Current rates (rev 1)
The CSV and the printed sheet are snapshots of rev 1. If DOL revises this determination after you save one, the watch above tells you exactly what moved.
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| ELECTRICIAN | $41.23 | $17.77 | $59.00 |
| TRUCK DRIVER: WATER TRUCK | $23.26 | $11.47 | $34.73 |
| TRUCK DRIVER: VACTOR | $23.40 | $0.00 | $23.40 |
| TRUCK DRIVER: DUMP TRUCK | $24.77 | $12.40 | $37.17 |
| TRAFFIC CONTROL: LABORER-CONES/ BARRICADES/BARRELS - SETTER/MOVER/SWEEPER | $20.59 | $8.65 | $29.24 |
| TRAFFIC CONTROL: FLAGGER | $20.59 | $8.65 | $29.24 |
| OPERATOR: PAVEMENT MARKING GRINDER | $24.37 | $15.65 | $40.02 |
| OPERATOR: SCREED | $21.34 | $9.59 | $30.93 |
| OPERATOR: ROLLER | $22.67 | $9.13 | $31.80 |
| OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE) | $25.63 | $10.53 | $36.16 |
| OPERATOR: OILER | $22.18 | $9.73 | $31.91 |
| OPERATOR: MILLING MACHINE | $20.68 | $6.84 | $27.52 |
| OPERATOR: MECHANIC | $31.00 | $15.65 | $46.65 |
| OPERATOR: LOADER | $22.63 | $11.88 | $34.51 |
| OPERATOR: GRADER/BLADE | $26.43 | $11.60 | $38.03 |
| OPERATOR: DRILL | $27.44 | $15.65 | $43.09 |
| OPERATOR: CRANE | $30.66 | $10.61 | $41.27 |
| OPERATOR: CONCRETE FINISHING MACHINE | $20.03 | $6.55 | $26.58 |
| OPERATOR: BROOM/SWEEPER | $22.12 | $8.72 | $30.84 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $18.43 | $3.31 | $21.74 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $20.04 | $7.27 | $27.31 |
| LABORER: PIPELAYER | $16.67 | $3.54 | $20.21 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $15.77 | $4.08 | $19.85 |
| LABORER: COMMON OR GENERAL | $17.51 | $5.84 | $23.35 |
| LABORER: ASPHALT, INCLUDES RAKER, SHOVELER, SPREADER AND DISTRIBUTOR | $22.08 | $8.65 | $30.73 |
| IRONWORKER, REINFORCING | $26.61 | $13.76 | $40.37 |
| HIGHWAY/PARKING LOT STRIPING: PAINTER | $19.52 | $1.62 | $21.14 |
| CEMENT MASON/CONCRETE FINISHER | $20.24 | $6.20 | $26.44 |
| CARPENTER, INCLUDES FORM WORK | $21.87 | $2.80 | $24.67 |