Building construction wages: Woods, Oklahoma
Wage determination OK20260066 · Active · Standard · verify on SAM.gov
Retrieved from wagepin.com/wd/OK20260066 on · latest revision 1 · verify at sam.gov/wage-determination/OK20260066/1
Revision history
| Revision | Published | Compare |
|---|---|---|
| rev 1 | 2026-05-18 | diff vs rev 0 |
| rev 0 | 2026-05-17 | original |
Current rates (rev 1)
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| PLUMBER (EXCLUDES HVAC PIPE INSTALLATION) | $41.00 | $16.03 | $57.03 |
| BOILERMAKER | $33.70 | $24.41 | $58.11 |
| BRICKLAYER | $26.92 | $13.09 | $40.01 |
| ELECTRICIAN | $41.40 | $13.14 | $54.54 |
| ELECTRICIAN (LOW VOLTAGE WIRING AND ALARM INSTALLATION ONLY) | $24.26 | $9.76 | $34.02 |
| POWER EQUIPMENT OPERATOR: GROUP 8 FORKLIFT | $28.77 | $19.05 | $47.82 |
| POWER EQUIPMENT OPERATOR: GROUP 4 CRANES WITH BOOM INCL. JIB LESS THAN 100 FT AND LESS THAN 3 CU. YD.; OVERHEAD MONORAIL CRANE AND BULLDOZER | $34.07 | $19.05 | $53.12 |
| POWER EQUIPMENT OPERATOR: GROUP 3 ALL CRANE TYPE EQUIPMENT 50 TON CAPACITY AND LARGER CRANES, AND LESS THAN 100 TON CAPACITY. CRANE EQUIPMENT (AS RATED BY MFG.) 3 CU. YD. AND OVER GUY DERRICK WHIRLEY POWER DRIVEN HOLE DIGGER (WITH 30' AND LONGER MAST) | $35.40 | $19.05 | $54.45 |
| POWER EQUIPMENT OPERATOR: GROUP 2 ALL CRANE TYPE EQUIPMENT 100 TON CAPACITY AND LARGER CRANES, AND LESS THAN 200 TON CAPACITY | $36.14 | $19.05 | $55.19 |
| POWER EQUIPMENT OPERATOR: GROUP 10 OILER | $27.25 | $19.05 | $46.30 |
| POWER EQUIPMENT OPERATOR: GROUP 1 ALL CRANE TYPE EQUIPMENT 200 TON AND LARGER AND INCLUDING 400 TON CAPACITY CRANES. ALL TOWER CRANES | $38.09 | $19.05 | $57.14 |
| IRONWORKER, STRUCTURAL | $32.10 | $17.38 | $49.48 |
| PLASTERER | $33.62 | $14.18 | $47.80 |
| PIPEFITTER (HVAC PIPE INSTALLATION ONLY) | $41.00 | $16.03 | $57.03 |
| SHEET METAL WORKER (HVAC DUCT AND UNIT INSTALLATION ONLY) | $33.38 | $16.36 | $49.74 |
| SHEET METAL WORKER, EXCLUDES HVAC DUCT AND UNIT INSTALLATION | $16.32 | $0.00 | $16.32 |
| ROOFER | $15.00 | $0.29 | $15.29 |
| PIPEFITTER, EXCLUDES HVAC PIPE INSTALLATION | $19.00 | $0.00 | $19.00 |
| PAINTER: DRYWALL FINISHING/TAPING | $12.00 | $0.00 | $12.00 |
| PAINTER: BRUSH, ROLLER AND SPRAY | $12.18 | $0.00 | $12.18 |
| OPERATOR: ROLLER | $13.80 | $0.94 | $14.74 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $19.34 | $0.74 | $20.08 |
| LABORER: PLASTER TENDER | $10.17 | $0.00 | $10.17 |
| LABORER: PIPELAYER | $13.03 | $0.00 | $13.03 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $13.04 | $0.00 | $13.04 |
| LABORER: MASON TENDER - BRICK | $11.88 | $0.00 | $11.88 |
| LABORER: COMMON OR GENERAL | $11.00 | $0.00 | $11.00 |
| CEMENT MASON/CONCRETE FINISHER | $16.10 | $0.00 | $16.10 |
| CARPENTER, EXCLUDES DRYWALL HANGING, FORM WORK, AND METAL STUD INSTALLATION | $12.79 | $0.00 | $12.79 |
| CARPENTER (FORM WORK ONLY) | $15.34 | $5.50 | $20.84 |
| CARPENTER (DRYWALL HANGING AND METAL STUD INSTALLATION ONLY) | $14.16 | $0.00 | $14.16 |