Building construction wages: Clearfield, Pennsylvania
Wage determination PA20260047 · Active · Standard · verify on SAM.gov
Retrieved from wagepin.com/wd/PA20260047 on · latest revision 3 · verify at sam.gov/wage-determination/PA20260047/3
Revision history
| Revision | Published | Compare |
|---|---|---|
| rev 3 | 2026-08-20 | diff vs rev 2 |
| rev 2 | 2026-05-18 | diff vs rev 1 |
| rev 1 | 2026-05-17 | diff vs rev 0 |
| rev 0 | 2026-01-09 | original |
Current rates (rev 3)
The CSV and the printed sheet are snapshots of rev 3. If DOL revises this determination after you save one, the watch above tells you exactly what moved.
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| BOILERMAKER | $48.28 | $33.17 | $81.45 |
| TILE FINISHER | $28.76 | $17.16 | $45.92 |
| TILE SETTER | $35.64 | $21.63 | $57.27 |
| BRICKLAYER: INCLUDING POINTING, CAULKING, CLEANING AND BRICK REFRACTORY WORK ADDITIONAL $0.75 TO THE BASE WAGE FOR BRICK REFRACTORY WORK | $34.14 | $22.77 | $56.91 |
| MASON - STONE ADDITIONAL $0.75 TO THE BASE WAGE FOR BRICK REFRACTORY WORK | $34.14 | $22.77 | $56.91 |
| CARPENTER (SCAFFOLD BUILDING ONLY) | $34.76 | $20.64 | $55.40 |
| CARPENTER (INCLUDES ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, METAL STUD INSTALLATION, FLOOR LAYING-CARPET AND VINYL, FORM WORK AND GUTTER INSTALLATION; EXCLUDES SCAFFOLD BUILDING) | $34.76 | $20.64 | $55.40 |
| MILLWRIGHT | $43.00 | $23.44 | $66.44 |
| ELECTRICIAN (INCLUDES ALARM INSTALLATION, INSTALLATION OF SOUND AND COMMUNICATION SYSTEM, LOW VOLTAGE WIRING AND HVAC TEMPERATURE CONTROL INSTALLATION) | $50.86 | $31.78 | $82.64 |
| POWER EQUIPMENT OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE, BOBCAT/SKID STEER/SKID LOADER, LOADER, CRANE*, BULLDOZER | $36.87 | $21.32 | $58.19 |
| POWER EQUIPMENT OPERATOR: OILER | $29.70 | $21.32 | $51.02 |
| POWER EQUIPMENT OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE) | $36.87 | $21.32 | $58.19 |
| POWER EQUIPMENT OPERATOR: ROLLER | $32.25 | $21.32 | $53.57 |
| IRONWORKER: ORNAMENTAL, REINFORCING, RIGGER, AND STRUCTURAL | $32.29 | $32.41 | $64.70 |
| LABORER (CONCRETE WORKER) | $25.98 | $19.53 | $45.51 |
| PAINTER (SPRAY ONLY) | $27.95 | $16.12 | $44.07 |
| PAINTER: BRUSH AND ROLLER ONLY | $30.56 | $23.72 | $54.28 |
| PAINTER: DRYWALL FINISHING/TAPING ONLY | $32.39 | $23.26 | $55.65 |
| GLAZIER | $25.40 | $25.47 | $50.87 |
| CEMENT MASON/CONCRETE FINISHER | $31.97 | $21.35 | $53.32 |
| PLASTERER | $30.69 | $18.99 | $49.68 |
| PIPEFITTER (INDUSTRIAL) | $47.75 | $26.55 | $74.30 |
| PLUMBER | $40.02 | $26.55 | $66.57 |
| PIPEFITTER (INCLUDES HVAC PIPE INSTALLATION AND HVAC UNIT INSTALLATION, EXCLUDES WORK ON INDUSTRIAL SITES) | $40.02 | $26.55 | $66.57 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | $49.75 | $28.96 | $78.71 |
| SHEET METAL WORKER (INCLUDING HVAC DUCT INSTALLATION) | $46.75 | $35.93 | $82.68 |
| ASBESTOS WORKER/HEAT & FROST INSULATOR - MECHANICAL (DUCT, PIPE & MECHANICAL SYSTEM INSULATION) | $33.62 | $18.79 | $52.41 |
| LABORER: COMMON OR GENERAL, INCLUDING CEMENT MASON TENDING | $18.55 | $9.74 | $28.29 |
| OPERATOR: FORKLIFT, ALL TYPES | $23.69 | $12.97 | $36.66 |
| ROOFER | $27.00 | $12.19 | $39.19 |
| TRUCK DRIVER: DUMP TRUCK | $24.98 | $12.17 | $37.15 |
| LABORER: MASON TENDER - BRICK | $23.23 | $18.53 | $41.76 |
| OPERATOR: MECHANIC | $36.53 | $22.01 | $58.54 |
Spot a rate that looks wrong? Email me the details and I’ll check it against the SAM.gov document.