Building construction wages: Eddy, New Mexico
Wage determination NM20260018 · Active · Standard · verify on SAM.gov
Retrieved from wagepin.com/wd/NM20260018 on · latest revision 1 · verify at sam.gov/wage-determination/NM20260018/1
Revision history
| Revision | Published | Compare |
|---|---|---|
| rev 1 | 2026-05-18 | diff vs rev 0 |
| rev 0 | 2026-05-17 | original |
Current rates (rev 1)
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| CARPENTER (METAL STUD INSTALLATION ONLY) | $24.08 | $10.79 | $34.87 |
| ELECTRICIAN, EXCLUDING LOW VOLTAGE WIRING FOR ALARMS: ZONE 1. ZONE 1: MILEAGE CALCULATED FROM THE MAIN POST OFFICE IN THE FOLLOWING TOWNS: ALBUQUERQUE-40 MILES, ARTESIA-12 MILES, BELEN-12 MILES, CARLSBAD-12 MILES, CARRIZOZO-12 MILES, CLOVIS-12 MILES, ESPANOLA-14 MILES, FARMINGTON-6 MILES, GALLUP-10 MILES, HOBBS-12 MILES, LAS VEGAS-8 MILES, LOS LUNAS-12 MILES, LOVINGTON-12 MILES, PORTALES-12 MILES, RATON-6 MILES, ROSWELL-12 MILES, RUIDOSO-12 MILES, SANTA FE-10 MILES, TUCUMCARI-6 MILES. ZONE 2: EXTENDING UP TO 20 MILES BEYOND ZONE 1, EXCEPT ALBURQUERQUE, SHALL RECEIVE 9% ABOVE ZONE 1 RATE. ZONE 3: EXTENDING UP TO 30 MILES BEYOND ZONE 1, EXCEPT ALBURQUERQUE, SHALL RECEIVE 15% ABOVE ZONE 1 RATE. ZONE 4: EXTENDING MORE THAN 30 MILES BEYOND ZONE 1, EXCEPT ALBURQUERQUE, SHALL RECEIVE 26% ABOVE ZONE 1 RATE | $40.30 | $13.41 | $53.71 |
| POWER EQUIPMENT OPERATOR ((8) CRANE) | $31.43 | $4.65 | $36.08 |
| POWER EQUIPMENT OPERATOR ((4) BOBCAT/SKID LOADER, LOADER (FRONT END)) | $27.70 | $4.65 | $32.35 |
| POWER EQUIPMENT OPERATOR ((2) ROLLER(DIRT AND GRADE COMPACTION)) | $26.75 | $4.65 | $31.40 |
| IRONWORKER: ORNAMENTAL | $28.05 | $18.11 | $46.16 |
| IRONWORKER, STRUCTURAL (METAL BUILDING ERECTION ONLY) | $28.05 | $18.11 | $46.16 |
| PLUMBER (EXCLUDING HVAC PIPE INSTALLATION) | $43.07 | $16.60 | $59.67 |
| PIPEFITTER: INCLUDING HVAC PIPE INSTALLATION | $43.07 | $16.60 | $59.67 |
| SHEET METAL WORKER (HVAC DUCT AND SYSTEM INSTALLATION ONLY) | $37.50 | $18.51 | $56.01 |
| TRUCK DRIVER: WATER TRUCK | $16.25 | $5.00 | $21.25 |
| TRUCK DRIVER: PICKUP TRUCK | $15.91 | $3.13 | $19.04 |
| TRUCK DRIVER: DUMP TRUCK | $15.36 | $5.00 | $20.36 |
| TILE SETTER | $19.00 | $0.00 | $19.00 |
| TILE FINISHER | $14.02 | $0.00 | $14.02 |
| SHEET METAL WORKER, EXCLUDES HVAC DUCT AND UNIT INSTALLATION | $22.01 | $9.65 | $31.66 |
| ROOFER | $15.41 | $0.00 | $15.41 |
| PLASTERER | $17.65 | $7.15 | $24.80 |
| PAINTER: BRUSH, ROLLER AND SPRAY, EXCLUDES DRYWALL FINISHING/TAPING | $16.58 | $1.75 | $18.33 |
| OPERATOR: GRADER/BLADE | $21.39 | $4.94 | $26.33 |
| OPERATOR: FORKLIFT | $21.13 | $4.83 | $25.96 |
| OPERATOR: BACKHOE | $22.13 | $4.30 | $26.43 |
| LABORER: PIPELAYER | $13.78 | $2.20 | $15.98 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $11.51 | $0.85 | $12.36 |
| LABORER: MASON TENDER - BRICK | $13.77 | $4.35 | $18.12 |
| LABORER: LANDSCAPE & IRRIGATION | $10.60 | $0.24 | $10.84 |
| LABORER: COMMON OR GENERAL | $10.76 | $2.11 | $12.87 |
| IRONWORKER, STRUCTURAL, EXCLUDES METAL BUILDING ERECTION | $22.20 | $8.06 | $30.26 |
| IRONWORKER, REINFORCING | $20.84 | $7.68 | $28.52 |
| INSULATOR - BATT | $24.44 | $8.43 | $32.87 |
| GLAZIER | $20.15 | $3.95 | $24.10 |
| FLOOR LAYER: CARPET | $22.31 | $0.30 | $22.61 |
| DRYWALL FINISHER/TAPER | $19.64 | $2.75 | $22.39 |
| CEMENT MASON/CONCRETE FINISHER | $17.72 | $3.72 | $21.44 |
| ELECTRICIAN (Low Voltage Wiring for Alarms) | $28.25 | $6.62 | $34.87 |
| CARPENTER, EXCLUDES ACOUSTICAL CEILING INSTALLATION, BATT INSULATION, DRYWALL HANGING, FORM WORK, AND METAL STUD INSTALLATION | $23.05 | $0.35 | $23.40 |
| CARPENTER (FORM WORK ONLY) | $19.79 | $6.14 | $25.93 |
| CARPENTER (DRYWALL HANGING ONLY) | $21.39 | $2.85 | $24.24 |
| CARPENTER (ACOUSTICAL CEILING INSTALLATION ONLY) | $20.79 | $0.00 | $20.79 |
| BRICKLAYER | $20.36 | $5.74 | $26.10 |
| BOILERMAKER | $21.77 | $3.98 | $25.75 |