Current rates (rev 1)
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR: INCLUDES THE APPLICATION OF ALL INSULATING MATERIALS, PROTECTIVE COVERINGS, COATINGS AND FINISHINGS TO ALL TYPES OF MECHANICAL SYSTEMS; ALSO, THE APPLICATION OF FIRESTOPPING MATERIAL TO OPENINGS AND PENETRATIONS IN WALLS, FLOORS, CEILINGS AND CURTAIN WALLS; ALSO, ALL LEAD ABATEMENT (MIDDLESEX COUNTY (Boroughs of Carteret and Dunellen; Township of Edison; Boroughs of Highland Park, Metuchen and Middlesex; City of New Brunswick; Township of Old Bridge; City of PerthAmboy; Township of Piscataway; Borough of Sayreville; City of South Amboy; Boroughs of South Plainfield and South River; Township of Woodbridge) | $51.74 | $46.20 | $97.94 |
| ASBESTOS WORKER/HEAT & FROST INSULATOR: INCLUDES THE APPLICATION OF ALL INSULATING MATERIALS, PROTECTIVE COVERINGS, COATINGS AND FINISHINGS TO ALL TYPES OF MECHANICAL SYSTEMS; ALSO, THE APPLICATION OF FIRESTOPPING MATERIAL TO OPENINGS AND PENETRATIONS IN WALLS, FLOORS, CEILINGS AND CURTAIN WALLS; ALSO, ALL LEAD ABATEMENT (MIDDLESEX COUNTY (does not include the Boroughs of Carteret and Dunellen; Township of Edison; Boroughs of Highland Park, Metuchen and Middlesex; City of New Brunswick; Township of Old Bridge; City of Perth Amboy; Township of Piscataway; Borough of Sayreville; City of South Amboy; Boroughs of South Plainfield and South River; Township of Woodbridge) PAID HOLIDAYS: The last day prior to the Christmas and New Year's Day observed holiday: 4 hrs. pay | $55.80 | $40.80 | $96.60 |
| BRICKLAYER Work on high stacks: 22% per hour additional | $43.56 | $32.50 | $76.06 |
| TILE SETTER (MIDDLESEX COUNTY (NORTH OF ROUTE 33)) | $64.90 | $37.28 | $102.18 |
| TILE FINISHER (MIDDLESEX COUNTY (NORTH OF ROUTE 33)) WORK GROUTING ALL EPOXY: $10.00 ADDITIONAL PER DAY | $50.05 | $33.90 | $83.95 |
| TILE SETTER (MIDDLESEX COUNTY (SOUTH OF ROUTE 33)) | $64.90 | $37.28 | $102.18 |
| TILE FINISHER (MIDDLESEX COUNTY (SOUTH OF ROUTE 33)) WORK GROUTING ALL EPOXY: $10.00 ADDITIONAL PER DAY | $50.05 | $33.90 | $83.95 |
| CARPENTER (SCAFFOLD The first sixty feet at the regular rate, 10% per hour additional for each additional fifty feet thereafter | $57.42 | $34.17 | $91.59 |
| CARPENTER (INCLUDING ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING AND FORMWORK) | $57.42 | $34.17 | $91.59 |
| MILLWRIGHT Work of erection and dismantling of elevators and towers, such as concrete conveyors and temporary material elevators, scaffolding or other structures to be used as scaffolding inside or outside of buildings: the first sixty feet at the regular rate, 10% per hour additional for each additional fifty feet thereafter | $58.84 | $35.06 | $93.90 |
| ELECTRICIAN, INCLUDING LOW VOLTAGE WIRING: ELECTRICIAN WORK ON LINE VOLTAGE OF 440 VOLTS AND OVER: 10% PER HOUR ADDITIONAL. WORK FROM TRUSSES, SCAFFOLDS AND LADDERS 40 FT. OR MORE FROM THE GROUND OR FLOOR; OR UNDER AIR PRESSURE; OR OVER CONVEYORS OR MOVING EQUIPMENT OR MACHINERY: 10% PER HOUR ADDITIONAL | $61.40 | $39.14 | $100.54 |
| ELECTRICIAN, INCLUDING LOW VOLTAGE WIRING: CABLE SPLICER WORK ON LINE VOLTAGE OF 440 VOLTS AND OVER: 10% PER HOUR ADDITIONAL. WORK FROM TRUSSES, SCAFFOLDS AND LADDERS 40 FT. OR MORE FROM THE GROUND OR FLOOR; OR UNDER AIR PRESSURE; OR OVER CONVEYORS OR MOVING EQUIPMENT OR MACHINERY: 10% PER HOUR ADDITIONAL | $65.35 | $46.56 | $111.91 |
| ELEVATOR MECHANIC Work on the addition, replacement, refurbishing or relocation of control, drive, generating equipment, hoistway or pit equipment, including work involving a structural rise in the elevator shafts in an existing building and other elevator work in the machine room, hoistway or pit; Also, changes in design and appearance of basic escalator equipment. PAID HOLIDAYS: New Year's Day, President's Day, Good Friday, Memorial Day, Fourth of July, Labor Day, Columbus Day, Veteran's Day, Thanksgiving Day, the Friday after Thanksgiving Day, and Christmas PAID VACATION: A worker who has worked less than 5 years: 4% of his or her hourly rate for all hours worked. A worker who has worked 5 to 10 years: 6% of his or her hourly rate for all hours worked. A worker who has worked 15 or more years: 8% of his or her hourly rate for all hours worked | $45.14 | $27.46 | $72.60 |
| ELEVATOR MECHANIC: ALL OTHER WORK PAID HOLIDAYS: New Year's Day, President's Day, Good Friday, Memorial Day, Fourth of July, Labor Day, Columbus Day, Veteran's Day, Thanksgiving Day, the Friday after Thanksgiving Day, and Christmas PAID VACATION: A worker who has worked less than 5 years: 4% of his or her hourly rate for all hours worked. A worker who has worked 5 to 10 years: 6% of his or her hourly rate for all hours worked. A worker who has worked 15 or more years: 8% of his or her hourly rate for all hours worked | $57.01 | $27.61 | $84.62 |
| POWER EQUIPMENT OPERATORS: GROUP 5 OILER HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY | $52.88 | $37.50 | $90.38 |
| POWER EQUIPMENT OPERATORS: GROUP 4 BOBCAT/SKID LOADER; COMPRESSOR (SINGLE); FARM TRACTOR; FRONT END LOADER (UNDER 1 CU. YD.); HYDROSEEDER; ROLLER, GRADE; PUMP, HYDRAULIC HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY | $56.59 | $37.50 | $94.09 |
| POWER EQUIPMENT OPERATORS: GROUP 3 ASPHALT SPREADER; BULLDOZER;COMPRESSOR(2 OR 3) (IN BATTERY) (WITHIN 100 FT.); FORKLIFT; FRONT END LOADER (1 CU. YD. AND OVER BUT LESS THAN 2 CU. YD.); LULL; MECHANIC; PAVER, ASPHALT; ROLLER, BLACKTOP; TRACTOR; HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY | $58.22 | $37.50 | $95.72 |
| POWER EQUIPMENT OPERATORS: GROUP 2 BACKHOE LOADER COMBO; CONCRETE PUMPER; GRADER/BLADE (FINISH); HOIST; HYDRAULIC CRANE, 10 TONS AND UNDER; FRONT END LOADER (2 CU. YD. BUT LESS THAN 5 CU. YD.); SCRAPER; SIDE BOOM HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY | $60.13 | $37.50 | $97.63 |
| POWER EQUIPMENT OPERATORS: GROUP 1 BACKHOE, INCLUDING BACKHOE TRACK; BOOM; CONCRETE PAVING MACHINE; CRANE (ALL TYPES, INCLUDING OVERHEAD AND STRADDLE TRAVELING TYPE); DRILL (DOWN-THE-HOLE DRILL, ROTARY DRILL, SELF-PROPELLED HYDRAULIC DRILL, SELF-POWERED DRILL); ELEVATING GRADER; EXCAVATOR; FRONT END LOADER (5 CU. YD. AND OVER); PILEDRIVER (LENGTH OF BOOM, INCLUDING LENGTH OF LEADS, SHALL DETERMINE PREMIUM RATE APPLICABLE); TRENCHER HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY | $61.72 | $37.50 | $99.22 |
| IRONWORKERS: REINFORCING (MIDDLESEX COUNTY (NORTHERN HALF OF COUNTY)) | $49.94 | $50.32 | $100.26 |
| IRONWORKERS: STRUCTURAL, ORNAMENTAL, RIGGER (MIDDLESEX COUNTY (NORTHERN HALF OF COUNTY)) | $52.24 | $50.32 | $102.56 |
| IRONWORKER: STRUCTURAL, ORNAMENTAL, RIGGER (MIDDLESEX COUNTY (SOUTHERN HALF OF COUNTY)) HAZARDOUS WASTE REMOVAL WORK, ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS REQUIRED TO WEAR LEVEL A, B OR C PERSONAL PROTECTION: $3.00 PER HOUR ADDITIONAL | $54.24 | $38.40 | $92.64 |
| IRONWORKER: REINFORCING (MIDDLESEX COUNTY (SOUTHERN HALF OF COUNTY)) HAZARDOUS WASTE REMOVAL WORK, ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS REQUIRED TO WEAR LEVEL A, B OR C PERSONAL PROTECTION: $3.00 PER HOUR ADDITIONAL | $53.24 | $38.40 | $91.64 |
| ASBESTOS REMOVAL LABORER The removal, abatement, enclosure and decontamination of personal protective equipment, chemical protective clothing and machinery relating to asbestos and/or toxic and hazardous waste or materials which shall include but not necessarily be limited to: the erection, moving, servicing and dismantling of all enclosures, scaffolding and barricades; the operation of all tools and equipment normally used in the removal or abatement of asbestos and toxic or hazardous waste or materials; the labeling, bagging, cartoning, crating, or other packaging of materials for disposal; the clean-up of the worksite; and all other work incidental to the removal, abatement, encapsulation, enclosure, and decontamination of asbestos and toxic or hazardous waste or materials; and, in addition, all work tasks involved in the maintenance and operation of energy resource recovery plants (co-generation plants) | $28.37 | $21.62 | $49.99 |
| LABORER: MASON TENDER: BRICK/CEMENT/CONCRETE | $36.50 | $30.22 | $66.72 |
| LABORER: ASPHALT SHOVELER, ASPHALT SPREADER, COMMON OR GENERAL LABORER, LANDSCAPE LABORER, PIPELAYER, POWER TOOL OPERATOR AND SCREEDMAN | $35.75 | $30.22 | $65.97 |
| DRYWALL FINISHER/TAPER | $44.87 | $30.15 | $75.02 |
| PAINTER (BRUSH & ROLLER) | $45.55 | $29.86 | $75.41 |
| PAINTER (PAPERHANGER) | $45.55 | $29.86 | $75.41 |
| PAINTER (SPRAY) | $45.55 | $29.86 | $75.41 |
| GLAZIER WORK WELDING OR USING A CUTTING TORCH: $1.00 PER HOUR ADDITIONAL. WORK ON A SWING STAGE SCAFFOLD; ON A PIPE SCAFFOLD PROVIDING THE WORKING HEIGHT OF THE PLATFORM IS 30 FT. OR ABOVE; AND ON MOTORIZED LIFTS PROVIDED THAT THE HEIGHT OF THE LIFT PLATFORM IS ABOVE THE SECOND FLOOR OR ABOVE THIRTY FEET: $1.00 PER HOUR ADDITIONAL | $52.68 | $31.29 | $83.97 |
| PLASTERER | $38.37 | $31.64 | $70.01 |
| CEMENT MASON/CONCRETE FINISHER | $53.21 | $33.42 | $86.63 |
| PLUMBER: EXCLUDING HVAC PIPE INSTALLATION (MIDDLESEX COUNTY (DOES NOT INCLUDE THE BOROUGHS OF DUNELLEN AND MIDDLESEX; BOROUGH OF SOUTH PLAINFIELD)) | $59.57 | $46.45 | $106.02 |
| PIPEFITTER: INCLUDING HVAC PIPE INSTALLATION (MIDDLESEX COUNTY (DOES NOT INCLUDE THE BOROUGHS OF DUNELLEN AND MIDDLESEX; BOROUGH OF SOUTH PLAINFIELD)) | $59.57 | $46.45 | $106.02 |
| PIPEFITTER: SERVICE AND REPAIR (MIDDLESEX COUNTY (DOES NOT INCLUDE THE BOROUGHS OF DUNELLEN AND MIDDLESEX; BOROUGH OF SOUTH PLAINFIELD)) | $46.23 | $29.23 | $75.46 |
| PLUMBER: SERVICE AND REPAIR (MIDDLESEX COUNTY (DOES NOT INCLUDE THE BOROUGHS OF DUNELLEN AND MIDDLESEX; BOROUGH OF SOUTH PLAINFIELD)) | $46.23 | $29.23 | $75.46 |
| PLUMBER: EXCLUDING HVAC PIPE INSTALLATION (MIDDLESEX COUNTY (BOROUGHS OF DUNELLEN AND MIDDLESEX; TOWNSHIP OF PISCATAWAY; BOROUGH OF SOUTH PLAINFIELD)) | $62.09 | $45.05 | $107.14 |
| PIPEFITTER: INCLUDING HVAC PIPE INSTALLATION (MIDDLESEX COUNTY (BOROUGHS OF DUNELLEN AND MIDDLESEX; TOWNSHIP OF PISCATAWAY; BOROUGH OF SOUTH PLAINFIELD)) | $56.34 | $50.80 | $107.14 |
| ROOFER (INCLUDES ALL TYPES OF ROOFERS) (MIDDLESEX COUNTY (north and east of Route #18)) | $44.52 | $32.25 | $76.77 |
| ROOFER: SLATE AND TILE (MIDDLESEX COUNTY (SOUTH AND WEST OF ROUTE #18)) MOPPER, AND OPERATOR OF FELT-LAYING MACHINE: $.50 PER HOUR ADDITIONAL. WORK APPLYING ROOFING MATERIAL, ON ANY NEW CONSTRUCTION JOB, ON THOSE DAYS ON WHICH A FELT-LAYING MACHINE OR SLAG-DISPENSING MACHINE IS USED: $.50 PER HOUR ADDITIONAL. PAID HOLIDAY: THE LAST WORKING DAY BEFORE CHRISTMAS, TO BE PAID AT THE RATE OF FOUR HOURS PAY | $38.95 | $21.85 | $60.80 |
| ROOFER: SHINGLES (MIDDLESEX COUNTY (SOUTH AND WEST OF ROUTE #18)) MOPPER, AND OPERATOR OF FELT-LAYING MACHINE: $.50 PER HOUR ADDITIONAL. WORK APPLYING ROOFING MATERIAL, ON ANY NEW CONSTRUCTION JOB, ON THOSE DAYS ON WHICH A FELT-LAYING MACHINE OR SLAG-DISPENSING MACHINE IS USED: $.50 PER HOUR ADDITIONAL. PAID HOLIDAY: THE LAST WORKING DAY BEFORE CHRISTMAS, TO BE PAID AT THE RATE OF FOUR HOURS PAY | $35.95 | $21.85 | $57.80 |
| ROOFER: ALL OTHER WORK (MIDDLESEX COUNTY (SOUTH AND WEST OF ROUTE #18)) MOPPER, AND OPERATOR OF FELT-LAYING MACHINE: $.50 PER HOUR ADDITIONAL. WORK APPLYING ROOFING MATERIAL, ON ANY NEW CONSTRUCTION JOB, ON THOSE DAYS ON WHICH A FELT-LAYING MACHINE OR SLAG-DISPENSING MACHINE IS USED: $.50 PER HOUR ADDITIONAL. PAID HOLIDAY: THE LAST WORKING DAY BEFORE CHRISTMAS, TO BE PAID AT THE RATE OF FOUR HOURS PAY | $46.03 | $34.27 | $80.30 |
| SPRINKLER FITTER: FIRE SPRINKLERS (MIDDLESEX COUNTY (PRINCETON, SOUTH BRUNSWICK AND MONROE TOWNSHIPS)) | $69.97 | $41.35 | $111.32 |
| SPRINKLER FITTER: FIRE SPRINKLERS (MIDDLESEX COUNTY (REMAINDER OF COUNTY)) | $67.97 | $39.35 | $107.32 |
| SHEET METAL WORKER (INCLUDING HVAC DUCT INSTALLATION) | $59.08 | $47.06 | $106.14 |
| TRUCK DRIVER: OFF THE ROAD HAZARDOUS WASTE REMOVAL WORK: Work on a state or federally designated hazardous waste site, where the worker is in direct contact with hazardous material, and when personal protective equipment is required for respiratory, skin and eye protection: $3.00 per hour Work on a state or federally designated hazardous waste site, in a zone requiring Level A personal protection for any workers other than the truck driver: $3.00 per hour additional. Work on a state or federally designated hazardous waste site where the worker is not working in a zone requiring Level A, B or C personal protection: $1.00 per hour PAID HOLIDAYS: New Year's Day, President's Day, Decoration Day, Independence Day, Labor Day, Presidential Election Day, Veteran's Day, Thanksgiving Day and Christmas VACATION PAY CREDIT: Workers working or receiving pay for 80 days within a year receive one week paid vacation (48 hours); 125 days receive two weeks paid vacation (96 hours); 145 days receive 15 days paid vacation (120 hours); 15 years seniority and 145 days receive 4 weeks paid vacation (160 hours) | $48.78 | $42.66 | $91.44 |
| TRUCK DRIVER: DUMP HAZARDOUS WASTE REMOVAL WORK: Work on a state or federally designated hazardous waste site, where the worker is in direct contact with hazardous material, and when personal protective equipment is required for respiratory, skin and eye protection: $3.00 per hour Work on a state or federally designated hazardous waste site, in a zone requiring Level A personal protection for any workers other than the truck driver: $3.00 per hour additional. Work on a state or federally designated hazardous waste site where the worker is not working in a zone requiring Level A, B or C personal protection: $1.00 per hour PAID HOLIDAYS: New Year's Day, President's Day, Decoration Day, Independence Day, Labor Day, Presidential Election Day, Veteran's Day, Thanksgiving Day and Christmas VACATION PAY CREDIT: Workers working or receiving pay for 80 days within a year receive one week paid vacation (48 hours); 125 days receive two weeks paid vacation (96 hours); 145 days receive 15 days paid vacation (120 hours); 15 years seniority and 145 days receive 4 weeks paid vacation (160 hours) | $48.63 | $42.66 | $91.29 |