Heavy construction wages: Tyler, Doddridge, West Virginia
Wage determination WV20260062 · Active · Standard · verify on SAM.gov
Retrieved from wagepin.com/wd/WV20260062 on · latest revision 1 · verify at sam.gov/wage-determination/WV20260062/1
Revision history
| Revision | Published | Compare |
|---|---|---|
| rev 1 | 2026-05-18 | diff vs rev 0 |
| rev 0 | 2026-05-17 | original |
Current rates (rev 1)
The CSV and the printed sheet are snapshots of rev 1. If DOL revises this determination after you save one, the watch above tells you exactly what moved.
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| ELECTRICIAN | $42.20 | $20.39 | $62.59 |
| POWER EQUIPMENT OPERATOR: GROUP 4 OILER | $34.62 | $20.45 | $55.07 |
| POWER EQUIPMENT OPERATOR: GROUP 3 ROLLER | $38.08 | $20.45 | $58.53 |
| POWER EQUIPMENT OPERATOR: GROUP 2 LOADERS UP TO SIX (6) CUBIC YARD CAPACITY, BULLDOZERS, BOBCAT/SKID STEER/SKID LOADER, FORKLIFT, DRILL | $39.19 | $20.45 | $59.64 |
| POWER EQUIPMENT OPERATOR: GROUP 1 CRANES (ALL TYPES), BOOM TRUCKS, LOADERS OF SIX (6) CUBIC YARD CAPACITY AND OVER | $41.95 | $20.45 | $62.40 |
| IRONWORKER, ORNAMENTAL, REINFORCING AND STRUCTURAL | $35.50 | $29.11 | $64.61 |
| LABORER: GROUP 2 FLAGGER | $25.26 | $16.80 | $42.06 |
| LABORER: GROUP 1 CHAIN SAW, CONCRETE WORKER, HAND HELD DRILL, FORM WORK, GRADE CHECKER, SIGNAL MAN | $28.02 | $16.80 | $44.82 |
| CEMENT MASON/CONCRETE FINISHER | $35.77 | $27.54 | $63.31 |
| TRUCK DRIVER: SINGLE AND DOUBLE AXLE DUMP TRUCKS | $23.44 | $12.52 | $35.96 |
| OPERATOR: EXCAVATOR | $24.39 | $15.50 | $39.89 |
| OPERATOR: BACKHOE | $24.39 | $15.50 | $39.89 |
| LABORER: PIPELAYER | $20.42 | $7.80 | $28.22 |
| LABORER: COMMON OR GENERAL | $22.59 | $10.14 | $32.73 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $26.17 | $16.50 | $42.67 |
| POWER EQUIPMENT OPERATOR: MECHANIC | $36.57 | $19.18 | $55.75 |
Spot a rate that looks wrong? Email me the details and I’ll check it against the SAM.gov document.