Bibb County, Georgia: Davis-Bacon prevailing wages
Rates from the current active wage determination for each construction type. Click through for revision history and change diffs.
Building GA20260314 rev 2
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR | $33.90 | $18.80 | $52.70 |
| ELECTRICIAN | $32.00 | $14.71 | $46.71 |
| OPERATOR: CRANE | $38.53 | $16.08 | $54.61 |
| OPERATOR: FORKLIFT | $32.93 | $16.08 | $49.01 |
| IRONWORKER: ORNAMENTAL | $32.00 | $15.05 | $47.05 |
| IRONWORKER, STRUCTURAL | $32.00 | $15.05 | $47.05 |
| IRONWORKER: ORNAMENTAL | $32.00 | $15.05 | $47.05 |
| IRONWORKER, STRUCTURAL | $32.00 | $15.05 | $47.05 |
| PIPEFITTER | $38.98 | $17.01 | $55.99 |
| PLUMBER | $38.98 | $17.01 | $55.99 |
| SHEET METAL WORKER | $38.29 | $17.40 | $55.69 |
| PAINTER: SPRAY | $15.67 | $0.00 | $15.67 |
| PAINTER (BRUSH AND ROLLER) | $15.33 | $0.00 | $15.33 |
| OPERATOR: ROLLER | $14.05 | $0.00 | $14.05 |
| OPERATOR: LOADER | $14.86 | $0.00 | $14.86 |
| OPERATOR: GRADER/BLADE | $16.80 | $0.00 | $16.80 |
| OPERATOR: BULLDOZER | $15.23 | $0.00 | $15.23 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $14.88 | $0.00 | $14.88 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $14.24 | $0.00 | $14.24 |
| LABORER: PIPELAYER | $12.55 | $1.90 | $14.45 |
| LABORER: COMMON OR GENERAL | $10.24 | $0.00 | $10.24 |
| CEMENT MASON/CONCRETE FINISHER | $13.12 | $0.00 | $13.12 |
| CARPENTER | $20.69 | $4.48 | $25.17 |
| IRONWORKER: REINFORCING | $31.31 | $17.68 | $48.99 |
Heavy GA20260292 rev 1
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| OPERATOR: ROLLER | $11.89 | $0.00 | $11.89 |
| OPERATOR: LOADER | $14.02 | $0.00 | $14.02 |
| OPERATOR: CRANE | $25.45 | $0.00 | $25.45 |
| OPERATOR: BULLDOZER | $16.29 | $0.00 | $16.29 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $16.40 | $0.00 | $16.40 |
| LABORER: PIPELAYER | $11.53 | $0.00 | $11.53 |
| LABORER: COMMON OR GENERAL | $13.76 | $0.00 | $13.76 |
| ELECTRICIAN | $26.18 | $8.68 | $34.86 |
| CEMENT MASON/CONCRETE FINISHER | $21.40 | $4.25 | $25.65 |
| CARPENTER | $22.36 | $4.19 | $26.55 |
Highway GA20260004 rev 1
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| TRUCK DRIVER: DUMP TRUCK | $21.58 | $3.58 | $25.16 |
| TRAFFIC CONTROL: FLAGGER | $14.64 | $0.00 | $14.64 |
| OPERATOR: ROLLER | $18.51 | $3.99 | $22.50 |
| OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE) | $23.22 | $4.10 | $27.32 |
| OPERATOR: LOADER | $22.81 | $1.91 | $24.72 |
| OPERATOR: GRADER/BLADE | $26.31 | $5.43 | $31.74 |
| OPERATOR: CRANE | $39.31 | $0.00 | $39.31 |
| OPERATOR: BULLDOZER | $22.82 | $0.00 | $22.82 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $23.40 | $3.73 | $27.13 |
| LABORER: PIPELAYER | $22.42 | $0.00 | $22.42 |
| LABORER: COMMON OR GENERAL | $14.00 | $2.45 | $16.45 |
| LABORER: ASPHALT, INCLUDES RAKER, SHOVELER, SPREADER AND DISTRIBUTOR | $16.72 | $2.23 | $18.95 |
| CEMENT MASON/CONCRETE FINISHER | $28.44 | $0.00 | $28.44 |
| CARPENTER | $32.68 | $0.00 | $32.68 |
Residential GA20260027 rev 1
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| SHEET METAL: EXCLUDING HVAC DUCT INSTALLATION: (BUILDINGS OVER 100,000 SQUARE FEET) | $32.60 | $15.52 | $48.12 |
| SHEET META: EXCLUDING HVAC DUCT INSTALLATION (BUILDINGS UP TO 100,000 SQUARE FEET) | $25.49 | $11.73 | $37.22 |
| TRUCK DRIVER | $12.17 | $0.83 | $13.00 |
| ROOFER | $9.47 | $0.00 | $9.47 |
| PLUMBER | $10.86 | $0.00 | $10.86 |
| PAINTER: BRUSH, ROLLER AND SPRAY | $8.63 | $0.00 | $8.63 |
| OPERATOR: EXCAVATOR | $8.96 | $0.00 | $8.96 |
| OPERATOR: BULLDOZER | $13.66 | $3.05 | $16.71 |
| LABORER: MASON TENDER | $8.00 | $0.00 | $8.00 |
| LABORER: COMMON OR GENERAL | $7.25 | $0.00 | $7.25 |
| HVAC MECHANIC (INSTALLATION OF HVAC DUCT) | $11.06 | $0.00 | $11.06 |
| ELECTRICIAN | $13.77 | $0.00 | $13.77 |
| CEMENT MASON/CONCRETE FINISHER | $13.02 | $3.52 | $16.54 |
| CARPENTER, INCLUDING DRYWALL HANGING | $10.00 | $0.00 | $10.00 |
| BRICKLAYER | $13.83 | $0.00 | $13.83 |
| OPERATING ENGINEERS: BACKHOE, COMPACTOR, AND LOADER | $28.32 | $13.45 | $41.77 |
Get an email when rates change here
One watch per determination above; every email includes a stop link. Bidding a specific job? Pin it to your bid date instead.