Current rates (rev 1)
The CSV and the printed sheet are snapshots of rev 1. If DOL revises this determination after you save one, the watch above tells you exactly what moved.
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR (INCLUDES THE APPLICATION OF ALL INSULATING MATERIALS, PROTECTIVE COVERINGS, COATINGS AND FINISHES TO ALL TYPES OF MECHANICAL SYSTEMS.). A. PAID HOLIDAYS: NEW YEAR'S DAY, MARTIN LUTHER KING DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERANS' DAY, THANKSGIVING DAY,THE DAY AFTER THANKSGIVING AND CHRISTMAS DAY | $33.27 | $12.20 | $45.47 |
| ELECTRICIAN | $34.03 | $17.03 | $51.06 |
| TRUCK DRIVER, INCLUDES ALL DUMP TRUCKS | $13.42 | $2.39 | $15.81 |
| POWER EQUIPMENT OPERATOR: TUGBOAT | $19.00 | $0.00 | $19.00 |
| POWER EQUIPMENT OPERATOR: TRACKHOE | $12.75 | $1.24 | $13.99 |
| POWER EQUIPMENT OPERATOR: MECHANIC | $26.78 | $6.32 | $33.10 |
| POWER EQUIPMENT OPERATOR: LOADER | $18.27 | $3.46 | $21.73 |
| POWER EQUIPMENT OPERATOR: CRANE (TOWER) | $23.29 | $6.02 | $29.31 |
| POWER EQUIPMENT OPERATOR: CRANE | $23.15 | $0.00 | $23.15 |
| POWER EQUIPMENT OPERATOR: BULLDOZER | $20.63 | $7.28 | $27.91 |
| POWER EQUIPMENT OPERATOR: BOBCAT/SKID LOADER | $11.40 | $0.00 | $11.40 |
| POWER EQUIPMENT OPERATOR: (EXCAVATOR) | $19.27 | $7.28 | $26.55 |
| POWER EQUIPMENT OPERATOR: (BACKHOE) | $17.61 | $2.57 | $20.18 |
| LABORERS: LANDSCAPE | $10.00 | $0.00 | $10.00 |
| LABORERS: COMMON OR GENERAL | $10.20 | $2.17 | $12.37 |
| LABORERS (PIPELAYER) | $13.88 | $1.32 | $15.20 |
| LABORERS (FLAGGER) | $7.39 | $0.20 | $7.59 |
| IRONWORKER, STRUCTURAL | $20.55 | $8.25 | $28.80 |
| IRONWORKER, REINFORCING | $22.45 | $11.85 | $34.30 |
| CEMENT MASON/CONCRETE FINISHER | $19.00 | $3.83 | $22.83 |
| CARPENTER | $21.57 | $3.74 | $25.31 |