Current rates (rev 1)
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR (PIPE INSULATION) | $75.37 | $18.82 | $94.19 |
| BRICKLAYER | $55.34 | $20.05 | $75.39 |
| TILE SETTER | $49.70 | $18.62 | $68.32 |
| TILE FINISHER | $40.98 | $18.17 | $59.15 |
| MILLWRIGHT | $55.39 | $22.38 | $77.77 |
| CARPENTER (INCLUDES ACOUSTICAL CEILING MECHANIC, DRYWALL HANGER & FORM WORK) | $63.98 | $19.13 | $83.11 |
| ELECTRICIAN | $65.14 | $26.56 | $91.70 |
| POWER EQUIPMENT OPERATORS: GROUP 1AAA Cranes-over 300 tons, or 300 ft of boom (including jib with attachments) | $63.35 | $27.57 | $90.92 |
| POWER EQUIPMENT OPERATOR: GROUP 4 ROLLER-OTHER THAN PLANT MIX; FORKLIFT: UNDER 3000 LBS WITH ATTACHMENTS | $55.43 | $27.57 | $83.00 |
| POWER EQUIPMENT OPERATOR: GROUP 3 DOZERS-D-9 AND UNDER; ROLLER-PLANT MIX; EXCAVATOR/TRACKHOE, BACKHOE: UNDER 15 METRIC TONS; FORKLIFT: 3000 LBS AND OVER WITH ATTACHMENTS | $59.23 | $27.57 | $86.80 |
| POWER EQUIPMENT OPERATOR: GROUP 2 EXCAVATOR/TRACKHOE, BACKHOE: 15 TO 30 METRIC TONS; LOADERS-OVERHEAD UNDER 6 YARDS; MECHANIC | $59.88 | $27.57 | $87.45 |
| POWER EQUIPMENT OPERATOR: GROUP 1 EXCAVATOR/TRACKHOE, BACKHOES: OVER 30 METRIC TONS TO 50 METRIC TONS; LOADER- OVERHEAD 6 YARDS TO, BUT NOT INCLUDING 8 YARDS; DOZER D-10 | $60.67 | $27.57 | $88.24 |
| POWER EQUIPMENT OPERATOR: GROUP 1AA EXCAVATOR/TRACKHOE, BACKHOES: OVER 90 METRIC TONS | $62.47 | $27.57 | $90.04 |
| POWER EQUIPMENT OPERATOR: GROUP 1A LOADERS-OVERHEAD, 8 YARDS AND OVER; EXCAVATOR/TRACKHOE, BACKHOES: OVER 50 METRIC TONS TO 90 METRIC TONS | $61.56 | $27.57 | $89.13 |
| IRONWORKER (REINFORCING, STRUCTURAL AND ORNAMENTAL) | $57.94 | $34.52 | $92.46 |
| DIFFERENTIAL (ADD TO ZONE 1 RATES): ZONE 2 - $1.00 VERNON, EVERETT, SEATTLE, KENT, TACOMA, OLYMPIA, CENTRALIA, ABERDEEN, SHELTON, PT. TOWNSEND, PT. ANGELES, AND BREMERTON ZONE 1 - PROJECTS WITHIN 25 RADIUS MILES OF THE RESPECTIVE CITY HALL ZONE 2 - MORE THAN 25 BUT LESS THAN 45 RADIUS MILES FROM THE RESPECTIVE CITY HALL ZONE 3 - MORE THAN 45 RADIUS MILES FROM THE RESPECTIVE CITY HALL | $52.31 | $17.01 | $69.32 |
| ZONE 2 - $1.00 ZONE 3 - $1.30 BASE POINTS: BELLINGHAM, MT. VERNON, EVERETT, SEATTLE, KENT, TACOMA, OLYMPIA, CENTRALIA, ABERDEEN, SHELTON, PT. TOWNSEND, PT. ANGELES, AND BREMERTON ZONE 1 - PROJECTS WITHIN 25 RADIUS MILES OF THE RESPECTIVE CITY HALL ZONE 2 - MORE THAN 25 BUT LESS THAN 45 RADIUS MILES FROM THE RESPECTIVE CITY HALL ZONE 3 - MORE THAN 45 RADIUS MILES FROM THE RESPECTIVE CITY HALL | $51.52 | $16.99 | $68.51 |
| 1 RATES): ZONE 2 - $1.00 ZONE 3 - $1.30 BASE POINTS: BELLINGHAM, MT. VERNON, EVERETT, SEATTLE, KENT, TACOMA, OLYMPIA, CENTRALIA, ABERDEEN, SHELTON, PT. TOWNSEND, PT. ANGELES, AND BREMERTON RESPECTIVE CITY HALL ZONE 2 - MORE THAN 25 BUT LESS THAN 45 RADIUS MILES FROM THE RESPECTIVE CITY HALL ZONE 3 - MORE THAN 45 RADIUS MILES FROM THE RESPECTIVE CITY HALL | $50.38 | $16.96 | $67.34 |
| GLAZIER | $61.14 | $23.76 | $84.90 |
| PAINTER (BRUSH AND ROLLER, EXCLUDES SPRAY AND DRYWALL FINISHING/TAPING) | $41.24 | $14.70 | $55.94 |
| SOFT FLOOR LAYER (INCLUDING VINYL AND CARPET) | $42.01 | $20.20 | $62.21 |
| CEMENT MASON/CONCRETE FINISHER | $54.16 | $21.27 | $75.43 |
| PIPEFITTER | $60.72 | $34.15 | $94.87 |
| ROOFER (INCLUDES ROOF TEAR OFF, WATERPROOFING, AND INSTALLATION OF METAL ROOFS) | $47.98 | $16.47 | $64.45 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | $44.13 | $26.40 | $70.53 |
| SHEET METAL WORKER (HVAC DUCT WORK ONLY) | $69.86 | $33.39 | $103.25 |
| TRUCK DRIVER: DUMP TRUCK | $23.50 | $6.87 | $30.37 |
| SHEET METAL WORKER, EXCLUDES HVAC DUCT INSTALLATION | $24.83 | $0.00 | $24.83 |
| PLUMBER | $35.00 | $0.00 | $35.00 |
| PAINTER: SPRAY | $17.80 | $4.18 | $21.98 |
| PAINTER: DRYWALL FINISHING/TAPING | $29.90 | $0.00 | $29.90 |
| OPERATOR: CRANE | $30.40 | $0.00 | $30.40 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $27.94 | $0.00 | $27.94 |