Heavy construction wages: Ferry, Garfield, Washington

Wage determination WA20260062 · Active · Standard · verify on SAM.gov

FerryGarfield

Get an email when this determination changes.This determination changed 2 times in the last 12 months, most recently 2026-05-18: 1 rate change, 1 removed (LINE CONSTRUCTION: LINEMEN $60.54 → $60.54).
Substantive rate changes only; no spam. Bidding a specific job? Pin a project instead to lock the revision that applied on your bid date.

Revision history

RevisionPublishedCompare
rev 22026-05-18diff vs rev 1
rev 12026-05-17diff vs rev 0
rev 02026-01-23original

Current rates (rev 2)

Download CSV

The CSV and the printed sheet are snapshots of rev 2. If DOL revises this determination after you save one, the watch above tells you exactly what moved.

ClassificationRateFringeTotal
ELECTRICIAN (FERRY COUNTY)$49.55$19.09$68.64
LINE CONSTRUCTION: LINEMEN$60.54$24.88$85.42
ELECTRICIAN$60.00$27.78$87.78
POWER EQUIPMENT OPERATOR: GROUP 8 CRANES (85 TONS AND OVER, AND ALL CLIMBING, OVERHEAD,RAIL AND TOWER); LOADERS (OVERHEAD AND FRONT-END, 10 YARDS AND OVER) (FERRY COUNTY)$45.36$23.40$68.76
POWER EQUIPMENT OPERATOR: GROUP 7 BACKHOE (OVER 110,000); TRACKHOE/EXCAVATOR (3 YDS & OVER); CRANES (OVER 45 TONS TO BUT NOT INCLUDING 85 TONS); LOADERS (OVERHEAD & FRONT-END, OVER 8 YDS. TO 10 YDS.); GRADER/BLADE (FERRY COUNTY)$43.39$23.40$66.79
POWER EQUIPMENT OPERATOR: GROUP 6 ASPHALT ROLLER; BACKHOE (45,000 GW AND OVER TO 110,000 GW); TRACKHOE/EXCAVATOR (3/4 YD. TO 3 YD.); CRANES (OVER 25 TONS, TO AND INCLUDING 45 TONS), BULLDOZER, 834 R/T & SIMILAR; LOADER OPERATOR (FRONT-END & OVERHEAD, 4 YDS. INCL. 8 YDS.); MECHANIC - (FERRY COUNTY)$43.05$23.40$66.45
POWER EQUIPMENT OPERATOR: GROUP 5 BACKHOE (UNDER 45,000 GW); TRACKHOE/EXCAVATOR (UNDER 3/4 YD.); CRANES (25 TONS & UNDER); DRILLING EQUIPMENT (8 UNCH BIT AND OVER) (ROBBINS, REVERSE CIRCULATION AND SIMILAR); BOOM TRUCK (UNDER 25 TONS) - (FERRY COUNTY)$42.71$23.40$66.11
POWER EQUIPMENT OPERATOR: GROUP 4 LOADERS (OVERHEAD & FRONT-END, UNDER 4 YDS. R/T); OILER; DRILL (CHURN, CORE, CALYX OR DIAMOND) (FERRY COUNTY)$42.51$23.40$65.91
POWER EQUIPMENT OPERATOR: GROUP 3 BULLDOZER (UP TO D-6 OR EQUIVALENT) - (FERRY COUNTY)$42.31$23.40$65.71
POWER EQUIPMENT OPERATOR: GROUP 2 FORK LIFT (FERRY COUNTY)$41.56$23.40$64.96
POWER EQUIPMENT OPERATOR: GROUP 1 ROLLERS, ALL TYPES ON SUBGRADE, INCLUDING SEAL AND CHIP COATINGS - (FERRY COUNTY)$41.17$23.40$64.57
POWER EQUIPMENT OPERATOR: GROUP 8 CRANES (85 TONS AND OVER, AND ALL CLIMBING, OVERHEAD,RAIL AND TOWER); LOADERS (OVERHEAD AND FRONT-END, 10 YARDS AND OVER) - (GARFIELD COUNTY)$42.36$23.40$65.76
POWER EQUIPMENT OPERATOR: GROUP 7 BACKHOE (OVER 110,000); TRACKHOE/EXCAVATOR (3 YDS & OVER); CRANES (OVER 45 TONS TO BUT NOT INCLUDING 85 TONS); LOADERS (OVERHEAD & FRONT-END, OVER 8 YDS. TO 10 YDS.); GRADER/BLADE - (GARFIELD COUNTY)$40.39$23.40$63.79
POWER EQUIPMENT OPERATOR: GROUP 6 ASPHALT ROLLER; BACKHOE (45,000 GW AND OVER TO 110,000 GW); TRACKHOE/EXCAVATOR (3/4 YD. TO 3 YD.); CRANES (OVER 25 TONS, TO AND INCLUDING 45 TONS), BULLDOZER, 834 R/T & SIMILAR; LOADER OPERATOR (FRONT-END & OVERHEAD, 4 YDS. INCL. 8 YDS.); MECHANIC - (GARFIELD COUNTY)$40.05$23.40$63.45
POWER EQUIPMENT OPERATOR: GROUP 5 BACKHOE (UNDER 45,000 GW); TRACKHOE/EXCAVATOR (UNDER 3/4 YD.); CRANES (25 TONS & UNDER); DRILLING EQUIPMENT (8 UNCH BIT AND OVER) (ROBBINS, REVERSE CIRCULATION AND SIMILAR); BOOM TRUCK (UNDER 25 TONS) - (GARFIELD COUNTY)$39.71$23.40$63.11
POWER EQUIPMENT OPERATOR: GROUP 4 LOADERS (OVERHEAD & FRONT-END, UNDER 4 YDS. R/T); OILER; DRILL (CHURN, CORE, CALYX OR DIAMOND) (GARFIELD COUNTY)$39.51$23.40$62.91
POWER EQUIPMENT OPERATOR: GROUP 3 BULLDOZER (UP TO D-6 OR EQUIVALENT) - (GARFIELD COUNTY)$39.31$23.40$62.71
POWER EQUIPMENT OPERATOR: GROUP 1 ROLLERS, ALL TYPES ON SUBGRADE, INCLUDING SEAL AND CHIP COATINGS (GARFIELD COUNTY)$38.17$23.40$61.57
POWER EQUIPMENT OPERATOR: GARFIELD COUNTY$38.56$23.40$61.96
IRONWORKER (REINFORCING AND STRUCTURAL)$43.40$32.77$76.17
LABORER, MASON TENDER BRICK$38.05$16.75$54.80
LABORER: A-1: GROUP 10 GRADE CHECKER - (GARFIELD COUNTY)$40.21$16.90$57.11
LABORER: A-1: GROUP 3 CEMENT/CONCRETE; PIPELAYER; CHIPPING GUNS - (GARFIELD COUNTY)$37.46$16.90$54.36
LABORER: A-1: GROUP 2 COMMON OR GENERAL LABORER (GARFIELD COUNTY)$37.13$16.90$54.03
LABORER: A-1: GROUP 1 FLAGGER - (GARFIELD COUNTY)$34.03$16.90$50.93
LABORER: A-2: GROUP 10 GRADE CHECKER - (FERRY COUNTY)$43.21$16.90$60.11
LABORER: A-2: GROUP 3 CEMENT/CONCRETE; PIPELAYER; CHIPPING GUNS - (FERRY COUNTY)$40.46$16.90$57.36
LABORER: A-2: GROUP 2 COMMON OR GENERAL LABORER - (FERRY COUNTY)$40.13$16.90$57.03
LABORER: A-2: GROUP 1 FLAGGER - (FERRY COUNTY)$37.03$16.90$53.93
PAINTER (BRUSH, ROLLER, AND SPRAY.)$36.26$17.01$53.27
TRUCK DRIVER: 10 YARD TRUCK$24.61$8.34$32.95
TRUCK DRIVER: WATER TRUCK$24.36$8.30$32.66
TRUCK DRIVER: DUMP TRUCK$19.67$0.00$19.67
LABORER: LANDSCAPE$14.67$0.00$14.67
CEMENT MASON/CONCRETE FINISHER$17.21$0.00$17.21
CARPENTER$24.03$6.50$30.53

Spot a rate that looks wrong? Email me the details and I’ll check it against the SAM.gov document.