Building construction wages: Okanogan, Washington

Wage determination WA20260035 · Active · Standard · verify on SAM.gov

Okanogan

Get an email when this determination changes.This determination changed once in the last 12 months, most recently 2026-05-17: 8 rate changes (POWER EQUIPMENT OPERATOR - GROUP 8 $42.88 → $45.36).
Substantive rate changes only; no spam. Bidding a specific job? Pin a project instead to lock the revision that applied on your bid date.

Revision history

RevisionPublishedCompare
rev 22026-05-18diff vs rev 1
rev 12026-05-17diff vs rev 0
rev 02026-01-23original

Current rates (rev 2)

Download CSV

The CSV and the printed sheet are snapshots of rev 2. If DOL revises this determination after you save one, the watch above tells you exactly what moved.

ClassificationRateFringeTotal
BRICKLAYER$33.95$19.33$53.28
TILE SETTER$29.86$13.95$43.81
CARPENTER (DRYWALL HANGING AND FORM WORK ONLY)$44.21$17.28$61.49
ELECTRICIAN$46.15$26.10$72.25
POWER EQUIPMENT OPERATOR: GROUP 4 ROLLER-OTHER THAN PLANT MIX; FORKLIFT: UNDER 3000 LBS WITH ATTACHMENTS (COUNTY WHICH LIES WEST OF THE 120TH MERIDIAN)$55.43$27.57$83.00
POWER EQUIPMENT OPERATOR: GROUP 3 CRANES-THRU 19 TONS WITH ATTACHMENTS; DOZERS-D-9 AND UNDER; ROLLER-PLANT MIX; EXCAVATOR/TRACKHOE, BACKHOE: UNDER 15 METRIC TONS; FORKLIFT: 3000 LBS AND OVER WITH ATTACHMENTS (COUNTY WHICH LIES WEST OF THE 120TH MERIDIAN)$59.23$27.57$86.80
POWER EQUIPMENT OPERATOR: GROUP 2 CRANES, 20 TONS THRU 44 TONS WITH ATTACHMENTS; EXCAVATOR/TRACKHOE, BACKHOE: 15 TO 30 METRIC TONS; LOADERS-OVERHEAD UNDER 6 YARDS; MECHANIC (COUNTY WHICH LIES WEST OF THE 120TH MERIDIAN)$59.88$27.57$87.45
POWER EQUIPMENT OPERATOR: GROUP 1 CRANES 45 TONS THRU 99 TONS, UNDER 150 FT OF BOOM (INCLUDING JIB WITH ATTACHMENTS); EXCAVATOR/TRACKHOE, BACKHOES: OVER 30 METRIC TONS TO 50 METRIC TONS; LOADER- OVERHEAD 6 YARDS TO, BUT NOT INCLUDING 8 YARDS; DOZER D-10 (COUNTY WHICH LIES WEST OF THE 120TH MERIDIAN)$60.67$27.57$88.24
POWER EQUIPMENT OPERATOR: GROUP 1AAA CRANES-OVER 300 TONS, OR 300 FT OF BOOM (INCLUDING JIB WITH ATTACHMENTS) (COUNTY WHICH LIES WEST OF THE 120TH MERIDIAN)$63.35$27.57$90.92
POWER EQUIPMENT OPERATOR: GROUP 1AA CRANES 200 TO 300 TONS, OR 250 FT OF BOOM (INCLUDING JIB WITH ATTACHMENTS); EXCAVATOR/TRACKHOE, BACKHOES: OVER 90 METRIC TONS (COUNTY WHICH LIES WEST OF THE 120TH MERIDIAN)$62.47$27.57$90.04
POWER EQUIPMENT OPERATOR: GROUP 1A CRANES, 100 TONS THRU 199 TONS, OR 150 FT OF BOOM (INCLUDING JIB WITH ATTACHMENTS); LOADERS-OVERHEAD, 8 YARDS AND OVER; EXCAVATOR/TRACKHOE, BACKHOES: OVER 50 METRIC TONS TO 90 METRIC TONS (COUNTY WHICH LIES WEST OF THE 120TH MERIDIAN)$61.56$27.57$89.13
POWER EQUIPMENT OPERATOR: GROUP 8 CRANES (85 TONS AND OVER, AND ALL CLIMBING, OVERHEAD,RAIL AND TOWER); LOADERS (OVERHEAD AND FRONT-END, 10 YARDS AND OVER) (OKANOGAN COUNTY WHICH LIES EAST OF THE 120TH MERIDIAN)$45.36$23.40$68.76
POWER EQUIPMENT OPERATOR: GROUP 7 BACKHOE (OVER 110,000); TRACKHOE/EXCAVATOR (3 YDS & OVER); CRANES (OVER 45 TONS TO BUT NOT INCLUDING 85 TONS); LOADERS (OVERHEAD & FRONT-END, OVER 8 YDS. TO 10 YDS.) (OKANOGAN COUNTY WHICH LIES EAST OF THE 120TH MERIDIAN)$43.39$23.40$66.79
POWER EQUIPMENT OPERATOR: GROUP 6 ASPHALT ROLLER; BACKHOE (45,000 GW AND OVER TO 110,000 GW); TRACKHOE/EXCAVATOR (3/4 YD. TO 3 YD.); CRANES (OVER 25 TONS, TO AND INCLUDING 45 TONS), BULLDOZER, 834 R/T & SIMILAR; LOADER OPERATOR (FRONT-END & OVERHEAD, 4 YDS. INCL. 8 YDS.); MECHANIC (OKANOGAN COUNTY WHICH LIES EAST OF THE 120TH MERIDIAN)$43.05$23.40$66.45
POWER EQUIPMENT OPERATOR: GROUP 5 BACKHOE (UNDER 45,000 GW); TRACKHOE/EXCAVATOR (UNDER 3/4 YD.); CRANES (25 TONS & UNDER) (OKANOGAN COUNTY WHICH LIES EAST OF THE 120TH MERIDIAN)$42.71$23.40$66.11
POWER EQUIPMENT OPERATOR: GROUP 4 LOADERS (OVERHEAD & FRONT-END, UNDER 4 YDS. R/T) (OKANOGAN COUNTY WHICH LIES EAST OF THE 120TH MERIDIAN)$42.51$23.40$65.91
POWER EQUIPMENT OPERATOR: GROUP 3 BULLDOZER (UP TO D-6 OR EQUIVALENT) (OKANOGAN COUNTY WHICH LIES EAST OF THE 120TH MERIDIAN)$42.31$23.40$65.71
POWER EQUIPMENT OPERATOR: GROUP 2 FORK LIFT (OKANOGAN COUNTY WHICH LIES EAST OF THE 120TH MERIDIAN)$41.56$23.40$64.96
POWER EQUIPMENT OPERATOR: GROUP 1 ROLLERS, ALL TYPES ON SUBGRADE, INCLUDING SEAL AND CHIP COATINGS (OKANOGAN COUNTY WHICH LIES EAST OF THE 120TH MERIDIAN)$41.17$23.40$64.57
IRONWORKER: ORNAMENTAL, REINFORCING AND STRUCTURAL$43.40$32.77$76.17
LABORER, MASON TENDER BRICK$38.05$16.75$54.80
LABORER: A-2: GROUP 10 GRADE CHECKER$43.21$16.90$60.11
LABORER: A-2: GROUP 3 CEMENT/CONCRETE; PIPELAYER$40.46$16.90$57.36
LABORER: A-2: GROUP 2 COMMON OR GENERAL LABORER$40.13$16.90$57.03
PAINTER (BRUSH & SPRAY ONLY)$33.95$15.65$49.60
CEMENT MASON/CONCRETE FINISHER: ZONE DIFFERENTIAL (ADD TO ZONE 1 RATES): ZONE 2 - $3.00 BASE POINTS: SPOKANE, PASCO, LEWISTON, WENATCHEE ZONE 1: 0 - 45 RADIUS MILES FROM THE MAIN POST OFFICE ZONE 2: 45 RADIUS MILES FROM THE MAIN POST OFFICE$40.89$18.64$59.53
PIPEFITTER (OKANOGAN COUNTY WHICH LIES WEST OF THE 120TH MERIDIAN)$75.21$33.88$109.09
PIPEFITTER (OKANOGAN COUNTY WHICH LIES EAST OF THE 120TH MERIDIAN)$65.20$34.91$100.11
ROOFER (INCLUDES ROOF TEAR OFF, WATERPROOFING, AND INSTALLATION OF METAL ROOFS)$35.75$14.40$50.15
SPRINKLER FITTER (FIRE SPRINKLERS)$44.30$28.58$72.88
SHEETMETAL WORKER (INCLUDING HVAC DUCT INSTALLATION)$45.83$27.92$73.75
TRUCK DRIVER, INCLUDES DUMP TRUCK$23.50$6.87$30.37
PLUMBER$35.00$0.00$35.00
PIPE INSULATOR/WRAPPER$24.21$4.07$28.28
PAINTER: ROLLER$22.06$2.72$24.78
PAINTER: DRYWALL FINISHING/TAPING$25.17$4.41$29.58
OPERATOR: BOBCAT/SKID STEER/SKID LOADER$27.94$0.00$27.94
METAL BUILDING ERECTOR$11.30$3.58$14.88
CARPENTER, EXCLUDES DRYWALL HANGING, AND FORM WORK$23.81$2.91$26.72

Spot a rate that looks wrong? Email me the details and I’ll check it against the SAM.gov document.