Heavy construction wages: Kitsap, Washington
Wage determination WA20260126 · Active · Standard · verify on SAM.gov
Retrieved from wagepin.com/wd/WA20260126 on · latest revision 1 · verify at sam.gov/wage-determination/WA20260126/1
Revision history
| Revision | Published | Compare |
|---|---|---|
| rev 1 | 2026-05-18 | diff vs rev 0 |
| rev 0 | 2026-05-17 | original |
Current rates (rev 1)
The CSV and the printed sheet are snapshots of rev 1. If DOL revises this determination after you save one, the watch above tells you exactly what moved.
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| CARPENTER, EXCLUDES FORM WORK | $63.98 | $19.13 | $83.11 |
| ELECTRICIAN | $75.96 | $33.48 | $109.44 |
| TREE TRIMMER: GROUND PERSON | $22.60 | $16.37 | $38.97 |
| TREE TRIMMER | $42.57 | $17.97 | $60.54 |
| OPERATOR: SCRAPER (SELF PROPELLED UNDER 45 YARDS) | $60.14 | $27.57 | $87.71 |
| OPERATOR: OILER (TRUCK CRANE OILER/DRIVER: 100 TONS AND OVER) | $59.49 | $27.57 | $87.06 |
| OPERATOR: OILER (DRILL OILERS: AUGER TYPE, TRUCK OR CRANE MOUNT) | $60.14 | $27.57 | $87.71 |
| OPERATOR: LOADER (OVERHEAD UNDER 6 YARDS; PLANT FEED) | $60.14 | $27.57 | $87.71 |
| OPERATOR: GRADER/BLADE | $60.93 | $27.57 | $88.50 |
| OPERATOR: DRILL (HORIZONTAL/DIRECTIONAL DRILL OPERATOR) | $59.49 | $27.57 | $87.06 |
| OPERATOR: DRILL (HORIZONTAL/DIRECTIONAL DRILL LOCATOR) | $60.14 | $27.57 | $87.71 |
| OPERATOR: DRILL (DRILLING MACHINE) | $61.83 | $27.57 | $89.40 |
| OPERATOR: CONCRETE PUMP | $59.49 | $27.57 | $87.06 |
| OPERATOR: BULLDOZER (D-9 & UNDER) | $59.49 | $27.57 | $87.06 |
| IRONWORKER | $57.94 | $34.52 | $92.46 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $50.38 | $16.96 | $67.34 |
| LABORER: NOZZLE PERSON | $52.31 | $17.01 | $69.32 |
| PAINTER | $41.24 | $14.70 | $55.94 |
| CEMENT MASON/CONCRETE FINISHER | $54.16 | $21.27 | $75.43 |
| TRUCK DRIVER: WATER TRUCK | $31.62 | $16.84 | $48.46 |
| TRUCK DRIVER: DUMP TRUCK | $26.13 | $12.71 | $38.84 |
| TRAFFIC CONTROL: FLAGGER | $35.09 | $0.00 | $35.09 |
| OPERATOR: ROLLER | $46.21 | $12.18 | $58.39 |
| OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE) | $32.35 | $13.44 | $45.79 |
| OPERATOR: MECHANIC | $53.10 | $4.41 | $57.51 |
| OPERATOR: FORKLIFT | $49.89 | $0.00 | $49.89 |
| OPERATOR: CRANE | $42.17 | $17.71 | $59.88 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $51.50 | $0.00 | $51.50 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $51.31 | $4.41 | $55.72 |
| LABORER: FENCE ERECTOR | $29.70 | $0.00 | $29.70 |
| LABORER: PIPELAYER | $39.04 | $10.31 | $49.35 |
| LABORER: HOD CARRIER | $38.58 | $10.89 | $49.47 |
| LABORER: CONCRETE SAW CHAIN | $36.41 | $10.89 | $47.30 |
| LABORER: COMMON OR GENERAL | $38.68 | $0.00 | $38.68 |
| LABORER: ASPHALT, INCLUDES RAKER, SHOVELER, SPREADER AND DISTRIBUTOR | $40.89 | $7.16 | $48.05 |
| FORM WORKER | $48.26 | $14.59 | $62.85 |
| TRUCK DRIVER: ASPHALT MIX | $55.43 | $27.52 | $82.95 |
| GRADE CHECKER | $48.64 | $18.82 | $67.46 |
| TRAFFIC CONTROL: LABORER-CONES/ BARRICADES/BARRELS - SETTER/MOVER/SWEEPER | $39.00 | $14.40 | $53.40 |