Current rates (rev 3)
The CSV and the printed sheet are snapshots of rev 3. If DOL revises this determination after you save one, the watch above tells you exactly what moved.
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| BOILERMAKER | $48.28 | $33.17 | $81.45 |
| TILE FINISHER | $28.76 | $17.16 | $45.92 |
| TILE SETTER | $35.64 | $21.63 | $57.27 |
| CARPENTER (SCAFFOLD BUILDING ONLY) | $34.76 | $20.64 | $55.40 |
| CARPENTER (INCLUDES ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, METAL STUD INSTALLATION, FLOOR LAYING-CARPET AND VINYL, FORM WORK AND GUTTER INSTALLATION; EXCLUDES SCAFFOLD BUILDING) | $34.76 | $20.64 | $55.40 |
| MILLWRIGHT | $43.00 | $23.44 | $66.44 |
| ELECTRICIAN (INCLUDES ALARM INSTALLATION, INSTALLATION OF SOUND AND COMMUNICATION SYSTEM, LOW VOLTAGE WIRING AND HVAC TEMPERATURE CONTROL INSTALLATION) | $50.86 | $31.78 | $82.64 |
| POWER EQUIPMENT OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE, BOBCAT/SKID STEER/SKID LOADER, LOADER, CRANE*, BULLDOZER | $36.87 | $21.32 | $58.19 |
| POWER EQUIPMENT OPERATOR: OILER | $29.70 | $21.32 | $51.02 |
| POWER EQUIPMENT OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE) | $36.87 | $21.32 | $58.19 |
| POWER EQUIPMENT OPERATOR: ROLLER | $32.25 | $21.32 | $53.57 |
| IRONWORKER: ORNAMENTAL, REINFORCING, RIGGER, AND STRUCTURAL | $32.29 | $32.41 | $64.70 |
| LABORER (CONCRETE WORKER) | $25.98 | $19.53 | $45.51 |
| PAINTER (SPRAY ONLY) | $27.95 | $16.12 | $44.07 |
| PAINTER: BRUSH AND ROLLER ONLY | $30.56 | $23.72 | $54.28 |
| PAINTER: DRYWALL FINISHING/TAPING ONLY | $32.39 | $23.26 | $55.65 |
| GLAZIER | $25.40 | $25.47 | $50.87 |
| CEMENT MASON/CONCRETE FINISHER | $31.97 | $21.35 | $53.32 |
| PIPEFITTER (INDUSTRIAL) | $47.75 | $26.55 | $74.30 |
| PIPEFITTER (INCLUDES HVAC UNIT INSTALLATION, EXCLUDES HVAC PIPE INSTALLATION AND WORK ON INDUSTRIAL SITES) | $40.02 | $26.55 | $66.57 |
| PIPEFITTER (HVAC PIPE INSTALLATION ONLY) | $41.36 | $29.45 | $70.81 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | $49.75 | $28.96 | $78.71 |
| SHEET METAL WORKER (EXCLUDES HVAC DUCT INSTALLATION) | $46.75 | $35.93 | $82.68 |
| ASBESTOS WORKER/HEAT & FROST INSULATOR - MECHANICAL (DUCT, PIPE & MECHANICAL SYSTEM INSULATION) | $33.62 | $18.79 | $52.41 |
| LABORER: COMMON OR GENERAL, INCLUDING CEMENT MASON TENDING | $18.43 | $9.74 | $28.17 |
| OPERATOR: FORKLIFT, ALL TYPES | $23.69 | $12.97 | $36.66 |
| PLASTERER | $20.97 | $10.78 | $31.75 |
| PLUMBER | $43.86 | $2.62 | $46.48 |
| ROOFER | $27.00 | $12.19 | $39.19 |
| SHEET METAL WORKER (HVAC DUCT INSTALLATION ONLY) | $30.58 | $24.04 | $54.62 |
| TRUCK DRIVER: DUMP TRUCK | $24.98 | $12.17 | $37.15 |
| BRICKLAYER, INCLUDING POINTING, CAULKING CLEANING AND BRICK REFRACTORY WORK | $37.17 | $22.94 | $60.11 |
| LABORER: MASON TENDER - BRICK | $23.23 | $18.53 | $41.76 |
| MASON - STONE | $34.00 | $22.63 | $56.63 |
| OPERATOR: MECHANIC | $36.53 | $22.01 | $58.54 |