Current rates (rev 2)
The CSV and the printed sheet are snapshots of rev 2. If DOL revises this determination after you save one, the watch above tells you exactly what moved.
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR (MECHANICAL (DUCT, PIPE & MECHANICAL SYSTEM INSULATION)) | $43.25 | $27.29 | $70.54 |
| BRICKLAYER | $62.54 | $29.40 | $91.94 |
| CEMENT MASON/CONCRETE FINISHER | $34.32 | $20.52 | $54.84 |
| TILE SETTER | $30.69 | $20.91 | $51.60 |
| SOFT FLOOR LAYER (HARDWOOD FLOORS) | $28.90 | $21.63 | $50.53 |
| CARPENTER (EXCLUDES DRYWALL HANGING, FORM WORK AND METAL STUD INSTALLATION) | $33.24 | $24.60 | $57.84 |
| CARPENTER (FORM WORK ONLY) | $43.50 | $30.22 | $73.72 |
| CARPENTER (DRYWALL HANGING ONLY) | $43.50 | $30.22 | $73.72 |
| INSTALLER - METAL STUD | $44.72 | $31.23 | $75.95 |
| ELECTRICIAN (INCLUDES LOW VOLTAGE WIRING) | $42.68 | $33.06 | $75.74 |
| ELEVATOR MECHANIC | $57.73 | $38.44 | $96.17 |
| POWER EQUIPMENT OPERATOR: CRANE | $61.72 | $37.50 | $99.22 |
| POWER EQUIPMENT OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $60.13 | $37.50 | $97.63 |
| IRONWORKER: ORNAMENTAL | $35.49 | $32.30 | $67.79 |
| IRONWORKER, STRUCTURAL | $42.63 | $53.70 | $96.33 |
| IRONWORKER, REINFORCING | $42.63 | $53.70 | $96.33 |
| LABORER (COMMON OR GENERAL) | $43.55 | $29.75 | $73.30 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $28.27 | $22.20 | $50.47 |
| PAINTER (SPRAY) | $28.35 | $25.21 | $53.56 |
| GLAZIER | $27.90 | $27.50 | $55.40 |
| PIPEFITTER | $37.47 | $27.40 | $64.87 |
| ROOFER | $50.25 | $39.62 | $89.87 |
| PAINTER (BRUSH AND ROLLER) | $25.37 | $19.91 | $45.28 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $41.10 | $19.26 | $60.36 |
| OPERATOR: FORKLIFT | $38.46 | $28.52 | $66.98 |
| PLUMBER | $37.19 | $27.89 | $65.08 |