Johnson County, Kansas: Davis-Bacon prevailing wages
Rates from the current active wage determination for each construction type. Click through for revision history and change diffs.
Building KS20260052 rev 1
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR (MECHANICAL (DUCT, PIPE & MECHANICAL SYSTEM INSULATION)) | $45.60 | $35.47 | $81.07 |
| TILE SETTER | $42.73 | $18.39 | $61.12 |
| BRICKLAYER | $43.57 | $23.02 | $66.59 |
| TILE FINISHER | $20.74 | $1.46 | $22.20 |
| CARPENTER (ACOUSTICAL CEILING INSTALLATION ONLY) | $43.28 | $21.25 | $64.53 |
| CARPENTER (EXCLUDES ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING AND FLOOR LAYING CARPET) | $44.63 | $22.40 | $67.03 |
| CARPENTER (FLOOR LAYING-CARPET ONLY) | $40.94 | $21.25 | $62.19 |
| ELECTRICIAN (LOW VOLTAGE WIRING ONLY) | $37.61 | $22.60 | $60.21 |
| ELECTRICIAN (EXCLUDES LOW VOLTAGE WIRING) | $51.01 | $26.25 | $77.26 |
| ELEVATOR MECHANIC A. VACATION PAY: 6% FOR 6 MONTHS TO 5 YEARS SERVICE; 8% WITH 5 OR MORE YEARS OF SERVICE. B. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERANS DAY, THANKSGIVING DAY AND FRIDAY AFTER, AND CHRISTMAS DAY | $60.69 | $38.44 | $99.13 |
| POWER EQUIPMENT OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE) | $45.48 | $22.42 | $67.90 |
| POWER EQUIPMENT OPERATOR: OILER | $39.93 | $22.42 | $62.35 |
| POWER EQUIPMENT OPERATOR: GRADER/BLADE | $45.48 | $22.42 | $67.90 |
| POWER EQUIPMENT OPERATOR: FORKLIFT | $44.14 | $22.42 | $66.56 |
| POWER EQUIPMENT OPERATOR: CRANE | $45.89 | $22.42 | $68.31 |
| POWER EQUIPMENT OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $45.48 | $22.42 | $67.90 |
| POWER EQUIPMENT OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $45.48 | $22.42 | $67.90 |
| IRONWORKER: ORNAMENTAL, REINFORCING AND STRUCTURAL | $39.00 | $34.25 | $73.25 |
| LABORERS: ASPHALT, INCLUDES RAKER, SHOVELER, SPREADER AND DISTRIBUTOR | $31.99 | $16.03 | $48.02 |
| LABORER: COMMON OR GENERAL | $31.60 | $16.95 | $48.55 |
| LABORER: MASON TENDER - BRICK | $32.25 | $16.95 | $49.20 |
| GLAZIER | $39.32 | $22.34 | $61.66 |
| PAINTER: BRUSH, ROLLER, AND SPRAY | $36.18 | $19.97 | $56.15 |
| PAINTER: DRYWALL FINISHING/TAPING | $36.18 | $19.97 | $56.15 |
| CEMENT MASON/CONCRETE FINISHER | $40.13 | $20.50 | $60.63 |
| PLUMBER | $54.28 | $23.79 | $78.07 |
| PIPEFITTER (INCLUDING HVAC PIPE, UNIT, AND INSTALLATION OF HVAC ELECTRICIAL/TEMPERATURE CONTROLS) | $55.56 | $25.80 | $81.36 |
| ROOFER | $38.45 | $22.29 | $60.74 |
| SHEET METAL WORKER (HVAC DUCT INSTALLATION ONLY) | $52.18 | $27.15 | $79.33 |
| SHEET METAL WORKER (EXCLUDES HVAC DUCT INSTALLATION) | $52.18 | $27.15 | $79.33 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | $26.68 | $11.61 | $38.29 |
| PLASTERER | $29.85 | $13.29 | $43.14 |
| OPERATOR: ROLLER | $32.68 | $13.57 | $46.25 |
| OPERATOR: LOADER | $30.35 | $12.04 | $42.39 |
| OPERATOR: BULLDOZER | $33.12 | $13.96 | $47.08 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $17.86 | $1.01 | $18.87 |
| LABORER: LANDSCAPE | $12.48 | $0.00 | $12.48 |
| LABORER: CONCRETE SAW (HAND HELD/WALK BEHIND) | $31.51 | $11.60 | $43.11 |
| CARPENTER (DRYWALL HANGING ONLY) | $30.00 | $1.62 | $31.62 |
| TRUCK DRIVER: LOWBOY TRUCK | $39.89 | $15.85 | $55.74 |
| TRUCK DRIVER: SEMI-TRAILER TRUCK | $39.89 | $15.85 | $55.74 |
| TRUCK DRIVER: DUMP (ALL TYPES) | $39.89 | $15.85 | $55.74 |
Heavy KS20260153 rev 1
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| CARPENTER | $43.28 | $21.25 | $64.53 |
| ELECTRICIAN | $40.64 | $18.29 | $58.93 |
| LINE CONSTRUCTION: LINEMAN | $53.68 | $26.44 | $80.12 |
| POWER EQUIPMENT OPERATOR: ROLLER | $40.17 | $22.29 | $62.46 |
| POWER EQUIPMENT OPERATOR: LOADER | $40.17 | $22.29 | $62.46 |
| POWER EQUIPMENT OPERATOR: GRADER/BLADE | $40.17 | $22.29 | $62.46 |
| POWER EQUIPMENT OPERATOR: FORKLIFT | $40.17 | $22.29 | $62.46 |
| POWER EQUIPMENT OPERATOR: BULLDOZER | $40.17 | $22.29 | $62.46 |
| POWER EQUIPMENT OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $40.17 | $22.29 | $62.46 |
| POWER EQUIPMENT OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $40.17 | $22.29 | $62.46 |
| IRONWORKER | $39.00 | $34.25 | $73.25 |
| LABORER: PIPELAYER | $36.24 | $15.87 | $52.11 |
| CEMENT MASON/CONCRETE FINISHER | $39.06 | $18.71 | $57.77 |
| TRUCK DRIVER: DUMP TRUCK | $32.95 | $19.49 | $52.44 |
| OPERATOR: CRANE | $34.41 | $11.22 | $45.63 |
| LABORER: COMMON OR GENERAL | $28.48 | $16.33 | $44.81 |
| CARPENTER, EXCLUDES FORM WORK | $24.72 | $4.11 | $28.83 |
Highway KS20260140 rev 1
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| OPERATOR: ROTO MILL GROUNDMAN | $18.43 | $0.00 | $18.43 |
| CARPENTER | $43.28 | $21.25 | $64.53 |
| POWER EQUIPMENT OPERATOR: ROTO MILL | $40.17 | $22.29 | $62.46 |
| POWER EQUIPMENT OPERATOR: ROLLER | $40.17 | $22.29 | $62.46 |
| POWER EQUIPMENT OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE) | $40.17 | $22.29 | $62.46 |
| POWER EQUIPMENT OPERATOR: LOADER | $40.17 | $22.29 | $62.46 |
| POWER EQUIPMENT OPERATOR: BROOM/SWEEPER | $40.17 | $22.29 | $62.46 |
| POWER EQUIPMENT OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $40.17 | $22.29 | $62.46 |
| IRONWORKER (REINFORCING AND STRUCTURAL) | $39.00 | $34.25 | $73.25 |
| LABORER: CONCRETE SAW (HAND HELD/WALK BEHIND) | $37.45 | $15.87 | $53.32 |
| LABORER: ASPHALT, INCLUDES RAKER, SHOVELER, SPREADER, AND DISTRIBUTOR | $37.45 | $15.87 | $53.32 |
| CEMENT MASON/CONCRETE FINISHER | $39.06 | $18.71 | $57.77 |
| TRUCK DRIVER: OFF ROAD TRUCK | $19.06 | $0.00 | $19.06 |
| TRUCK DRIVER: FLATBED AND LOWBOY | $28.41 | $14.05 | $42.46 |
| TRUCK DRIVER: DUMP AND TANDEM | $29.04 | $12.45 | $41.49 |
| TRAFFIC SIGNALIZATION: TRAFFIC SIGNAL INSTALLATION (GROUNDMAN) | $17.10 | $0.00 | $17.10 |
| TRAFFIC CONTROL: SERVICE DRIVER | $20.00 | $12.49 | $32.49 |
| OPERATOR: STRIPING MACHINE | $27.27 | $12.25 | $39.52 |
| OPERATOR: TRACTOR | $24.28 | $0.00 | $24.28 |
| OPERATOR: SCREED | $17.38 | $3.52 | $20.90 |
| OPERATOR: SCRAPER | $17.67 | $0.00 | $17.67 |
| OPERATOR: MECHANIC | $32.25 | $15.31 | $47.56 |
| OPERATOR: MATERIAL TRANSFER VEHICLE | $14.65 | $0.00 | $14.65 |
| OPERATOR: GRADER/BLADE | $29.66 | $12.55 | $42.21 |
| OPERATOR: CRANE | $30.38 | $11.08 | $41.46 |
| OPERATOR: CONCRETE SAW | $33.87 | $15.16 | $49.03 |
| OPERATOR: CONCRETE FINISHING MACHINE | $24.26 | $0.00 | $24.26 |
| OPERATOR: BULLDOZER | $28.15 | $11.65 | $39.80 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $34.88 | $15.40 | $50.28 |
| LINE CONSTRUCTION: LINEMAN | $41.52 | $17.26 | $58.78 |
| LINE CONSTRUCTION: GROUNDMAN | $24.92 | $12.15 | $37.07 |
| LINE CONSTRUCTION: EQUIPMENT OPERATOR | $30.67 | $14.36 | $45.03 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $29.75 | $12.83 | $42.58 |
| LABORER: FORM WORK ONLY | $30.21 | $14.57 | $44.78 |
| LABORER: FLAGGER | $13.20 | $0.00 | $13.20 |
| LABORER: COMMON OR GENERAL | $27.81 | $14.30 | $42.11 |
| ELECTRICIAN | $29.93 | $14.14 | $44.07 |
| TRUCK DRIVER: WATER TRUCK | $38.04 | $15.85 | $53.89 |
| LABORER: PIPELAYER | $32.12 | $14.73 | $46.85 |
Residential KS20260006 rev 1
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| ASBESTOS WORKERS/INSULATOR (INCLUDES THE APPLICATION OF ALL INSULATING MATERIALS, PROTECTIVE COVERINGS, COATINGS, AND FINISHINGS TO ALL TYPES OF MECHANICAL SYSTEMS. ALSO THE APPLICATION OF FIRESTOPPING MATERIAL FOR WALL OPENINGS AND PENETRATIONS IN WALLS, FLOORS, CEILINGS AND CURTAIN WALLS.) | $45.60 | $35.47 | $81.07 |
| HAZARDOUS MATERIAL HANDLER (INCLUDES PREPARATION, WETTING, STRIPPING, REMOVAL, SCRAPPING, VACUUMING, BAGGING, AND DISPOSING OF ALL INSULATION MATERIALS FROM MECHANICAL SYSTEMS, WHETHER THEY CONTAIN ASBESTOS OR NOT) | $45.60 | $35.47 | $81.07 |
| BOILERMAKER | $48.00 | $31.08 | $79.08 |
| BRICKLAYER | $29.93 | $10.75 | $40.68 |
| CARPENTER | $35.72 | $22.40 | $58.12 |
| ELECTRICIAN | $48.23 | $25.35 | $73.58 |
| ELEVATOR MECHANIC A. VACATION PAY: 6% FOR 6 MONTHS TO 5 YEARS SERVICE; 8% WITH 5 OR MORE YEARS OF SERVICE. B. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERANS DAY, THANKSGIVING DAY AND FRIDAY AFTER, AND CHRISTMAS DAY | $60.69 | $38.44 | $99.13 |
| POWER EQUIPMENT OPERATORS: GROUP 4: OILERS DRIVER | $40.73 | $22.42 | $63.15 |
| POWER EQUIPMENT OPERATORS: GROUP 4: OILERS | $39.93 | $22.42 | $62.35 |
| POWER EQUIPMENT OPERATORS: GROUP 3 BOILERS - 1; CHIP SPREADER (FRONT MAN); CHURN DRILL OPERATOR; COMPRESSOR MAINTENANCE OPERATOR - 1; CONCRETE SAWS, SELF-PROPELLED; CONVEYOR OPERATOR; DISTRIBUTOR OPERATOR; FINISHING MACHINE OPERATOR; FIREMAN, RIG; FLOAT OPERATOR; FORM GRADER OPERATOR; PUMP; PUMP MAINTENANCE OPERATOR, OTHER THAN DREDGE; ROLLER OPERATOR, OTHER THAN HIGH TYPE ASPHALT; SCREENING AND WASHING PLANT OPERATOR; SELF-PROPELLED STREET BROOM OR SWEEPER; SIPHONS AND JETS; SUB-GRADING MACHINE OPERATOR; TANK CAR HEATER OPERATOR - COMBINATION BOILER AND BOOSTER; TRACTOR, 50 H.P. OR LESS, WITHOUT ATTACHMENTS; VIBRATING MACHINE OPERATOR, NOT HAND; WELDING MACHINE MAINTENANCE OPERATOR - 1 | $44.14 | $22.42 | $66.56 |
| POWER EQUIPMENT OPERATORS: GROUP 2 A-FRAME TRUCK, ASPHALT HOT MIX SILO; ASPHALT PLANT FIREMAN, DRUM OR BOILER; ASPHALT PLANT MIXER OPERATOR; ASPHALT PLANT MAN; ASPHALT ROLLER OPERATOR; BACK FILLER OPERATOR; CHIP SPREADER; CONCRETE BATCH PLANT, DRY-POWER OPERATED; CONCRETE MIXER OPERATOR, SKIP LOADER; CONCRETE PUMP OPERATOR; CRUSHER OPERATOR; ELEVATING GRADER; GREASER; HOISTING ENGINE - 1 DRUM; LATOURNEAU ROOTER; MULTIPLE COMPACTOR; PAVEMENT BREAKER, SELF- PROPELLED, OF THE HYDRAHAMMER OR SIMILAR TYPE; POWER SHIELD; PUG MILL OPERATOR; STUMP CUTTING MACHINE; TOWBOAT OPERATOR, TRACTOR OPERATOR OVER 50 H.P | $45.48 | $22.42 | $67.90 |
| POWER EQUIPMENT OPERATORS: GROUP 1 ASPHALT PAVER AND SPREADER; ASPHALT PLANT CONSOLE OPERATOR; AUTO GRADER; BACKHOE; BLADE OPERATOR, ALL TYPES; BOILERS-2; BOOSTER PUMP ON DREDGE; BORING MACHINE (TRUCK OR CRANE MOUNTED); BULLDOZER OPERATOR; CLAMSHELL OPERATOR; COMPRESSOR MAINTENANCE OPERATOR - 2; CONCRETE MIXER PAVER; CRANE OPERATOR; DERRICK OR DERRICK TRUCKS; DITCHING MACHINE; DRAGLINE OPERATOR; DREDGE ENGINEMAN; DREDGE OPERATOR; DRILLCAT WITH COMPRESSOR MOUNTED ON CAT; DRILLING OR BORING MACHINE, ROTARY, SELF-PROPELLED; HIGH LOADER - FORKLIFT; HOISTLINE ENGINE - 2 ACTIVE DRUMS; LOCOMOTIVE OPERATOR, STANDARD GUAGE; MECHANICS AND WELDERS; MAINTENANCE OPERATOR;MUCKING MACHINE; PILE DRIVER OPERATOR; PITMAN CRANE OPERATOR; PUMP - 2; PUSH CAT OP.; QUAD- TRACK; SCOOP OPERATOR - ALL TYPES; SCOOPS IN TANDEM; SELF- PROPELLED ROTARY DRILL (LEROY OR EQUAL NOT AIR TRAC); SHOVEL OPERATOR; SIDE DISCHARGE SPREADER; SIDEBOOM CATS; SKIMMER SCOOP OPERATOR; SLIP-FORM PAVER (CMI, REX, OR EQUAL); THROTTLE MAN; TRUCK CRANE; WELDING MACHINE MAINTENANCE OPERATOR - 2 | $46.29 | $22.42 | $68.71 |
| IRONWORKER | $39.00 | $34.25 | $73.25 |
| LABORER | $18.70 | $11.01 | $29.71 |
| PAINTERS: SPRAY | $21.10 | $12.50 | $33.60 |
| PAINTERS: DRYWALL FINISHER/TAPER | $21.10 | $12.50 | $33.60 |
| PAINTERS: BRUSH, AND ROLLER | $21.10 | $12.50 | $33.60 |
| GLAZIER | $36.95 | $15.01 | $51.96 |
| SIGN PAINTER A. PAID VACATION: EMPLOYED FOR 1 YEAR BUT LESS THAN 2 YEARS SHALL RECEIVE 1 WEEK VACATION WITH PAY; 2 YEARS OR MORE SHALL RECEIVE 2 WEEKS VACATION WITH PAY; 10 YEARS OF MORE SHALL RECEIVE 3 WEEKS OF VACATION WITH PAY | $17.70 | $4.30 | $22.00 |
| FLOOR LAYER: CARPET | $31.05 | $13.25 | $44.30 |
| CEMENT MASON/CONCRETE FINISHER | $40.13 | $20.50 | $60.63 |
| PLASTERER | $37.92 | $18.83 | $56.75 |
| PLUMBER | $54.28 | $23.79 | $78.07 |
| PIPEFITTER | $55.56 | $25.80 | $81.36 |
| ROOFER | $38.45 | $22.29 | $60.74 |
| SHEET METAL WORKER | $52.18 | $27.15 | $79.33 |
| TRUCK DRIVERS: GROUP 4 MECHANICS. A. PAID VACATION: AN EMPLOYEE WHO HAS WORKED 1300 HRS. OR MORE FOR AN EMPLOYER DURING THE LAST FULL YEAR SHALL RECEIVE 1 WEEK VACATION WITH PAY FOR THAT YEAR | $41.09 | $15.85 | $56.94 |
| TRUCK DRIVERS: GROUP 3 SEMI-TRUCK DRIVER; STEEL TRUCK DRIVER; DISTRIBUTOR TRUCK DRIVERS AND OPERATOR; OILERS AND GREASERS. A. PAID VACATION: AN EMPLOYEE WHO HAS WORKED 1300 HRS. OR MORE FOR AN EMPLOYER DURING THE LAST FULL YEAR SHALL RECEIVE 1 WEEK VACATION WITH PAY FOR THAT YEAR | $39.89 | $15.85 | $55.74 |
| TRUCK DRIVERS: GROUP 2 DOUBLE BOTTOM UNITS (20 TONS CAPACITY AND OVER); FORK TRUCKS; HEAVY EXCAVATING (DUMPSTERS, ETC.); HEAVY HAULING, A-FRAME AND WINCH FORK TRUCKS; HYDRAULICALLY OPERATED AERIAL LIFT; HYDRO LIFT TRUCKS; STRADDLE TRUCKS; WHEEL TRACTORS. 1300 HRS. OR MORE FOR AN EMPLOYER DURING THE LAST FULL YEAR SHALL RECEIVE 1 WEEK VACATION WITH PAY FOR THAT YEAR | $39.89 | $15.85 | $55.74 |
| TRUCK DRIVERS: GROUP 1 FLAT BEDS; PICK-UP; DUMP TRUCKS UNDER 10 YDS.; DUMP TRUCKS 10 YDS. AND OVER. 1300 HRS. OR MORE FOR AN EMPLOYER DURING THE LAST FULL YEAR SHALL RECEIVE 1 WEEK VACATION WITH PAY FOR THAT YEAR | $39.89 | $15.85 | $55.74 |
| TRAFFIC CONTROL SERVICE DRIVER A. PAID HOLIDAYS: NEW YEAR'S DAY, DECORATION DAY, JULY 4TH, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, EMPLOYEE'S BIRTHDAY AND 2 PERSONAL DAYS | $14.15 | $2.44 | $16.59 |