Anson County, North Carolina: Davis-Bacon prevailing wages
Rates from the current active wage determination for each construction type. Click through for revision history and change diffs.
Building NC20260021 rev 1
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| ELECTRICIAN ON SMOKESTACKS WHERE ELECTRICAL WORK PERFORMED IS ABOVE 40 FT. FROM THE GROUND: $0.50 PER HOUR ADDITIONAL. WORK FROM SWINGING SCAFFOLDS, BOSUN CHAIRS, OR RAW STRUCTURAL STEEL: $0.50 PER HOUR ADDITIONAL | $32.31 | $13.66 | $45.97 |
| IRONWORKER, STRUCTURAL | $29.75 | $18.00 | $47.75 |
| PLUMBER/PIPEFITTER (EXCLUDING HVAC SYSTEM INSTALLATION) | $31.66 | $12.69 | $44.35 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | $15.52 | $0.00 | $15.52 |
| SHEET METAL WORKER, EXCLUDES HVAC DUCT INSTALLATION | $15.96 | $1.01 | $16.97 |
| SHEET METAL WORKER (HVAC DUCT INSTALLATION ONLY) | $17.32 | $1.56 | $18.88 |
| ROOFER | $12.50 | $0.81 | $13.31 |
| PAINTER: BRUSH, ROLLER AND SPRAY | $14.13 | $2.88 | $17.01 |
| LABORER: MASON TENDER-BRICK/CEMENT/CONCRETE | $12.00 | $0.00 | $12.00 |
| LABORER: PIPELAYER | $13.35 | $2.80 | $16.15 |
| LABORER: LANDSCAPE & IRRIGATION | $9.13 | $0.28 | $9.41 |
| LABORER: COMMON OR GENERAL | $11.88 | $2.15 | $14.03 |
| HVAC MECHANIC (INSTALLATION OF HVAC UNIT ONLY, EXCLUDES INSTALLATION OF HVAC PIPE AND DUCT) | $17.36 | $2.23 | $19.59 |
| FORM WORKER | $14.09 | $0.00 | $14.09 |
| DRYWALL HANGER | $13.83 | $0.00 | $13.83 |
| CEMENT MASON/CONCRETE FINISHER | $16.41 | $0.00 | $16.41 |
| CARPENTER, EXCLUDES DRYWALL HANGING, AND FORM WORK | $15.57 | $0.00 | $15.57 |
| BRICKLAYER | $19.76 | $9.18 | $28.94 |
OPERATOR 6 classifications · $13.86 to $24.25 total
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| OPERATOR: LOADER | $16.17 | $0.25 | $16.42 |
| OPERATOR: GRADER/BLADE | $15.72 | $1.49 | $17.21 |
| OPERATOR: FORKLIFT | $13.86 | $0.00 | $13.86 |
| OPERATOR: CRANE | $19.77 | $4.48 | $24.25 |
| OPERATOR: BULLDOZER | $16.00 | $1.87 | $17.87 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $16.00 | $2.48 | $18.48 |
Heavy NC20260019 rev 2
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| WELDER (HYDRAULIC DREDGES UNDER 20"). PREMIUMS: ADDITIONAL 20% FOR HAZARDOUS MATERIAL WORK | $9.79 | $1.73 | $11.52 |
| SPILL BARGE OPERATOR (HYDRAULIC DREDGES UNDER 20"). PREMIUMS: ADDITIONAL 20% FOR HAZARDOUS MATERIAL WORK | $8.68 | $1.73 | $10.41 |
| SPIDER BARGE OPERATOR (HYDRAULIC DREDGES UNDER 20").PREMIUMS: ADDITIONAL 20% FOR HAZARDOUS MATERIAL WORK | $8.68 | $1.73 | $10.41 |
| SHOREMAN (HYDRAULIC DREDGES UNDER 20"). PREMIUMS: ADDITIONAL 20% FOR HAZARDOUS MATERIAL WORK | $7.82 | $1.73 | $9.55 |
| OILER & FIREMAN (HYDRAULIC DREDGES UNDER 20") | $8.11 | $1.73 | $9.84 |
| MESSMAN & JANITOR (HYDRAULIC DREDGES UNDER 20"). PREMIUMS: ADDITIONAL 20% FOR HAZARDOUS MATERIAL WORK | $7.53 | $1.73 | $9.26 |
| MESS COOK (HYDRAULIC DREDGES UNDER 20"). PREMIUMS: ADDITIONAL 20% FOR HAZARDOUS MATERIAL WORK | $7.71 | $1.73 | $9.44 |
| MATE (HYDRAULIC DREDGES UNDER 20"). PREMIUMS: ADDITIONAL 20% FOR HAZARDOUS MATERIAL WORK | $8.82 | $1.73 | $10.55 |
| LEVERMAN (HYDRAULIC DREDGES UNDER 20"). PREMIUMS: ADDITIONAL 20% FOR HAZARDOUS MATERIAL WORK | $10.03 | $1.73 | $11.76 |
| LAUNCHMAN (HYDRAULIC DREDGES UNDER 20"). PREMIUMS: ADDITIONAL 20% FOR HAZARDOUS MATERIAL WORK | $8.19 | $1.73 | $9.92 |
| ENGINEER (HYDRAULIC DREDGES UNDER 20"). PREMIUMS: ADDITIONAL 20% FOR HAZARDOUS MATERIAL WORK | $9.59 | $1.73 | $11.32 |
| DECKHAND (HYDRAULIC DREDGES UNDER 20"). PREMIUMS: ADDITIONAL 20% FOR HAZARDOUS MATERIAL WORK | $7.77 | $1.73 | $9.50 |
| COOK (HYDRAULIC DREDGES UNDER 20"). PREMIUMS: ADDITIONAL 20% FOR HAZARDOUS MATERIAL WORK | $8.11 | $1.73 | $9.84 |
| WELDER (HYDRAULIC DREDGES UNDER 20"). PREMIUMS: ADDITIONAL 20% FOR HAZARDOUS MATERIAL WORK | $9.79 | $1.73 | $11.52 |
| SPILL BARGE OPERATOR (HYDRAULIC DREDGES UNDER 20"). PREMIUMS: ADDITIONAL 20% FOR HAZARDOUS MATERIAL WORK | $8.68 | $1.73 | $10.41 |
| SPIDER BARGE OPERATOR (HYDRAULIC DREDGES UNDER 20").PREMIUMS: ADDITIONAL 20% FOR HAZARDOUS MATERIAL WORK | $8.68 | $1.73 | $10.41 |
| SHOREMAN (HYDRAULIC DREDGES UNDER 20"). PREMIUMS: ADDITIONAL 20% FOR HAZARDOUS MATERIAL WORK | $7.82 | $1.73 | $9.55 |
| OILER & FIREMAN (HYDRAULIC DREDGES UNDER 20") | $8.11 | $1.73 | $9.84 |
| MESSMAN & JANITOR (HYDRAULIC DREDGES UNDER 20"). PREMIUMS: ADDITIONAL 20% FOR HAZARDOUS MATERIAL WORK | $7.53 | $1.73 | $9.26 |
| MESS COOK (HYDRAULIC DREDGES UNDER 20"). PREMIUMS: ADDITIONAL 20% FOR HAZARDOUS MATERIAL WORK | $7.71 | $1.73 | $9.44 |
| MATE (HYDRAULIC DREDGES UNDER 20"). PREMIUMS: ADDITIONAL 20% FOR HAZARDOUS MATERIAL WORK | $8.82 | $1.73 | $10.55 |
| LEVERMAN (HYDRAULIC DREDGES UNDER 20"). PREMIUMS: ADDITIONAL 20% FOR HAZARDOUS MATERIAL WORK | $10.03 | $1.73 | $11.76 |
| LAUNCHMAN (HYDRAULIC DREDGES UNDER 20"). PREMIUMS: ADDITIONAL 20% FOR HAZARDOUS MATERIAL WORK | $8.19 | $1.73 | $9.92 |
| ENGINEER (HYDRAULIC DREDGES UNDER 20"). PREMIUMS: ADDITIONAL 20% FOR HAZARDOUS MATERIAL WORK | $9.59 | $1.73 | $11.32 |
| DECKHAND (HYDRAULIC DREDGES UNDER 20"). PREMIUMS: ADDITIONAL 20% FOR HAZARDOUS MATERIAL WORK | $7.77 | $1.73 | $9.50 |
| COOK (HYDRAULIC DREDGES UNDER 20"). PREMIUMS: ADDITIONAL 20% FOR HAZARDOUS MATERIAL WORK | $8.11 | $1.73 | $9.84 |
DREDGING 14 classifications · $45.01 to $63.82 total
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| DREDGING :, HYDRAULIC DREDGES OVER 20":CLASS A1: DECK CAPTAIN, LEVERMAN, MECHANICAL DREDGE OPERATOR. LICENSED TUG OPERATOR OVER 1000 HP. PREMIUMS: ADDITIONAL 20% FOR HAZARDOUS MATERIAL WORK | $48.48 | $15.34 | $63.82 |
| DREDGING :, HYDRAULIC DREDGES OVER 20": CLASS D: SHOREMAN, DECKHAND, RODMAN, SCOWMAN, COOK, MESSMAN, OILER, JANITOR, DRILL OILER. PREMIUMS: ADDITIONAL 20% FOR HAZARDOUS MATERIAL WORK | $30.86 | $14.15 | $45.01 |
| DREDGING :, HYDRAULIC DREDGES OVER 20": CLASS C2: BOAT OPERATOR. PREMIUMS: ADDITIONAL 20% FOR HAZARDOUS MATERIAL WORK | $37.15 | $14.57 | $51.72 |
| DREDGING :, HYDRAULIC DREDGES OVER 20": CLASS C1: MATE, DRAG BARGE OPERATOR, WELDER, ASSISTANT FILL PLACER, STEWARD | $38.38 | $14.66 | $53.04 |
| DREDGING :, HYDRAULIC DREDGES OVER 20": CLASS B2: CERTIFIED WELDER. PREMIUMS: ADDITIONAL 20% FOR HAZARDOUS MATERIAL WORK | $39.46 | $14.73 | $54.19 |
| DREDGING :, HYDRAULIC DREDGES OVER 20": CLASS A2: CRANE OPERATOR (360 SWING) . PREMIUMS: ADDITIONAL 20% FOR HAZARDOUS MATERIAL WORK | $43.20 | $14.99 | $58.19 |
| DREDGING :, HYDRAULIC DREDGES OVER 20": CLASS B1: OPERATOR, TIMBER FORK OPERATOR, DOZER OPERATOR, ENGINEER, BLASTER/DRILLER, FILL PLACER, ELECTRICIAN, LICENSED BOAT OPERATOR, LICENSED CREW BOAT OPERATOR. PREMIUMS: ADDITIONAL 20% FOR HAZARDOUS MATERIAL WORK | $41.93 | $14.90 | $56.83 |
| DREDGING :, HYDRAULIC DREDGES OVER 20":CLASS A1: DECK CAPTAIN, LEVERMAN, MECHANICAL DREDGE OPERATOR. LICENSED TUG OPERATOR OVER 1000 HP. PREMIUMS: ADDITIONAL 20% FOR HAZARDOUS MATERIAL WORK | $48.48 | $15.34 | $63.82 |
| DREDGING :, HYDRAULIC DREDGES OVER 20": CLASS D: SHOREMAN, DECKHAND, RODMAN, SCOWMAN, COOK, MESSMAN, OILER, JANITOR, DRILL OILER. PREMIUMS: ADDITIONAL 20% FOR HAZARDOUS MATERIAL WORK | $30.86 | $14.15 | $45.01 |
| DREDGING :, HYDRAULIC DREDGES OVER 20": CLASS C2: BOAT OPERATOR. PREMIUMS: ADDITIONAL 20% FOR HAZARDOUS MATERIAL WORK | $37.15 | $14.57 | $51.72 |
| DREDGING :, HYDRAULIC DREDGES OVER 20": CLASS C1: MATE, DRAG BARGE OPERATOR, WELDER, ASSISTANT FILL PLACER, STEWARD | $38.38 | $14.66 | $53.04 |
| DREDGING :, HYDRAULIC DREDGES OVER 20": CLASS B2: CERTIFIED WELDER. PREMIUMS: ADDITIONAL 20% FOR HAZARDOUS MATERIAL WORK | $39.46 | $14.73 | $54.19 |
| DREDGING :, HYDRAULIC DREDGES OVER 20": CLASS A2: CRANE OPERATOR (360 SWING) . PREMIUMS: ADDITIONAL 20% FOR HAZARDOUS MATERIAL WORK | $43.20 | $14.99 | $58.19 |
| DREDGING :, HYDRAULIC DREDGES OVER 20": CLASS B1: OPERATOR, TIMBER FORK OPERATOR, DOZER OPERATOR, ENGINEER, BLASTER/DRILLER, FILL PLACER, ELECTRICIAN, LICENSED BOAT OPERATOR, LICENSED CREW BOAT OPERATOR. PREMIUMS: ADDITIONAL 20% FOR HAZARDOUS MATERIAL WORK | $41.93 | $14.90 | $56.83 |
Highway NC20260088 rev 1
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| TRUCK DRIVER (GVWR OF 26,001 LBS OR GREATER) | $13.57 | $0.03 | $13.60 |
| TRUCK DRIVER (GVWR OF 26,000 OR LESS) | $11.45 | $0.00 | $11.45 |
| POWER EQUIPMENT OPERATOR: MILLING MACHINE | $15.22 | $0.00 | $15.22 |
| POWER EQUIPMENT OPERATOR: MECHANIC | $17.51 | $0.00 | $17.51 |
| POWER EQUIPMENT OPERATOR (TACK TRUCK/DISTRIBUTOR OPERATOR) | $14.82 | $0.00 | $14.82 |
| POWER EQUIPMENT OPERATOR (SLIP FORM MACHINE) | $19.60 | $0.00 | $19.60 |
| POWER EQUIPMENT OPERATOR (SCRAPER ROUGH) | $11.50 | $0.00 | $11.50 |
| POWER EQUIPMENT OPERATOR (SCRAPER FINISH) | $12.65 | $0.00 | $12.65 |
| POWER EQUIPMENT OPERATOR (ROLLER OTHER) | $12.08 | $0.00 | $12.08 |
| POWER EQUIPMENT OPERATOR (ROLLER ASPHALT FINISH) | $13.76 | $0.00 | $13.76 |
| POWER EQUIPMENT OPERATOR (ROLLER ASPHALT BREAKDOWN) | $12.79 | $0.00 | $12.79 |
| POWER EQUIPMENT OPERATOR (PAVER CONCRETE) | $18.20 | $0.00 | $18.20 |
| POWER EQUIPMENT OPERATOR (PAVER ASPHPALT) | $15.97 | $0.00 | $15.97 |
| POWER EQUIPMENT OPERATOR (PAVEMENT MARKING EQUIPMENT) | $12.05 | $0.00 | $12.05 |
| POWER EQUIPMENT OPERATOR (OILER/GREASER) | $14.16 | $0.00 | $14.16 |
| POWER EQUIPMENT OPERATOR (OFF-ROAD HAULER/WATER TANKER) | $11.83 | $0.00 | $11.83 |
| POWER EQUIPMENT OPERATOR (MATERIAL TRANSFER VEHICLE (SHUTTLE BUGGY)) | $15.44 | $0.00 | $15.44 |
| POWER EQUIPMENT OPERATOR (LOADER GREATER THAN 2 CUBIC YARDS) | $16.19 | $0.00 | $16.19 |
| POWER EQUIPMENT OPERATOR (LOADER 2 CUBIC YARDS OR LESS) | $13.31 | $0.00 | $13.31 |
| POWER EQUIPMENT OPERATOR (GRADER/BLADE ROUGH) | $15.47 | $0.00 | $15.47 |
| POWER EQUIPMENT OPERATOR (GRADER/BLADE FINE) | $19.84 | $0.00 | $19.84 |
| POWER EQUIPMENT OPERATOR (EXCAVATOR ROUGH) | $13.63 | $0.00 | $13.63 |
| POWER EQUIPMENT OPERATOR (EXCAVATOR FINE) | $16.95 | $0.00 | $16.95 |
| POWER EQUIPMENT OPERATOR (DRILL OPERATOR STRUCTURE) | $20.89 | $0.00 | $20.89 |
| POWER EQUIPMENT OPERATOR (DRILL OPERATOR ROCK) | $14.28 | $0.00 | $14.28 |
| POWER EQUIPMENT OPERATOR (CRANE ROUGH/ALL-TERRAIN) | $19.10 | $0.00 | $19.10 |
| POWER EQUIPMENT OPERATOR (CRANE OTHER) | $19.83 | $0.00 | $19.83 |
| POWER EQUIPMENT OPERATOR (CRANE BOOM TRUCKS) | $18.19 | $0.00 | $18.19 |
| POWER EQUIPMENT OPERATOR (CONCRETE GRINDER/GROOVER) | $17.92 | $0.00 | $17.92 |
| POWER EQUIPMENT OPERATOR (BULLDOZER ROUGH) | $14.36 | $0.00 | $14.36 |
| POWER EQUIPMENT OPERATOR (BULLDOZER FINE) | $16.13 | $0.00 | $16.13 |
| POWER EQUIPMENT OPERATOR (ASPHALT BROOM TRACTOR) | $10.00 | $0.00 | $10.00 |
| PAINTER (BRIDGE) | $23.77 | $0.00 | $23.77 |
| LABORER: PIPELAYER | $12.43 | $0.00 | $12.43 |
| LABORER: COMMON OR GENERAL | $10.40 | $0.01 | $10.41 |
| LABORER (TRAFFIC SIGNAL/LIGHTING INSTALLER) | $15.65 | $0.24 | $15.89 |
| LABORER (GUARDRAIL/FENCE INSTALLER) | $13.22 | $0.00 | $13.22 |
| LABORER (CEMENT MASON/CONCRETE FINISHER TENDER) | $11.04 | $0.00 | $11.04 |
| LABORER (CARPENTER TENDER) | $12.51 | $0.27 | $12.78 |
| LABORER (ASPHALT SCREED/JACKMAN) | $14.50 | $0.00 | $14.50 |
| LABORER (ASPHALT RAKER AND SPREADER) | $12.78 | $0.00 | $12.78 |
| IRONWORKER | $13.30 | $0.00 | $13.30 |
| ELECTRICIAN (TELECOMMUNICATIONS TECHNICIAN) | $15.19 | $1.25 | $16.44 |
| ELECTRICIAN (ELECTRICIAN) | $18.79 | $2.72 | $21.51 |
| CEMENT MASON/CONCRETE FINISHER | $13.93 | $0.00 | $13.93 |
| CARPENTER | $13.68 | $0.05 | $13.73 |
| BLASTER | $18.64 | $0.00 | $18.64 |
Residential NC20260095 rev 1
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| ROOFER | $14.41 | $0.00 | $14.41 |
| PLUMBER | $14.39 | $0.00 | $14.39 |
| PAINTER: SPRAY | $11.91 | $0.00 | $11.91 |
| PAINTER (BRUSH AND ROLLER) | $11.91 | $0.00 | $11.91 |
| LABORER: COMMON OR GENERAL | $11.78 | $0.00 | $11.78 |
| HVAC MECHANIC (HVAC DUCT INSTALLATION ONLY) | $14.11 | $0.00 | $14.11 |
| ELECTRICIAN | $14.61 | $0.00 | $14.61 |
| CEMENT MASON/CONCRETE FINISHER | $15.25 | $0.00 | $15.25 |
| CARPENTER | $14.66 | $0.00 | $14.66 |
Get an email when rates change here
One watch per determination above; every email includes a stop link. Bidding a specific job? Pin it to your bid date instead.