Heavy construction wages: Morris, New Jersey
Wage determination NJ20260059 · Active · Standard · verify on SAM.gov
Retrieved from wagepin.com/wd/NJ20260059 on July 24, 2026 · latest revision 1 · verify at sam.gov/wage-determination/NJ20260059/1
Revision history
| Revision | Published | Compare |
|---|---|---|
| rev 1 | 2026-05-18 | diff vs rev 0 |
| rev 0 | 2026-05-17 | original |
Current rates (rev 1)
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| CEMENT MASON | $49.60 | $37.96 | $87.56 |
| HOUR ADDITIONAL FOR EACH ADDITIONAL FIFTY FEET THEREAFTER | $57.42 | $34.17 | $91.59 |
| DISMANTLING OF ELEVATORS AND TOWERS, SUCH AS CONCRETE CONVEYORS AND TEMPORARY MATERIAL ELEVATORS, SCAFFOLDING OR OTHER STRUCTURES TO BE USED AS SCAFFOLDING INSIDE OR OUTSIDE OF BUILDINGS: THE FIRST SIXTY FEET AT THE REGULAR RATE, 10% PER HOUR ADDITIONAL FOR EACH ADDITIONAL FIFTY FEET THEREAFTER | $58.84 | $35.06 | $93.90 |
| FORTY FT. OR MORE ABOVE THE GROUND OR PROTECTIVE RIGGING (DOES NOT APPLY TO POLE WORK, OR TO USE OF A MANLIFT OR HIGH REACH-TYPE LIFT): 10% PER HOUR ADDITIONAL. WORK WITH, OR THE REMOVAL OF, ASBESTOS MATERIALS: 112% TIMES THE JOURNEYMAN RATE | $65.43 | $42.86 | $108.29 |
| PROTECTIVE RIGGING (DOES NOT APPLY TO POLE WORK, OR TO USE OF A MANLIFT OR HIGH REACH-TYPE LIFT): 10% PER HOUR ADDITIONAL. WORK WITH, OR THE REMOVAL OF, ASBESTOS MATERIALS: 112% TIMES THE JOURNEYMAN RATE | $71.97 | $46.42 | $118.39 |
| WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY | $52.88 | $37.50 | $90.38 |
| BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY | $56.59 | $37.50 | $94.09 |
| WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY | $58.22 | $37.50 | $95.72 |
| HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY | $60.13 | $37.50 | $97.63 |
| BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY | $61.72 | $37.50 | $99.22 |
| IRONWORKER: STRUCTURAL AND ORNAMENTAL | $52.24 | $50.32 | $102.56 |
| IRONWORKER: REINFORCING | $49.94 | $50.32 | $100.26 |
| LABORER: MASON TENDER: CEMENT/CONCRETE | $29.35 | $23.07 | $52.42 |
| HOLIDAYS: NEW YEAR'S DAY, PRESIDENT'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED THAT THE WORKER WORKS THREE DAYS FOR THE SAME EMPLOYER WITHIN A PERIOD OF TEN WORKING DAYS CONSISTING OF FIVE WORKING DAYS BEFORE AND FIVE WORKING DAYS AFTER THE DAY UPON WHICH THE HOLIDAY FALLS OR IS OBSERVED | $51.65 | $38.53 | $90.18 |
| PRESIDENT'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED THAT THE WORKER WORKS THREE DAYS FOR THE SAME EMPLOYER WITHIN A PERIOD OF TEN WORKING DAYS CONSISTING OF FIVE WORKING DAYS BEFORE AND FIVE WORKING DAYS AFTER THE DAY UPON WHICH THE HOLIDAY FALLS OR IS OBSERVED | $50.95 | $38.53 | $89.48 |
| PAINTER: WORK ON BRIDGES (MAJOR BRIDGES DESIGNED FOR COMMERCIAL NAVIGATION) | $58.28 | $33.85 | $92.13 |
| PAINTER: BRUSH AND ROLLER (REPAINT WORK, ON PROJECTS ON WHICH NO MAJOR ALTERATIONS OCCUR.) | $29.05 | $18.91 | $47.96 |
| PAINTER: BRUSH AND ROLLER (NEW CONSTRUCTION) | $40.19 | $22.72 | $62.91 |
| PIPEFITTER (MORRIS COUNTY (DOES NOT INCLUDE THE BOROUGH OF CHATHAM; TOWNSHIP OF CHATHAM; BOROUGH OF CHESTER; TOWNSHIPS OF CHESTER, HARDING AND LONG HILL; BOROUGH OF MENDHAM; TOWNSHIPS OF MENDHAM AND MOUNT OLIVE; TOWNSHIP OF WASHINGTON (TOWN OF LONG VALLEY ONLY))) | $57.97 | $40.22 | $98.19 |
| PIPEFITTER (MORRIS COUNTY (BOROUGH OF CHATHAM; TOWNSHIP OF CHATHAM; BOROUGH OF CHESTER; TOWNSHIPS OF CHESTER, HARDING AND LONG HILL; BOROUGH OF MENDHAM; TOWNSHIPS OF MENDHAM AND MOUNT OLIVE; TOWNSHIP OF WASHINGTON (TOWN OF LONG VALLEY ONLY)) | $56.34 | $50.80 | $107.14 |
| PRESIDENT'S DAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED THAT THE WORKER HAS BEEN ASSIGNED TO WORK, OR, "SHAPES", ONE DAY OF THE CALENDAR WEEK DURING WHICH THE HOLIDAY OCCURS | $46.51 | $31.82 | $78.33 |
| HOLIDAYS: NEW YEAR'S DAY, PRESIDENT'S DAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED THAT THE WORKER HAS BEEN ASSIGNED TO WORK, OR, "SHAPES", ONE DAY OF THE CALENDAR WEEK DURING WHICH THE HOLIDAY OCCURS | $46.41 | $31.82 | $78.23 |