Building construction wages: Grays Harbor, Washington

Wage determination WA20260027 · Active · Standard · verify on SAM.gov

Grays Harbor

Get an email when this determination changes.No substantive rate changes here in the last 12 months. The watch exists for the day that changes.
Substantive rate changes only; no spam. Bidding a specific job? Pin a project instead to lock the revision that applied on your bid date.

Revision history

RevisionPublishedCompare
rev 12026-05-18diff vs rev 0
rev 02026-05-17original

Current rates (rev 1)

Download CSV

The CSV and the printed sheet are snapshots of rev 1. If DOL revises this determination after you save one, the watch above tells you exactly what moved.

ClassificationRateFringeTotal
ASBESTOS WORKER/HEAT & FROST INSULATOR (PIPE INSULATION)$75.37$18.82$94.19
BRICKLAYER$55.34$20.05$75.39
TILE SETTER$49.70$18.62$68.32
TILE FINISHER$40.98$18.17$59.15
MILLWRIGHT$55.39$22.38$77.77
CARPENTER (INCLUDES ACOUSTICAL CEILING MECHANIC, DRYWALL HANGER & FORM WORK)$63.98$19.13$83.11
ELECTRICIAN$65.14$26.56$91.70
POWER EQUIPMENT OPERATORS: GROUP 1AAA Cranes-over 300 tons, or 300 ft of boom (including jib with attachments)$63.35$27.57$90.92
POWER EQUIPMENT OPERATOR: GROUP 4 ROLLER-OTHER THAN PLANT MIX; FORKLIFT: UNDER 3000 LBS WITH ATTACHMENTS$55.43$27.57$83.00
POWER EQUIPMENT OPERATOR: GROUP 3 DOZERS-D-9 AND UNDER; ROLLER-PLANT MIX; EXCAVATOR/TRACKHOE, BACKHOE: UNDER 15 METRIC TONS; FORKLIFT: 3000 LBS AND OVER WITH ATTACHMENTS$59.23$27.57$86.80
POWER EQUIPMENT OPERATOR: GROUP 2 EXCAVATOR/TRACKHOE, BACKHOE: 15 TO 30 METRIC TONS; LOADERS-OVERHEAD UNDER 6 YARDS; MECHANIC$59.88$27.57$87.45
POWER EQUIPMENT OPERATOR: GROUP 1 EXCAVATOR/TRACKHOE, BACKHOES: OVER 30 METRIC TONS TO 50 METRIC TONS; LOADER- OVERHEAD 6 YARDS TO, BUT NOT INCLUDING 8 YARDS; DOZER D-10$60.67$27.57$88.24
POWER EQUIPMENT OPERATOR: GROUP 1AA EXCAVATOR/TRACKHOE, BACKHOES: OVER 90 METRIC TONS$62.47$27.57$90.04
POWER EQUIPMENT OPERATOR: GROUP 1A LOADERS-OVERHEAD, 8 YARDS AND OVER; EXCAVATOR/TRACKHOE, BACKHOES: OVER 50 METRIC TONS TO 90 METRIC TONS$61.56$27.57$89.13
IRONWORKER (REINFORCING, STRUCTURAL AND ORNAMENTAL)$57.94$34.52$92.46
LABORER: ZONE 1: GROUP 5 MASON TENDER-BRICK; MASON TENDER-CEMENT/CONCRETE; GRADE CHECKER ZONE DIFFERENTIAL (ADD TO ZONE 1 RATES): ZONE 2 - $1.00 ZONE 3 - $1.30 BASE POINTS: BELLINGHAM, MT. VERNON, EVERETT, SEATTLE, KENT, TACOMA, OLYMPIA, CENTRALIA, ABERDEEN, SHELTON, PT. TOWNSEND, PT. ANGELES, AND BREMERTON ZONE 1 - PROJECTS WITHIN 25 RADIUS MILES OF THE RESPECTIVE CITY HALL ZONE 2 - MORE THAN 25 BUT LESS THAN 45 RADIUS MILES FROM THE RESPECTIVE CITY HALL ZONE 3 - MORE THAN 45 RADIUS MILES FROM THE RESPECTIVE CITY HALL$52.31$17.01$69.32
LABORER: ZONE 1: GROUP 4 PIPE LAYER ZONE DIFFERENTIAL (ADD TO ZONE 1 RATES): ZONE 2 - $1.00 ZONE 3 - $1.30 BASE POINTS: BELLINGHAM, MT. VERNON, EVERETT, SEATTLE, KENT, TACOMA, OLYMPIA, CENTRALIA, ABERDEEN, SHELTON, PT. TOWNSEND, PT. ANGELES, AND BREMERTON ZONE 1 - PROJECTS WITHIN 25 RADIUS MILES OF THE RESPECTIVE CITY HALL ZONE 2 - MORE THAN 25 BUT LESS THAN 45 RADIUS MILES FROM THE RESPECTIVE CITY HALL ZONE 3 - MORE THAN 45 RADIUS MILES FROM THE RESPECTIVE CITY HALL$51.52$16.99$68.51
LABORER: ZONE 1: GROUP 3 GENERAL OR COMMON LABORER ZONE DIFFERENTIAL (ADD TO ZONE 1 RATES): ZONE 2 - $1.00 ZONE 3 - $1.30 BASE POINTS: BELLINGHAM, MT. VERNON, EVERETT, SEATTLE, KENT, TACOMA, OLYMPIA, CENTRALIA, ABERDEEN, SHELTON, PT. TOWNSEND, PT. ANGELES, AND BREMERTON ZONE 1 - PROJECTS WITHIN 25 RADIUS MILES OF THE RESPECTIVE CITY HALL ZONE 2 - MORE THAN 25 BUT LESS THAN 45 RADIUS MILES FROM THE RESPECTIVE CITY HALL ZONE 3 - MORE THAN 45 RADIUS MILES FROM THE RESPECTIVE CITY HALL$50.38$16.96$67.34
GLAZIER$61.14$23.76$84.90
PAINTER (BRUSH AND ROLLER, EXCLUDES SPRAY AND DRYWALL FINISHING/TAPING)$41.24$14.70$55.94
SOFT FLOOR LAYER (INCLUDING VINYL AND CARPET)$42.01$20.20$62.21
CEMENT MASON/CONCRETE FINISHER$54.16$21.27$75.43
PIPEFITTER$60.72$34.15$94.87
ROOFER (INCLUDES ROOF TEAR OFF, WATERPROOFING, AND INSTALLATION OF METAL ROOFS)$47.98$16.47$64.45
SPRINKLER FITTER (FIRE SPRINKLERS)$44.13$26.40$70.53
SHEET METAL WORKER (HVAC DUCT WORK ONLY)$69.86$33.39$103.25
TRUCK DRIVER: DUMP TRUCK$23.50$6.87$30.37
SHEET METAL WORKER, EXCLUDES HVAC DUCT INSTALLATION$24.83$0.00$24.83
PLUMBER$35.00$0.00$35.00
PAINTER: SPRAY$17.80$4.18$21.98
PAINTER: DRYWALL FINISHING/TAPING$29.90$0.00$29.90
OPERATOR: CRANE$30.40$0.00$30.40
OPERATOR: BOBCAT/SKID STEER/SKID LOADER$27.94$0.00$27.94

Spot a rate that looks wrong? Email me the details and I’ll check it against the SAM.gov document.