Building construction wages: Wayne, Pennsylvania
Wage determination PA20260072 · Active · Standard · verify on SAM.gov
Retrieved from wagepin.com/wd/PA20260072 on · latest revision 2 · verify at sam.gov/wage-determination/PA20260072/2
Revision history
| Revision | Published | Compare |
|---|---|---|
| rev 2 | 2026-05-18 | diff vs rev 1 |
| rev 1 | 2026-05-17 | diff vs rev 0 |
| rev 0 | 2026-01-09 | original |
Current rates (rev 2)
The CSV and the printed sheet are snapshots of rev 2. If DOL revises this determination after you save one, the watch above tells you exactly what moved.
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR (MECHANICAL- DUCT, PIPE & MECHANICAL SYSTEM INSULATION) | $39.18 | $26.07 | $65.25 |
| BOILERMAKER | $48.28 | $33.17 | $81.45 |
| BRICKLAYER | $37.07 | $18.82 | $55.89 |
| TILE SETTER | $35.64 | $21.63 | $57.27 |
| TILE FINISHER | $28.76 | $17.16 | $45.92 |
| CARPENTER (INCLUDING DRYWALL HANGING, METAL STUD INSTALLATION, AND FORM WORK) | $36.57 | $20.04 | $56.61 |
| ELECTRICIAN (INCLUDING INSTALLATION OF SOUND AND COMMUNICATION SYSTEMS, HVAC/TEMPERATURE CONTROLS AND LOW VOLTAGE WIRING) | $47.97 | $23.29 | $71.26 |
| ELEVATOR MECHANIC | $61.41 | $38.44 | $99.85 |
| POWER EQUIPMENT OPERATOR: PAVER (ASPHALT, AGGREGATE AND CONCRETE) | $36.87 | $21.32 | $58.19 |
| POWER EQUIPMENT OPERATOR: CRANE | $47.14 | $31.58 | $78.72 |
| POWER EQUIPMENT OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $44.61 | $30.83 | $75.44 |
| POWER EQUIPMENT OPERATOR (OILER) | $39.42 | $29.30 | $68.72 |
| POWER EQUIPMENT OPERATOR (FORKLIFT (UNDER 20 FT)) | $41.88 | $30.03 | $71.91 |
| POWER EQUIPMENT OPERATOR (BULLDOZER, LOADER, FORKLIFT (OVER 20 FT)) | $44.61 | $30.83 | $75.44 |
| IRONWORKER, REINFORCING | $37.26 | $32.63 | $69.89 |
| IRONWORKER, STRUCTURAL | $37.26 | $32.63 | $69.89 |
| LABORER: COMMON OR GENERAL | $24.35 | $21.43 | $45.78 |
| PAINTER (BRUSH, ROLLER, SPRAY, AND DRYWALL FINISHING/TAPING) | $27.95 | $16.12 | $44.07 |
| PIPEFITTER (INCLUDES HVAC PIPE INSTALLATION) | $41.36 | $29.45 | $70.81 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | $49.75 | $28.96 | $78.71 |
| SHEET METAL WORKER: EXCLUDING HVAC DUCT INSTALLATION | $43.09 | $42.52 | $85.61 |
| SHEET METAL WORKER (HVAC DUCT INSTALLATION ONLY) | $36.13 | $30.32 | $66.45 |
| TRUCK DRIVER: DUMP TRUCK | $24.98 | $11.88 | $36.86 |
| ROOFER | $22.55 | $12.56 | $35.11 |
| PLUMBER | $32.78 | $17.09 | $49.87 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $26.96 | $13.93 | $40.89 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $16.09 | $3.44 | $19.53 |
| CEMENT MASON/CONCRETE FINISHER | $19.81 | $9.03 | $28.84 |
| OPERATOR: MECHANIC | $36.53 | $22.01 | $58.54 |
| IRONWORKER: ORNAMENTAL | $34.65 | $31.12 | $65.77 |
| LABORER: MASON TENDER - BRICK | $24.88 | $17.27 | $42.15 |
Spot a rate that looks wrong? Email me the details and I’ll check it against the SAM.gov document.