Building construction wages: Muskogee, Oklahoma
Wage determination OK20260061 · Active · Standard · verify on SAM.gov
Retrieved from wagepin.com/wd/OK20260061 on · latest revision 1 · verify at sam.gov/wage-determination/OK20260061/1
Revision history
| Revision | Published | Compare |
|---|---|---|
| rev 1 | 2026-05-18 | diff vs rev 0 |
| rev 0 | 2026-05-17 | original |
Current rates (rev 1)
The CSV and the printed sheet are snapshots of rev 1. If DOL revises this determination after you save one, the watch above tells you exactly what moved.
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| BOILERMAKER | $33.70 | $24.41 | $58.11 |
| ELEVATOR MECHANIC PAID HOLIDAYS: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, THE FRIDAY AFTER THANKSGIVING, AND CHRISTMAS DAY. B. EMPLOYER CONTRIBUTES 8% OF REGULAR HOURLY RATE TO VACATION PAY CREDIT FOR EMPLOYEE WHO HAS WORKED IN BUSINESS MORE THAN 5 YEARS; 6% FOR LESS THAN 5 YEARS' SERVICE | $51.24 | $38.44 | $89.68 |
| POWER EQUIPMENT OPERATOR: GROUP 8 FORKLIFT | $28.77 | $19.05 | $47.82 |
| POWER EQUIPMENT OPERATOR: GROUP 4 CRANES WITH BOOM INCL. JIB LESS THAN 100 FT AND LESS THAN 3 CU. YD.; OVERHEAD MONORAIL CRANE AND BULLDOZER | $34.07 | $19.05 | $53.12 |
| POWER EQUIPMENT OPERATOR: GROUP 3 ALL CRANE TYPE EQUIPMENT 50 TON CAPACITY AND LARGER CRANES, AND LESS THAN 100 TON CAPACITY. CRANE EQUIPMENT (AS RATED BY MFG.) 3 CU. YD. AND OVER GUY DERRICK WHIRLEY POWER DRIVEN HOLE DIGGER (WITH 30' AND LONGER MAST) | $35.40 | $19.05 | $54.45 |
| POWER EQUIPMENT OPERATOR: GROUP 2 ALL CRANE TYPE EQUIPMENT 100 TON CAPACITY AND LARGER CRANES, AND LESS THAN 200 TON CAPACITY | $36.14 | $19.05 | $55.19 |
| POWER EQUIPMENT OPERATOR: GROUP 10 OILER | $27.25 | $19.05 | $46.30 |
| POWER EQUIPMENT OPERATOR: GROUP 1 ALL CRANE TYPE EQUIPMENT 200 TON AND LARGER AND INCLUDING 400 TON CAPACITY CRANES. ALL TOWER CRANES | $38.09 | $19.05 | $57.14 |
| IRONWORKER, STRUCTURAL | $30.35 | $16.83 | $47.18 |
| PIPEFITTER (INCLUDING HVAC PIPE AND UNIT INSTALLATION) | $36.65 | $16.03 | $52.68 |
| SHEET METAL WORKER (INCLUDING HVAC DUCT INSTALLATION) | $35.49 | $14.60 | $50.09 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | $39.95 | $0.38 | $40.33 |
| ROOFER | $15.00 | $0.29 | $15.29 |
| PLUMBER, EXCLUDES HVAC PIPE INSTALLATION | $24.66 | $10.36 | $35.02 |
| PAINTER: BRUSH, ROLLER AND SPRAY | $13.56 | $0.00 | $13.56 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $13.00 | $0.00 | $13.00 |
| LABORER: PIPELAYER | $12.93 | $0.00 | $12.93 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $13.04 | $0.00 | $13.04 |
| LABORER: MASON TENDER - BRICK | $10.25 | $0.00 | $10.25 |
| LABORER: COMMON OR GENERAL | $9.22 | $0.00 | $9.22 |
| ELECTRICIAN: EXCLUDES LOW VOLTAGE WIRING AND INSTALLATION OF ALARMS AND SOUND AND COMMUNICATION SYSTEMS | $23.04 | $5.52 | $28.56 |
| ELECTRICIAN: ALARM INSTALLATION | $20.47 | $4.52 | $24.99 |
| ELECTRICIAN (SOUND AND COMMUNICATIONS SYSTEMS INSTALLATION) | $22.10 | $5.76 | $27.86 |
| ELECTRICIAN (LOW VOLTAGE WIRING) | $21.03 | $4.94 | $25.97 |
| CEMENT MASON/CONCRETE FINISHER | $16.91 | $0.61 | $17.52 |
| CAULKER | $20.00 | $1.61 | $21.61 |
| CARPENTER | $13.62 | $0.00 | $13.62 |
| BRICKLAYER | $20.00 | $0.00 | $20.00 |
Spot a rate that looks wrong? Email me the details and I’ll check it against the SAM.gov document.