Building construction wages: Raleigh, West Virginia
Wage determination WV20260023 · Active · Standard · verify on SAM.gov
Retrieved from wagepin.com/wd/WV20260023 on · latest revision 1 · verify at sam.gov/wage-determination/WV20260023/1
Revision history
| Revision | Published | Compare |
|---|---|---|
| rev 1 | 2026-05-18 | diff vs rev 0 |
| rev 0 | 2026-05-17 | original |
Current rates (rev 1)
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR | $38.05 | $30.87 | $68.92 |
| BOILERMAKER | $47.13 | $28.93 | $76.06 |
| BRICK POINTER/CAULKER/CLEANER | $31.65 | $25.56 | $57.21 |
| MASON - STONE | $33.00 | $26.18 | $59.18 |
| CARPENTER (INCLUDING DRYWALL HANGING, FORM WORK, SCAFFOLD BUILDER AND FLOOR LAYING - CARPET, HARDWOOD, RESILIENT AND VINYL) | $33.84 | $25.51 | $59.35 |
| MILLWRIGHT | $37.40 | $26.06 | $63.46 |
| ELECTRICIAN | $42.73 | $23.71 | $66.44 |
| POWER EQUIPMENT OPERATOR: GROUP 4 BOBCAT/SKID STEER/SKID LOADER, ROLLER, OILER | $34.71 | $22.05 | $56.76 |
| POWER EQUIPMENT OPERATOR: GROUP 3 BACKHOE, ALL OTHER CRANES | $45.21 | $22.05 | $67.26 |
| POWER EQUIPMENT OPERATOR: GROUP 2 OPERATING CRANES AND TOWER CRANES WITH A LIFTING CAPACITY OF 15 TONS AND OVER | $46.21 | $22.05 | $68.26 |
| POWER EQUIPMENT OPERATOR: GROUP 1 ALL FRICTION CRANES, TOWER CRANES AND ALL CRANES WITH 180 FT. OR MORE OF BOOM INCLUDING MAST AND JIBS OR LIFTING CAPACITY OF 100 TONS OR MORE AND HOISTS WITH 30,000 POUND LINE PULL OR MORE | $46.56 | $22.05 | $68.61 |
| IRONWORKER: ORNAMENTAL | $35.19 | $25.66 | $60.85 |
| IRONWORKER: STRUCTURAL | $36.10 | $24.65 | $60.75 |
| IRONWORKER: REINFORCING | $36.10 | $24.65 | $60.75 |
| LABORER (WACKER ROLLER OPERATOR) | $28.02 | $16.80 | $44.82 |
| LABORER: GROUP 1 CARPENTER TENDER, COMMON OR GENERAL, DEMOLITION | $22.76 | $16.75 | $39.51 |
| LABORER: ASPHALT RAKER, JACK HAMMER, MOTORIZED BUGGY OPERATOR, WATER BOY | $25.41 | $16.75 | $42.16 |
| PLASTERER | $24.13 | $16.05 | $40.18 |
| PAINTER (DRYWALL FINISHING/TAPING; BRUSH, ROLLER AND SPRAY) | $30.85 | $17.80 | $48.65 |
| GLAZIER | $32.89 | $13.38 | $46.27 |
| LABORER GROUP 2 (Concrete Saw (Hand Held/Walk Behind), Grouting) | $31.97 | $25.36 | $57.33 |
| LABORER GROUP 2 (Airtool Operator, Asbestos Abatement (Removal from Floors, Walls, and Ceiling), Bobcat Operator (Clean up/Demolition), Dewatering, Rodman, Skytrak Forklift Operator) | $34.77 | $26.66 | $61.43 |
| CEMENT MASON/CONCRETE FINISHER | $34.77 | $26.66 | $61.43 |
| LABORER GROUP 2 (Concrete Saw (Hand Held/Walk Behind), Grouting) | $31.97 | $25.36 | $57.33 |
| LABORER GROUP 2 (Airtool Operator, Asbestos Abatement (Removal from Floors, Walls, and Ceiling), Bobcat Operator (Clean up/Demolition), Dewatering, Rodman, Skytrak Forklift Operator) | $34.77 | $26.66 | $61.43 |
| CEMENT MASON/CONCRETE FINISHER | $34.77 | $26.66 | $61.43 |
| CEMENT MASON/CONCRETE FINISHER | $32.52 | $22.34 | $54.86 |
| PLUMBER | $41.00 | $37.63 | $78.63 |
| SHEET METAL WORKER (INCLUDES HVAC DUCT INSTALLATION) | $32.07 | $27.52 | $59.59 |
| TRUCK DRIVER: SINGLE AND DOUBLE AXLE DUMP TRUCKS | $28.52 | $3.00 | $31.52 |
| ROOFER | $24.28 | $9.32 | $33.60 |
| PIPEFITTER, INCLUDES HVAC PIPE INSTALLATION | $27.64 | $18.09 | $45.73 |
| OPERATOR: FORKLIFT | $33.09 | $3.00 | $36.09 |
| OPERATOR: EXCAVATOR | $30.31 | $10.81 | $41.12 |
| OPERATOR: BULLDOZER | $30.24 | $10.26 | $40.50 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $22.05 | $8.54 | $30.59 |
| LABORER: MASON TENDER - BRICK | $21.47 | $8.29 | $29.76 |
| BRICKLAYER | $26.78 | $2.55 | $29.33 |
| LABORER (TAMPER- HAND HELD) | $23.33 | $16.04 | $39.37 |
| LABORER (SCAFFOLD BUILDER) | $23.63 | $16.13 | $39.76 |
| LABORER (PIPELAYER) | $24.06 | $16.31 | $40.37 |
| LABORER (MORTAR MIXING) | $23.35 | $16.07 | $39.42 |
| LABORER (LANDSCAPE) | $22.99 | $16.35 | $39.34 |
| LABORER (GRADE CHECKER) | $22.70 | $16.15 | $38.85 |
| LABORER (CONCRETE WORKER) | $23.57 | $16.19 | $39.76 |
| LABORER (CHIPPING GUNS) | $24.78 | $16.25 | $41.03 |