Building SC20260026 rev 1
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| PIPEFITTER | $36.00 | $14.19 | $50.19 |
| TRUCK DRIVER | $14.05 | $3.18 | $17.23 |
| ROOFER | $12.11 | $0.00 | $12.11 |
| PLUMBER | $18.87 | $5.55 | $24.42 |
| PAINTER: BRUSH, ROLLER AND SPRAY | $12.36 | $0.00 | $12.36 |
| OPERATOR: LOADER | $14.18 | $1.99 | $16.17 |
| OPERATOR: GRADER/BLADE | $17.59 | $1.56 | $19.15 |
| OPERATOR: CRANE | $19.39 | $2.02 | $21.41 |
| OPERATOR: BULLDOZER | $17.07 | $2.65 | $19.72 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $17.04 | $0.25 | $17.29 |
| LABORER: PIPELAYER | $14.69 | $2.08 | $16.77 |
| LABORER: MASON TENDER-BRICK/CONCRETE/CEMENT/STONE | $11.00 | $0.00 | $11.00 |
| LABORER: LANDSCAPE | $9.45 | $0.49 | $9.94 |
| LABORER: COMMON OR GENERAL | $9.88 | $1.43 | $11.31 |
| HVAC MECHANIC (HVAC DUCT INSTALLATION ONLY) | $19.36 | $2.62 | $21.98 |
| ELECTRICIAN | $18.15 | $0.00 | $18.15 |
| CEMENT MASON/CONCRETE FINISHER | $14.77 | $0.00 | $14.77 |
| CARPENTER, EXCLUDES DRYWALL HANGING, AND FORM WORK | $17.21 | $3.02 | $20.23 |
| CARPENTER (FORM WORK ONLY) | $14.09 | $2.22 | $16.31 |
| CARPENTER (DRYWALL HANGING ONLY) | $16.32 | $1.50 | $17.82 |
| BRICKLAYER | $18.00 | $0.00 | $18.00 |
Heavy SC20260043 rev 1
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| IRONWORKER, STRUCTURAL | $29.75 | $18.00 | $47.75 |
| TRUCK DRIVER | $13.85 | $2.49 | $16.34 |
| OPERATOR: LOADER | $10.50 | $1.98 | $12.48 |
| OPERATOR: GRADER/BLADE | $20.11 | $1.39 | $21.50 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $15.56 | $2.19 | $17.75 |
| LABORER: PIPELAYER | $12.55 | $1.82 | $14.37 |
| LABORER: COMMON OR GENERAL | $11.56 | $2.53 | $14.09 |
| CARPENTER, INCLUDES FORM WORK | $14.85 | $0.00 | $14.85 |
Highway SC20260034 rev 1
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| TRUCK DRIVER: LOWBOY TRUCK | $15.55 | $0.00 | $15.55 |
| TRUCK DRIVER: DUMP TRUCK | $10.67 | $0.00 | $10.67 |
| LABORER: PIPELAYER | $13.98 | $0.00 | $13.98 |
| LABORER: MASON TENDER-CEMENT/CONCRETE | $10.40 | $0.00 | $10.40 |
| LABORER, TRAFFIC CONTROL-CONE SETTER (HORRY) | $12.63 | $0.00 | $12.63 |
| LABORER, TRAFFIC CONTROL-CONE SETTER (BERKELEY, CHARLESTON, DORECHESTER) | $13.19 | $0.00 | $13.19 |
| LABORER, COMMON OR GENERAL (HORRY) | $9.72 | $0.00 | $9.72 |
| LABORER, COMMON OR GENERAL (DORCHESTER) | $11.69 | $0.00 | $11.69 |
| LABORER, COMMON OR GENERAL (CHARLESTON) | $10.16 | $0.00 | $10.16 |
| LABORER, COMMON OR GENERAL (BERKELEY) | $10.06 | $0.00 | $10.06 |
| LABORER, ASPHALT, INCLUDES ASPHALT DISTRIBUTOR, SHOVELER AND SPREADER (HORRY) | $11.54 | $0.00 | $11.54 |
| LABORER, ASPHALT, INCLUDES ASPHALT DISTRIBUTOR, RAKER, SHOVELER, AND SPREADER (BERKELEY, CHARLESTON, DORCHESTER) | $11.62 | $0.00 | $11.62 |
| LABORER (TRAFFIC CONTROL-FLAGGER) | $11.07 | $0.00 | $11.07 |
| LABORER (LUTEMAN) | $11.61 | $0.00 | $11.61 |
| IRONWORKER, REINFORCING | $15.35 | $0.00 | $15.35 |
| CEMENT MASON/CONCRETE FINISHER (HORRY) | $14.62 | $0.00 | $14.62 |
| CEMENT MASON/CONCRETE FINISHER (CHARLESTON) | $14.33 | $0.00 | $14.33 |
| CEMENT MASON/CONCRETE FINISHER (BERKELEY, DORCHESTER) | $14.79 | $0.00 | $14.79 |
| CARPENTER, FORM WORK ONLY (HORRY) | $14.29 | $0.00 | $14.29 |
| CARPENTER, FORM WORK ONLY (CHARLESTON) | $13.07 | $0.00 | $13.07 |
| CARPENTER, FORM WORK ONLY (BERKELEY, DORCHESTER) | $13.50 | $0.00 | $13.50 |
POWER EQUIPMENT OPERATOR 21 classifications · $11.00 to $24.73 total
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| POWER EQUIPMENT OPERATOR: TRACTOR | $13.28 | $0.00 | $13.28 |
| POWER EQUIPMENT OPERATOR: SCREED | $13.56 | $0.00 | $13.56 |
| POWER EQUIPMENT OPERATOR: SCRAPER | $12.71 | $0.00 | $12.71 |
| POWER EQUIPMENT OPERATOR: PAVER (HORRY) | $13.29 | $0.00 | $13.29 |
| POWER EQUIPMENT OPERATOR: PAVER (BERKELEY, CHARLESTON, DORCHESTER) | $18.85 | $0.00 | $18.85 |
| POWER EQUIPMENT OPERATOR: MECHANIC (HORRY) | $19.48 | $0.00 | $19.48 |
| POWER EQUIPMENT OPERATOR: MECHANIC (CHARLESTON) | $19.21 | $0.00 | $19.21 |
| POWER EQUIPMENT OPERATOR: MECHANIC (BERKELEY, DORCHESTER) | $19.07 | $0.00 | $19.07 |
| POWER EQUIPMENT OPERATOR: GRADER/BLADE | $14.61 | $0.00 | $14.61 |
| POWER EQUIPMENT OPERATOR: CRANE (HORRY) | $20.58 | $0.00 | $20.58 |
| POWER EQUIPMENT OPERATOR: CRANE (CHARLESTON) | $20.08 | $0.00 | $20.08 |
| POWER EQUIPMENT OPERATOR: CRANE (BERKELEY, DORCHESTER) | $20.00 | $4.73 | $24.73 |
| POWER EQUIPMENT OPERATOR: BULLDOZER | $14.81 | $0.00 | $14.81 |
| POWER EQUIPMENT OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE (HORRY) | $15.04 | $0.00 | $15.04 |
| POWER EQUIPMENT OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE (DORCHESTER) | $16.06 | $0.00 | $16.06 |
| POWER EQUIPMENT OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE (CHARLESTON) | $16.09 | $0.00 | $16.09 |
| POWER EQUIPMENT OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE (BERKELEY) | $15.68 | $0.00 | $15.68 |
| POWER EQUIPMENT OPERATOR: (ROLLER) | $15.17 | $0.00 | $15.17 |
| POWER EQUIPMENT OPERATOR: (MILLING MACHINE) | $11.84 | $0.00 | $11.84 |
| POWER EQUIPMENT OPERATOR: (LOADER (FRONT END/TRACK)) | $16.80 | $0.00 | $16.80 |
| POWER EQUIPMENT OPERATOR: (HYDROSEEDER) | $11.00 | $0.00 | $11.00 |
Residential SC20260066 rev 1
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| ROOFER | $15.00 | $0.00 | $15.00 |
| PLUMBER | $16.81 | $0.00 | $16.81 |
| PAINTER (BRUSH AND ROLLER) | $13.49 | $0.00 | $13.49 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $18.85 | $0.00 | $18.85 |
| LABORER: COMMON OR GENERAL | $12.00 | $0.00 | $12.00 |
| ELECTRICIAN | $16.55 | $0.00 | $16.55 |
| CEMENT MASON/CONCRETE FINISHER | $14.69 | $0.00 | $14.69 |
| CARPENTER | $15.00 | $0.00 | $15.00 |