rev 12026-05-18diff vs rev 0
rev 02026-05-17original

Current rates (rev 1)

Download CSV

The CSV and the printed sheet are snapshots of rev 1. If DOL revises this determination after you save one, the watch above tells you exactly what moved.

ClassificationRateFringeTotal
ASBESTOS WORKER/HEAT & FROST INSULATOR$35.23$23.04$58.27
BRICKLAYER$33.30$18.28$51.58
TILE SETTER$30.98$15.82$46.80
TILE FINISHER$28.28$11.05$39.33
ELECTRICIAN$38.00$22.49$60.49
ELEVATOR MECHANIC PAID HOLIDAYS: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERN'S DAY, THANKSGIVING DAY, THE FRIDAY AFTER THANKSGIVING, AND CHRISTMAS DAY. B. EMPLOYER CONTRIBUTES 8% OF REGULAR HOURLY RATE TO VACATION PAY CREDIT FOR EMPLOYEE WHO HAS WORKED IN BUSINESS MORE THAN 5 YEARS; 6% FOR LESS THAN 5 YEARS' SERVICE$57.41$38.44$95.85
POWER EQUIPMENT OPERATOR: CRANE$44.14$16.41$60.55
POWER EQUIPMENT OPERATOR: GRADER/BLADE$32.42$19.66$52.08
POWER EQUIPMENT OPERATOR: FORKLIFT$28.87$19.66$48.53
POWER EQUIPMENT OPERATOR (MECHANIC)$32.92$19.66$52.58
IRONWORKER: ORNAMENTAL$37.77$23.90$61.67
IRONWORKER (REINFORCING AND STRUCTURAL)$37.39$25.35$62.74
LABORER: MASON TENDER - BRICK$32.25$12.95$45.20
LABORER: COMMON OR GENERAL; ASBESTOS ABATEMENT (REMOVAL FROM CEILINGS, FLOORS, AND WALLS)$31.65$12.95$44.60
PAINTER: BRUSH AND ROLLER$29.15$13.97$43.12
GLAZIER$31.95$18.20$50.15
PIPEFITTER (EXCLUDES HVAC PIPE INSTALLATION)$51.00$32.56$83.56
PLUMBER (HVAC PIPE INSTALLATION ONLY)$43.05$27.18$70.23
ROOFER$34.38$19.94$54.32
SPRINKLER FITTER (FIRE SPRINKLERS)$48.28$28.08$76.36
TRUCK DRIVER: DUMP (ALL TYPES)$22.08$11.51$33.59
SHEET METAL WORKER (HVAC DUCT AND HVAC UNIT INSTALLATION ONLY)$24.23$11.25$35.48
PLUMBER, EXCLUDES HVAC PIPE INSTALLATION$26.68$12.55$39.23
PAINTER: SPRAY$22.78$12.40$35.18
OPERATOR: ROLLER$28.25$12.61$40.86
OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE)$30.28$13.29$43.57
OPERATOR: LOADER$29.99$12.80$42.79
OPERATOR: BULLDOZER$26.01$4.95$30.96
OPERATOR: BOBCAT/SKID STEER/SKID LOADER$30.26$12.58$42.84
OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE$31.97$9.08$41.05
LABORER: PIPELAYER$23.98$8.58$32.56
LABORER: MASON TENDER - CEMENT/CONCRETE$22.95$8.60$31.55
FORM WORKER$22.41$9.01$31.42
DRYWALL HANGER AND METAL STUD INSTALLER$21.02$4.21$25.23
CEMENT MASON/CONCRETE FINISHER$26.07$12.34$38.41
CARPENTER$21.80$7.13$28.93
OPERATOR: OILER$27.56$16.37$43.93
SHEET METAL WORKER, EXCLUDES HVAC DUCT AND UNIT INSTALLATION$28.10$23.41$51.51