Building construction wages: Union, Pennsylvania
Wage determination PA20260069 · Active · Standard · verify on SAM.gov
Retrieved from wagepin.com/wd/PA20260069 on · latest revision 3 · verify at sam.gov/wage-determination/PA20260069/3
Revision history
| Revision | Published | Compare |
|---|---|---|
| rev 3 | 2026-05-18 | diff vs rev 2 |
| rev 2 | 2026-05-17 | diff vs rev 1 |
| rev 1 | 2026-01-16 | diff vs rev 0 |
| rev 0 | 2026-01-09 | original |
Current rates (rev 3)
The CSV and the printed sheet are snapshots of rev 3. If DOL revises this determination after you save one, the watch above tells you exactly what moved.
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR (MECHANICAL- DUCT, PIPE & MECHANICAL SYSTEM INSULATION) | $39.18 | $26.07 | $65.25 |
| BOILERMAKER | $48.28 | $33.17 | $81.45 |
| MASON - STONE | $32.66 | $21.58 | $54.24 |
| BRICKLAYER (INCLUDING POINTING, CAULKING, AND CLEANING) | $32.66 | $21.58 | $54.24 |
| TERRAZZO WORKER/SETTER | $33.83 | $20.78 | $54.61 |
| TERRAZZO WORKER/GRINDER | $33.94 | $19.03 | $52.97 |
| TERRAZZO FINISHER | $33.23 | $19.03 | $52.26 |
| TILE SETTER | $35.64 | $21.63 | $57.27 |
| TILE FINISHER | $28.76 | $17.16 | $45.92 |
| CARPENTER (INCLUDES DRYWALL HANGING, METAL STUD INSTALLATION, FORM WORK AND SCAFFOLD BUILDING; EXCLUDES ACOUSTICAL CEILING INSTALLATION) | $36.84 | $20.19 | $57.03 |
| MILLWRIGHT | $43.00 | $23.44 | $66.44 |
| ELECTRICIAN (ALARM INSTALLATION, INSTALLATION OF SOUND AND COMMUNICATION SYSTEMS, AND LOW VOLTAGE WIRING ONLY) | $39.27 | $22.28 | $61.55 |
| ELECTRICIAN (HVAC/TEMPERATURE CONTROLS INSTALLATION ONLY) | $38.50 | $26.46 | $64.96 |
| ELEVATOR MECHANIC | $61.41 | $38.44 | $99.85 |
| POWER EQUIPMENT OPERATOR: PAVER (ASPHALT, AGGREGATE AND CONCRETE) | $36.87 | $21.32 | $58.19 |
| POWER EQUIPMENT OPERATOR: CRANE | $47.14 | $31.58 | $78.72 |
| POWER EQUIPMENT OPERATOR (FORKLIFT (UNDER 20 FT., EXCLUDES MASONRY WORK)) | $41.88 | $30.03 | $71.91 |
| POWER EQUIPMENT OPERATOR (BULLDOZER, LOADER, FORKLIFT (20 FT. AND OVER, EXCLUDES MASONRY WORK)) | $44.61 | $30.83 | $75.44 |
| IRONWORKER (STRUCTURAL AND REINFORCING) | $37.26 | $32.63 | $69.89 |
| LABORER (VIBRATING PLATE) | $21.57 | $15.04 | $36.61 |
| LABORER (FORKLIFT (MASONRY WORK ONLY)) | $25.29 | $15.04 | $40.33 |
| PAINTER: BRUSH, ROLLER, AND SPRAY | $27.95 | $16.12 | $44.07 |
| PLUMBER (EXCLUDES HVAC UNIT INSTALLATION) | $41.36 | $29.45 | $70.81 |
| PIPEFITTER (HVAC PIPE INSTALLATION ONLY) | $41.36 | $29.45 | $70.81 |
| PIPEFITTER (EXCLUDES HVAC PIPE INSTALLATION) | $51.69 | $27.07 | $78.76 |
| SHEET METAL WORKER: EXCLUDING HVAC DUCT INSTALLATION | $43.09 | $42.52 | $85.61 |
| SHEET METAL WORKER (HVAC DUCT INSTALLATION ONLY) | $36.13 | $30.32 | $66.45 |
| TRUCK DRIVER: DUMP TRUCK | $24.98 | $11.88 | $36.86 |
| ROOFER | $41.37 | $13.28 | $54.65 |
| PLUMBER (HVAC UNIT INSTALLATION ONLY) | $24.31 | $3.95 | $28.26 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $26.96 | $13.93 | $40.89 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $29.88 | $14.13 | $44.01 |
| LABORER: COMMON OR GENERAL, INCLUDING CEMENT MASON TENDING | $18.14 | $7.11 | $25.25 |
| ELECTRICIAN, EXCLUDES ALARM INSTALLATION, SOUND AND COMMUNICATION INSTALLATION, HVAC/TEMPERATURE CONTROL INSTALLATION, AND LOW VOLTAGE WIRING | $28.98 | $16.73 | $45.71 |
| CEMENT MASON/CONCRETE FINISHER | $19.81 | $9.03 | $28.84 |
| CARPENTER (ACOUSTICAL CEILING INSTALLATION ONLY) | $25.71 | $12.02 | $37.73 |
| OPERATOR: MECHANIC | $36.53 | $22.01 | $58.54 |
| IRONWORKER: ORNAMENTAL | $34.65 | $31.12 | $65.77 |
| LABORER: MASON TENDER - BRICK | $22.29 | $15.92 | $38.21 |
| OPERATOR: OILER | $37.10 | $27.62 | $64.72 |
Spot a rate that looks wrong? Email me the details and I’ll check it against the SAM.gov document.