OH20260081: rev 0 → rev 1

1 rate change, 3 added, 3 removed.

Rate changes

Rates below include fringe (the full hourly package). Enter your remaining crew hours per classification to price this change for a job.

ClassificationOld totalNew totalΔ/hrHours on jobCost impact
ROOFER$52.42$54.32+1.90

Added classifications

OPERATOR: OILER$27.56$16.37
SHEET METAL WORKER, EXCLUDES HVAC DUCT AND UNIT INSTALLATION$28.10$23.41
OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE$34.84$14.76

Removed classifications

OPERATOR: Oilerwas $27.56
SHEET METAL WORKER, Excludes HVAC Duct and Unit Installationwas $28.10
OPERATOR: Backhoe/Excavator/Trackhoewas $34.84