Highway construction wages: Washington, Utah
Wage determination UT20260110 · Active · Standard · verify on SAM.gov
Retrieved from wagepin.com/wd/UT20260110 on · latest revision 1 · verify at sam.gov/wage-determination/UT20260110/1
Revision history
| Revision | Published | Compare |
|---|---|---|
| rev 1 | 2026-05-18 | diff vs rev 0 |
| rev 0 | 2026-05-17 | original |
Current rates (rev 1)
The CSV and the printed sheet are snapshots of rev 1. If DOL revises this determination after you save one, the watch above tells you exactly what moved.
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| CARPENTER (INCLUDES FORM WORK) | $32.17 | $17.50 | $49.67 |
| POWER EQUIPMENT OPERATOR (OILER) | $31.99 | $17.64 | $49.63 |
| TRUCK DRIVER: VACTOR | $23.40 | $0.00 | $23.40 |
| TRUCK DRIVER: DUMP TRUCK | $24.02 | $12.68 | $36.70 |
| TRAFFIC CONTROL: LABORER-CONES/ BARRICADES/BARRELS - SETTER/MOVER/SWEEPER | $20.59 | $8.65 | $29.24 |
| TRAFFIC CONTROL: FLAGGER | $13.25 | $1.75 | $15.00 |
| OPERATOR: PAVEMENT MARKING GRINDER | $27.95 | $7.05 | $35.00 |
| OPERATOR: SCREED | $21.21 | $7.90 | $29.11 |
| OPERATOR: ROLLER | $20.69 | $8.04 | $28.73 |
| OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE) | $23.04 | $8.23 | $31.27 |
| OPERATOR: MECHANIC | $20.83 | $0.00 | $20.83 |
| OPERATOR: LOADER | $25.97 | $11.45 | $37.42 |
| OPERATOR: GRADER/BLADE | $28.20 | $15.88 | $44.08 |
| OPERATOR: DRILL | $27.44 | $15.65 | $43.09 |
| OPERATOR: CRANE | $30.66 | $10.61 | $41.27 |
| OPERATOR: CONCRETE FINISHING MACHINE | $20.03 | $6.55 | $26.58 |
| OPERATOR: BROOM/SWEEPER | $15.12 | $6.95 | $22.07 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $23.97 | $10.06 | $34.03 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $24.55 | $9.53 | $34.08 |
| LABORER: PIPELAYER | $17.23 | $2.79 | $20.02 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $13.02 | $2.64 | $15.66 |
| LABORER: COMMON OR GENERAL | $18.83 | $2.53 | $21.36 |
| LABORER: ASPHALT, INCLUDES RAKER, SHOVELER, SPREADER AND DISTRIBUTOR | $23.83 | $5.92 | $29.75 |
| IRONWORKER, REINFORCING | $26.61 | $13.76 | $40.37 |
| HIGHWAY/PARKING LOT STRIPING: PAINTER | $17.11 | $2.53 | $19.64 |
| ELECTRICIAN | $26.72 | $2.30 | $29.02 |
| CEMENT MASON/CONCRETE FINISHER | $20.41 | $2.41 | $22.82 |
Spot a rate that looks wrong? Email me the details and I’ll check it against the SAM.gov document.