Current rates (rev 2)
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR (MECHANICAL- DUCT, PIPE & MECHANICAL SYSTEM INSULATION) | $39.18 | $26.07 | $65.25 |
| BOILERMAKER | $48.28 | $33.17 | $81.45 |
| BRICKLAYER | $37.07 | $18.82 | $55.89 |
| TILE SETTER | $35.64 | $21.63 | $57.27 |
| TILE FINISHER | $28.76 | $17.16 | $45.92 |
| CARPENTER (INCLUDES DRYWALL HANGING AND METAL STUD INSTALLATION, EXCLUDES FORM WORK) | $36.84 | $20.04 | $56.88 |
| CARPENTER (FORM WORK ONLY) | $36.84 | $20.04 | $56.88 |
| ELECTRICIAN (INCLUDING INSTALLATION OF SOUND AND COMMUNICATION SYSTEMS, HVAC/TEMPERATURE CONTROLS AND LOW VOLTAGE WIRING) | $47.97 | $23.29 | $71.26 |
| ELEVATOR MECHANIC | $61.41 | $38.44 | $99.85 |
| POWER EQUIPMENT OPERATOR: PAVER (ASPHALT, AGGREGATE AND CONCRETE) | $36.87 | $21.32 | $58.19 |
| POWER EQUIPMENT OPERATOR: CRANE | $47.14 | $31.58 | $78.72 |
| POWER EQUIPMENT OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $44.61 | $30.83 | $75.44 |
| POWER EQUIPMENT OPERATOR (OILER) | $39.42 | $29.30 | $68.72 |
| POWER EQUIPMENT OPERATOR (FORKLIFT (UNDER 20 FT)) | $41.88 | $30.03 | $71.91 |
| POWER EQUIPMENT OPERATOR (BULLDOZER, LOADER, FORKLIFT (OVER 20 FT)) | $44.61 | $30.83 | $75.44 |
| IRONWORKER, REINFORCING | $37.26 | $32.63 | $69.89 |
| IRONWORKER, STRUCTURAL | $37.26 | $32.63 | $69.89 |
| PAINTER (BRUSH, ROLLER, SPRAY, AND DRYWALL FINISHING/TAPING) | $27.95 | $16.12 | $44.07 |
| PIPEFITTER (INCLUDES HVAC PIPE INSTALLATION) | $41.36 | $29.45 | $70.81 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | $49.75 | $28.96 | $78.71 |
| SHEET METAL WORKER: EXCLUDING HVAC DUCT INSTALLATION | $43.09 | $42.52 | $85.61 |
| SHEET METAL WORKER (HVAC DUCT INSTALLATION ONLY) | $36.13 | $30.32 | $66.45 |
| TRUCK DRIVER: DUMP TRUCK | $24.98 | $11.88 | $36.86 |
| ROOFER | $22.55 | $12.56 | $35.11 |
| PLUMBER | $32.78 | $17.09 | $49.87 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $26.96 | $13.93 | $40.89 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $16.09 | $3.44 | $19.53 |
| LABORER: COMMON OR GENERAL | $20.88 | $9.91 | $30.79 |
| CEMENT MASON/CONCRETE FINISHER | $19.81 | $9.03 | $28.84 |
| OPERATOR: MECHANIC | $36.53 | $22.01 | $58.54 |
| IRONWORKER: ORNAMENTAL | $34.65 | $31.12 | $65.77 |
| LABORER: MASON TENDER - BRICK | $24.88 | $17.27 | $42.15 |