RADIUS MILES FROM THE MAIN POST OFFICE. ZONE 2: 45 RADIUS MILES AND OVER FROM THE MAIN POST OFFICE | $32.15 | $16.30 | $48.45 |
| TRUCK DRIVER: WATER TRUCK | $21.00 | $13.42 | $34.42 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $22.15 | $10.15 | $32.30 |
| LABORER: GRADE CHECKER | $22.68 | $10.90 | $33.58 |
| CEMENT MASON/CONCRETE FINISHER | $22.43 | $15.06 | $37.49 |
| CARPENTER, EXCLUDES FORM WORK | $26.06 | $11.26 | $37.32 |
| CARPENTER (FORM WORK ONLY) | $23.92 | $9.03 | $32.95 |
| TRUCK DRIVER, GROUP 5F DUMP (OVER 100 YDS) | $37.19 | $17.00 | $54.19 |
| TRUCK DRIVER, GROUP 5E DUMP (75-100 YDS) | $36.75 | $17.00 | $53.75 |
| TRUCK DRIVER, GROUP 5D DUMP (50-75 YDS) | $36.12 | $17.00 | $53.12 |
| TRUCK DRIVER, GROUP 5C DUMP (30-50 YDS) | $36.01 | $17.00 | $53.01 |
| TRUCK DRIVER, GROUP 5B DUMP (16-30 YDS) | $35.78 | $17.00 | $52.78 |
| TRUCK DRIVER, GROUP 5A DUMP (0-16 YDS) | $35.60 | $17.00 | $52.60 |
Spot a rate that looks wrong? Email me the details and I’ll check it against the SAM.gov document.