Wage determination NM20260023 · Active · Standard · verify on SAM.gov

Luna

Get an email when this determination changes.This determination changed once in the last 12 months, most recently 2026-05-18: 1 rate change (ELECTRICIAN (EXCLUDING LOW VOLTAGE WIRING FOR A… $38.00 → $38.00).
Substantive rate changes only; no spam. Bidding a specific job? Pin a project instead to lock the revision that applied on your bid date.

Revision history

RevisionPublishedCompare
rev 12026-05-18diff vs rev 0
rev 02026-05-17original

Current rates (rev 1)

Download CSV

The CSV and the printed sheet are snapshots of rev 1. If DOL revises this determination after you save one, the watch above tells you exactly what moved.

ClassificationRateFringeTotal
CARPENTER (METAL STUD INSTALLATION ONLY)$24.08$10.79$34.87
ELECTRICIAN (EXCLUDING LOW VOLTAGE WIRING FOR ALARMS)$38.00$9.82$47.82
POWER EQUIPMENT OPERATOR ((8)CRANE)$31.43$4.65$36.08
POWER EQUIPMENT OPERATOR ((4) BOBCAT/SKID LOADER, LOADER (FRONT END))$27.70$4.65$32.35
IRONWORKER: ORNAMENTAL$28.05$18.11$46.16
IRONWORKER, STRUCTURAL (METAL BUILDING ERECTION ONLY)$28.05$18.11$46.16
PLUMBER (EXCLUDING HVAC PIPE INSTALLATION)$43.07$16.60$59.67
PIPEFITTER: INCLUDING HVAC PIPE INSTALLATION$43.07$16.60$59.67
SHEET METAL WORKER (HVAC DUCT AND SYSTEM INSTALLATION ONLY)$37.50$18.51$56.01
TRUCK DRIVER: WATER TRUCK$16.25$5.00$21.25
TRUCK DRIVER: PICKUP TRUCK$15.91$3.13$19.04
TRUCK DRIVER: DUMP TRUCK$15.36$5.00$20.36
TILE SETTER$19.00$0.00$19.00
TILE FINISHER$14.02$0.00$14.02
SHEET METAL WORKER, INCLUDES HVAC DUCT AND UNIT INSTALLATION$22.01$9.65$31.66
ROOFER$13.24$0.50$13.74
PLASTERER$17.65$7.15$24.80
PAINTER: BRUSH, ROLLER AND SPRAY, EXCLUDES DRYWALL FINISHING/TAPING$16.58$1.75$18.33
OPERATOR: ROLLER (DIRT AND GRADE COMPACTION)$16.80$4.43$21.23
OPERATOR: GRADER/BLADE$21.39$4.94$26.33
OPERATOR: FORKLIFT$21.13$4.83$25.96
OPERATOR: BACKHOE$22.13$4.30$26.43
LABORER: PIPELAYER$13.78$2.20$15.98
LABORER: MASON TENDER - CEMENT/CONCRETE$11.51$0.85$12.36
LABORER: MASON TENDER - BRICK$13.77$4.35$18.12
LABORER: LANDSCAPE & IRRIGATION$10.60$0.24$10.84
LABORER: COMMON OR GENERAL$13.12$3.79$16.91
IRONWORKER, STRUCTURAL, EXCLUDES METAL BUILDING ERECTION$22.20$8.06$30.26
IRONWORKER, REINFORCING$20.84$7.68$28.52
INSULATOR - BATT$24.44$8.43$32.87
GLAZIER$20.15$3.95$24.10
FLOOR LAYER: CARPET$22.31$0.30$22.61
DRYWALL FINISHER/TAPER$19.64$2.75$22.39
CEMENT MASON/CONCRETE FINISHER$17.72$3.72$21.44
ELECTRICIAN (Low Voltage Wiring for Alarms)$28.25$6.62$34.87
CARPENTER, EXCLUDES ACOUSTICAL CEILING INSTALLATION, BATT INSULATION, DRYWALL HANGING, FORM WORK, AND METAL STUD INSTALLATION$20.86$1.30$22.16
CARPENTER (FORM WORK ONLY)$19.79$6.14$25.93
CARPENTER (DRYWALL HANGING ONLY)$21.39$2.85$24.24
CARPENTER (ACOUSTICAL CEILING INSTALLATION ONLY)$20.79$0.00$20.79
BRICKLAYER$20.36$5.74$26.10
BOILERMAKER$21.77$3.98$25.75