NJ20260038: rev 0 → rev 1
6 rate changes, 3 added, 3 removed.
Rate changes
Rates below include fringe (the full hourly package). Enter your remaining crew hours per classification to price this change for a job.
| Classification | Old total | New total | Δ/hr | Hours on job | Cost impact |
|---|---|---|---|---|---|
| CARPENTER (INCLUDING ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORMWORK, BATT AND BLOWN INSULATION) | $57.57 | $91.59 | +34.02 | — | |
| SOFT FLOOR LAYER | $57.57 | $91.59 | +34.02 | — | |
| MILLWRIGHT Work of erection and dismantling of elevators and towers, such as concrete conveyors and temporary material elevators, scaffolding or other structures to be used as scaffolding inside or outside of buildings: the first sixty feet at the regular rate, 10% per hour additional for each additional fifty feet thereafter | $59.04 | $93.90 | +34.86 | — | |
| ELECTRICIAN, INCLUDING LOW VOLTAGE WIRING: CABLE SPLICER. WORK FORTY FT. OR MORE ABOVE THE GROUND OR PROTECTIVE RIGGING (DOES NOT APPLY TO POLE WORK, OR TO USE OF A MANLIFT OR HIGH REACH-TYPE LIFT): 10% PER HOUR ADDITIONAL. WORK WITH, OR THE REMOVAL OF, ASBESTOS MATERIALS: 112% TIMES THE JOURNEYMAN RATE | $133.22 | $113.99 | -19.23 | — | |
| ELECTRICIAN, INCLUDING LOW VOLTAGE WIRING: ELECTRICIAN. WORK FORTY FT. OR MORE ABOVE THE GROUND OR PROTECTIVE RIGGING (DOES NOT APPLY TO POLE WORK, OR TO USE OF A MANLIFT OR HIGH REACH-TYPE LIFT): 10% PER HOUR ADDITIONAL. WORK WITH, OR THE REMOVAL OF, ASBESTOS MATERIALS: 112% TIMES THE JOURNEYMAN RATE | $130.93 | $108.29 | -22.64 | — | |
| GLAZIER WORK WELDING OR USING A CUTTING TORCH: $1.00 PER HOUR ADDITIONAL. WORK ON A SWING STAGE SCAFFOLD; ON A PIPE SCAFFOLD PROVIDING THE WORKING HEIGHT OF THE PLATFORM IS 30 FT. OR ABOVE; AND ON MOTORIZED LIFTS PROVIDED THAT THE HEIGHT OF THE LIFT PLATFORM IS ABOVE THE SECOND FLOOR OR ABOVE THIRTY FEET: $1.00 PER HOUR ADDITIONAL | $77.65 | $83.97 | +6.32 | — |
Added classifications
| CARPENTER (SCAFFOLD The first sixty feet at the regular rate, 10% per hour additional for each additional fifty feet thereafter | $57.42 | $34.17 |
| ELEVATOR MECHANIC: ALL OTHER PAID HOLIDAYS: New Year's Day, President's Day, Good Friday, Memorial Day, Fourth of July, Labor Day, Columbus Day, Veteran's Day, Thanksgiving Day, the Friday after Thanksgiving Day, and Christmas PAID VACATION: A worker who has worked less than 5 years: 4% of his or her hourly rate for all hours worked. A worker who has worked 5 to 10 years: 6% of his or her hourly rate for all hours worked. A worker who has worked 15 or more years: 8% of his or her hourly rate for all hours worked | $57.01 | $27.60 |
| ELEVATOR MECHANIC Work on the addition, replacement, refurbishing or relocation of control, drive, generating equipment, hoistway or pit equipment, including work involving a structural rise in the elevator shafts in an existing building and other elevator work in the machine room, hoistway or pit; Also, changes in design and appearance of basic escalator equipment. PAID HOLIDAYS: New Year's Day, President's Day, Good Friday, Memorial Day, Fourth of July, Labor Day, Columbus Day, Veteran's Day, Thanksgiving Day, the Friday after Thanksgiving Day, and Christmas PAID VACATION: A worker who has worked less than 5 years: 4% of his or her hourly rate for all hours worked. A worker who has worked 5 to 10 years: 6% of his or her hourly rate for all hours worked. A worker who has worked 15 or more years: 8% of his or her hourly rate for all hours worked | $45.14 | $27.45 |
Removed classifications
| CARPENTER (Scaffold Builder) | was $57.42 |
| basic escalator equipment | was $45.14 |
| All other work | was $57.01 |