| Classification | Rate | Fringe | Total |
|---|---|---|---|
| BOILERMAKER | $33.70 | $24.41 | $58.11 |
| ELECTRICIAN (LOW VOLTAGE WIRING, ALARM INSTALLATION, AND SOUND AND COMMUNICATIONS SYSTEMS INSTALLATION ONLY) | $21.60 | — | $21.60 |
| POWER EQUIPMENT OPERATOR: GROUP 4 CRANES WITH BOOM INCL. JIB LESS THAN 100 FT AND LESS THAN 3 CU. YD.; OVERHEAD MONORAIL CRANE AND BULLDOZER | $34.07 | $19.05 | $53.12 |
| POWER EQUIPMENT OPERATOR: GROUP 3 ALL CRANE TYPE EQUIPMENT 50 TON CAPACITY AND LARGER CRANES, AND LESS THAN 100 TON CAPACITY. CRANE EQUIPMENT (AS RATED BY MFG.) 3 CU. YD. AND OVER GUY DERRICK WHIRLEY POWER DRIVEN HOLE DIGGER (WITH 30' AND LONGER MAST) | $35.40 | $19.05 | $54.45 |
| POWER EQUIPMENT OPERATOR: GROUP 2 ALL CRANE TYPE EQUIPMENT 100 TON CAPACITY AND LARGER CRANES, AND LESS THAN 200 TON CAPACITY | $36.14 | $19.05 | $55.19 |
| POWER EQUIPMENT OPERATOR: GROUP 10 OILER | $27.25 | $19.05 | $46.30 |
| POWER EQUIPMENT OPERATOR: GROUP 1 ALL CRANE TYPE EQUIPMENT 200 TON AND LARGER AND INCLUDING 400 TON CAPACITY CRANES. ALL TOWER CRANES | $38.09 | $19.05 | $57.14 |
| IRONWORKER, STRUCTURAL | $32.10 | $17.38 | $49.48 |
| PIPEFITTER (INCLUDING INSTALLATION OF HVAC ELECTRICAL/TEMPERATURE CONTROLS AND HVAC PIPE INSTALLATION) | $41.00 | $16.03 | $57.03 |
| SHEET METAL WORKER (INCLUDING HVAC DUCT INSTALLATION) | $33.38 | $16.36 | $49.74 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | $21.52 | $6.00 | $27.52 |
| ROOFER | $15.00 | $0.29 | $15.29 |
| PLUMBER, EXCLUDES HVAC PIPE INSTALLATION | $18.00 | $3.23 | $21.23 |
| PAINTER: BRUSH, ROLLER AND SPRAY | $12.32 | $0.00 | $12.32 |
| OPERATOR: FORKLIFT | $18.02 | $0.00 | $18.02 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $16.83 | $0.00 | $16.83 |
| LABORER: PIPELAYER | $11.65 | $0.00 | $11.65 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $13.04 | $0.00 | $13.04 |
| LABORER: MASON TENDER - BRICK | $12.00 | $0.00 | $12.00 |
| LABORER: COMMON OR GENERAL | $11.58 | $0.77 | $12.35 |
| GLAZIER | $15.27 | $1.46 | $16.73 |
| FORM WORKER | $13.79 | $0.92 | $14.71 |
| FLOOR LAYER (HARDWOOD AND CARPET) | $18.74 | $1.10 | $19.84 |
| ELECTRICIAN | $21.51 | $6.27 | $27.78 |
| CEMENT MASON/CONCRETE FINISHER | $14.50 | $0.00 | $14.50 |
| CARPENTER, EXCLUDES ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, AND FORM WORK | $16.19 | $0.96 | $17.15 |
| CARPENTER (DRYWALL HANGING ONLY) | $14.96 | $0.00 | $14.96 |
| CARPENTER (ACOUSTICAL CEILING INSTALLATION ONLY) | $16.20 | $0.00 | $16.20 |
| BRICKLAYER | $20.00 | $0.00 | $20.00 |