Building construction wages: Hunterdon, New Jersey

Wage determination NJ20260034 · Active · Standard · verify on SAM.gov

Hunterdon

Get an email when this determination changes.
Substantive rate changes only; no spam. Bidding a specific job? Pin a project instead to lock the revision that applied on your bid date.

Revision history

RevisionPublishedCompare
rev 22026-05-18diff vs rev 1
rev 12026-05-17diff vs rev 0
rev 02026-01-30original

Current rates (rev 2)

Download CSV
ClassificationRateFringeTotal
ASBESTOS WORKER/HEAT & FROST INSULATOR (Includes the application of all insulating materials, protective coverings, coatings and finishings to all types of mechanical systems; also, the application of firestopping material to openings and penetrations in walls, floors, ceilings and curtain walls; also, all lead abatement) (HUNTERDON COUNTY (Borough of Califon; Township of Tewksbury))$51.74$46.20$97.94
ASBESTOS WORKER/HEAT & FROST INSULATOR (Includes the application of all insulating materials, protective coverings, coatings and finishings to all types of mechanical systems; also, the application of firestopping material to openings and penetrations in walls, floors, ceilings and curtain walls; also, all lead abatement) (HUNTERDON COUNTY (does not include the Borough of Califon; Township of PAID HOLIDAYS: The last day prior to the Christmas and New Year's Day observed holiday: 4 hrs. pay$55.80$40.80$96.60
BRICKLAYER Work on high stacks: 22% per hour additional$45.20$33.26$78.46
CEMENT MASON$49.60$37.96$87.56
TILE SETTER$64.90$37.28$102.18
TILE FINISHER Work grouting all epoxy: $10.00 additional per day$50.05$33.90$83.95
CARPENTER (SCAFFOLD The first sixty feet at the regular rate, 10% per hour additional for each additional fifty feet thereafter$57.42$34.17$91.59
CARPENTER (INCLUDING ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORMWORK)$57.42$34.17$91.59
Work of erection and dismantling of elevators and towers, such as concrete conveyors and temporary material elevators, scaffolding or other structures to be used as scaffolding inside or outside of buildings: the first sixty feet at the regular rate, 10% per hour additional for each additional fifty feet thereafter$58.84$35.06$93.90
ELECTRICIAN (INCLUDING LOW VOLTAGE WIRING) (HUNTERDON COUNTY (Townships of Alexandria and Bethlehem; Boroughs of Bloomsbury and Califon; Town of Clinton; Township of Clinton; Township of Delaware (west of a line following County Route 523 from the Delaware River north to the Raritan Township line); Township of East Amwell (east of State Hwy. 31); Township of Franklin; Boroughs of Frenchtown, Glen Gardner, Hampton and High Bridge; Townships of Holland and Kingwood; Borough of Lebanon; Township of Lebanon; Borough of Milford; Township of Raritan (east of State Hwy. 31 and north of County Route 523); Townships of Readington, Tewksbury and Work forty ft. or more above the ground or protective rigging (does not apply to pole work, or to use of a manlift or high reach-type lift): 10% per hour Work with, or the removal of, asbestos materials: 114% times the journeyman rate$65.43$42.86$108.29
ELECTRICIAN (INCLUDING LOW VOLTAGE WIRING): CABLE SPLICER (HUNTERDON COUNTY (Townships of Alexandria and Bethlehem; Boroughs of Bloomsbury and Califon; Town of Clinton; Township of Clinton; Township of Delaware (west of a line following County Route 523 from the Delaware River north to the Raritan Township line); Township of East Amwell (east of State Hwy. 31); Township of Franklin; Boroughs of Frenchtown, Glen Gardner, Hampton and High Bridge; Townships of Holland and Kingwood; Borough of Lebanon; Township of Lebanon; Borough of Milford; Township of Raritan (east of State Hwy. 31 and north of County Route 523); Townships of Readington, Tewksbury and Work forty ft. or more above the ground or protective rigging (does not apply to pole work, or to use of a manlift or high reach-type lift): 10% per hour Work with, or the removal of, asbestos materials: 114% times the journeyman rate$69.72$44.27$113.99
ELECTRICIAN (INCLUDING LOW VOLTAGE WIRING) (HUNTERDON COUNTY (Township of Delaware (east of a line following County Route 523 from the Delaware River north to the Raritan Township line); Township of East Amwell (west of State Hwy. 31); Borough of Flemington; City of Lambertville; Township of Raritan (west of State Hwy. 31 and south of County Route 523); Borough of Stockton; Township of West Amwell))$63.82$41.99$105.81
ELEVATOR a. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Veteran's Day, Thanksgiving Day, the Friday after Thanksgiving Day, and Christmas b. VACATION PAY CREDIT: A worker with 6 months but less than 5 years of service receives two weeks vacation; a worker with 5 years or more of service receives three weeks vacation$61.41$38.44$99.85
POWER EQUIPMENT OPERATORS: GROUP 5 OILER HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY$52.88$37.50$90.38
POWER EQUIPMENT OPERATORS: GROUP 4 BOBCAT/SKID LOADER; COMPRESSOR (SINGLE); FARM TRACTOR; FRONT END LOADER (UNDER 1 CU. YD.); HYDROSEEDER; ROLLER, GRADE; PUMP, HYDRAULIC HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY$56.59$37.50$94.09
POWER EQUIPMENT OPERATORS: GROUP 3 ASPHALT SPREADER; BULLDOZER;COMPRESSOR(2 OR 3) (IN BATTERY) (WITHIN 100 FT.); FORKLIFT; FRONT END LOADER (1 CU. YD. AND OVER BUT LESS THAN 2 CU. YD.); LULL; MECHANIC; PAVER, ASPHALT; ROLLER, BLACKTOP; TRACTOR; HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY$58.22$37.50$95.72
POWER EQUIPMENT OPERATORS: GROUP 2 BACKHOE LOADER COMBO; CONCRETE PUMPER; GRADER/BLADE (FINISH); HOIST; HYDRAULIC CRANE, 10 TONS AND UNDER; FRONT END LOADER (2 CU. YD. BUT LESS THAN 5 CU. YD.); SCRAPER; SIDE BOOM HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY$60.13$37.50$97.63
POWER EQUIPMENT OPERATORS: GROUP 1 BACKHOE, INCLUDING BACKHOE TRACK; BOOM; CONCRETE PAVING MACHINE; CRANE (ALL TYPES, INCLUDING OVERHEAD AND STRADDLE TRAVELING TYPE); DRILL (DOWN-THE-HOLE DRILL, ROTARY DRILL, SELF-PROPELLED HYDRAULIC DRILL, SELF-POWERED DRILL); ELEVATING GRADER; EXCAVATOR; FRONT END LOADER (5 CU. YD. AND OVER); PILEDRIVER (LENGTH OF BOOM, INCLUDING LENGTH OF LEADS, SHALL DETERMINE PREMIUM RATE APPLICABLE); TRENCHER HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY$61.72$37.50$99.22
IRONWORKER: STRUCTURAL, ORNAMENTAL, RIGGER (Hunterdon County (Western Half of County))$52.24$50.32$102.56
IRONWORKER: REINFORCING (Hunterdon County (Western Half of County))$49.94$50.32$100.26
IRONWORKER: REINFORCING (Hunterdon County (Eastern Half of County))$53.24$38.40$91.64
IRONWORKER: STRUCTURAL, ORNAMENTAL, RIGGER (Hunterdon County (Eastern Half of County))$54.24$38.40$92.64
ASBESTOS REMOVAL LABORER The removal, abatement, enclosure and decontamination of personal protective equipment, chemical protective clothing and machinery relating to asbestos and/or toxic and hazardous waste or materials which shall include but not necessarily be limited to: the erection, moving, servicing and dismantling of all enclosures, scaffolding and barricades; the operation of all tools and equipment normally used in the removal or abatement of asbestos and toxic or hazardous waste or materials; the labeling, bagging, cartoning, crating, or other packaging of materials for disposal; the clean-up of the worksite; and all other work incidental to the removal, abatement, encapsulation, enclosure, and decontamination of asbestos and toxic or hazardous waste or materials; and, in addition, all work tasks involved in the maintenance and operation of energy resource recovery plants (co-generation plants)$28.37$21.62$49.99
LABORER: MASON TENDER: BRICK/CEMENT/CONCRETE$36.50$30.22$66.72
LABORER: ASPHALT SHOVELER, ASPHALT SPREADER, COMMON OR GENERAL LABORER, LANDSCAPE LABORER, PIPELAYER, POWER TOOL OPERATOR AND SCREEDMAN$35.75$30.22$65.97
DRYWALL FINISHER/TAPER$44.87$30.15$75.02
PAINTER (BRUSH & ROLLER)$45.55$29.86$75.41
PAINTER (PAPERHANGER)$45.55$29.86$75.41
PAINTER (SPRAY)$45.55$29.86$75.41
Work welding or using a cutting torch: $1.00 per hour additional. Work on a swing stage scaffold; on a pipe scaffold providing the working height of the platform is 30 ft. or above; and on motorized lifts provided that the height of the lift platform is above the second floor or above thirty feet: $1.00 per hour additional$52.68$31.29$83.97
PLASTERER$38.37$31.64$70.01
PLUMBER, EXCLUDING HVAC PIPE INSTALLATION (HUNTERDON COUNTY (south of a line drawn from a point where Bridge St. crosses the Delaware River, continuing along Bridge St. through Frenchtown to Rt. 513; then, continuing along Rt. 513 to Rt. 12; then, continuing along Rt. 12 to Rt. 31/202; then, continung south on Rt. 31/202 to Rt. 514 (Amwell Rd. or Old York Rd.); then, making a left turn in a northeasterly direction onto Rt. 514 (Amwell Rd. or Old York Rd.); then, continuing along Rt. 514 (Amwell Rd. or Old York Rd.) to Reaville and the intersection with County Rd. Rt. 609 (Manner's Rd.); then, making a right turn onto County Rd. Rt. 609 (Manner's Rd.); then, continuing south along County Rd. Rt. 609 (Manner's Rd.) until it reaches County Rd. Rt. 602 (Wertsville Rd.); then, making a right turn onto Rt. 602 (Wertsville Rd.); then, continuing south along Rt. 602 (Wertsville Rd.) until it reaches Rt. 607 (Rileyville Rd., also known as Hopewell - Wertsville Rd.); then, making a left turn onto Rt. 607 (Rileyville Rd., also known as Hopewell - Wertsville Rd.); then, continuing along Rt. 607 (Rileyville Rd., also known as Hopewell - Wertsville Rd.) until it reaches the Hunterdon/Mercer county line)$59.57$46.45$106.02
PIPEFITTER, INCLUDING HVAC PIPE INSTALLATION (HUNTERDON COUNTY (south of a line drawn from a point where Bridge St. crosses the Delaware River, continuing along Bridge St. through Frenchtown to Rt. 513; then, continuing along Rt. 513 to Rt. 12; then, continuing along Rt. 12 to Rt. 31/202; then, continung south on Rt. 31/202 to Rt. 514 (Amwell Rd. or Old York Rd.); then, making a left turn in a northeasterly direction onto Rt. 514 (Amwell Rd. or Old York Rd.); then, continuing along Rt. 514 (Amwell Rd. or Old York Rd.) to Reaville and the intersection with County Rd. Rt. 609 (Manner's Rd.); then, making a right turn onto County Rd. Rt. 609 (Manner's Rd.); then, continuing south along County Rd. Rt. 609 (Manner's Rd.) until it reaches County Rd. Rt. 602 (Wertsville Rd.); then, making a right turn onto Rt. 602 (Wertsville Rd.); then, continuing south along Rt. 602 (Wertsville Rd.) until it reaches Rt. 607 (Rileyville Rd., also known as Hopewell - Wertsville Rd.); then, making a left turn onto Rt. 607 (Rileyville Rd., also known as Hopewell - Wertsville Rd.); then, continuing along Rt. 607 (Rileyville Rd., also known as Hopewell - Wertsville Rd.) until it reaches the Hunterdon/Mercer county line)$59.57$46.45$106.02
PLUMBER/PIPEFITTER: SERVICE AND REPAIR (HUNTERDON COUNTY (south of a line drawn from a point where Bridge St. crosses the Delaware River, continuing along Bridge St. through Frenchtown to Rt. 513; then, continuing along Rt. 513 to Rt. 12; then, continuing along Rt. 12 to Rt. 31/202; then, continung south on Rt. 31/202 to Rt. 514 (Amwell Rd. or Old York Rd.); then, making a left turn in a northeasterly direction onto Rt. 514 (Amwell Rd. or Old York Rd.); then, continuing along Rt. 514 (Amwell Rd. or Old York Rd.) to Reaville and the intersection with County Rd. Rt. 609 (Manner's Rd.); then, making a right turn onto County Rd. Rt. 609 (Manner's Rd.); then, continuing south along County Rd. Rt. 609 (Manner's Rd.) until it reaches County Rd. Rt. 602 (Wertsville Rd.); then, making a right turn onto Rt. 602 (Wertsville Rd.); then, continuing south along Rt. 602 (Wertsville Rd.) until it reaches Rt. 607 (Rileyville Rd., also known as Hopewell - Wertsville Rd.); then, making a left turn onto Rt. 607 (Rileyville Rd., also known as Hopewell - Wertsville Rd.); then, continuing along Rt. 607 (Rileyville Rd., also known as Hopewell - Wertsville Rd.) until it reaches the Hunterdon/Mercer county line)$46.23$29.23$75.46
PLUMBER, EXCLUDING HVAC PIPE INSTALLATION (HUNTERDON COUNTY (north of a line drawn from a point where Bridge St. crosses the Delaware River, continuing along Bridge St. through Frenchtown to Rt. 513; then, continuing along Rt. 513 to Rt. 12; then, continuing along Rt. 12 to Rt. 31/202; then, continung south on Rt. 31/202 to Rt. 514 (Amwell Rd. or Old York Rd.); then, making a left turn in a northeasterly direction onto Rt. 514 (Amwell Rd. or Old York Rd.); then, continuing along Rt. 514 (Amwell Rd. or Old York Rd.) to Reaville and the intersection with County Rd. Rt. 609 (Manner's Rd.); then, making a right turn onto County Rd. Rt. 609 (Manner's Rd.); then, continuing south along County Rd. Rt. 609 (Manner's Rd.) until it reaches County Rd. Rt. 602 (Wertsville Rd.); then, making a right turn onto Rt. 602 (Wertsville Rd.); then, continuing south along Rt. 602 (Wertsville Rd.) until it reaches Rt. 607 (Rileyville Rd., also known as Hopewell -Wertsville Rd.); then, making a left turn onto Rt. 607 (Rileyville Rd., also known as Hopewell - Wertsville Rd.); then, continuing along Rt. 607 (Rileyville Rd., also known as Hopewell - Wertsville Rd.) until it reaches the Hunterdon - Mercer County line)$62.09$45.05$107.14
PIPEFITTER: INCLUDING HVAC PIPE INSTALLATION HUNTERDON COUNTY (north of a line drawn from a point where Bridge St. crosses the Delaware River, continuing along Bridge St. through Frenchtown to Rt. 513; then, continuing along Rt. 513 to Rt. 12; then, continuing along Rt. 12 to Rt. 31/202; then, continung south on Rt. 31/202 to Rt. 514 (Amwell Rd. or Old York Rd.); then, making a left turn in a northeasterly direction onto Rt. 514 (Amwell Rd. or Old York Rd.); then, continuing along Rt. 514 (Amwell Rd. or Old York Rd.) to Reaville and the intersection with County Rd. Rt. 609 (Manner's Rd.); then, making a right turn onto County Rd. Rt. 609 (Manner's Rd.); then, continuing south along County Rd. Rt. 609 (Manner's Rd.) until it reaches County Rd. Rt. 602 (Wertsville Rd.); then, making a right turn onto Rt. 602 (Wertsville Rd.); then, continuing south along Rt. 602 (Wertsville Rd.) until it reaches Rt. 607 (Rileyville Rd., also known as Hopewell - Wertsville Rd.); then, making a left turn onto Rt. 607 (Rileyville Rd., also known as Hopewell - Wertsville Rd.); then, continuing along Rt. 607 (Rileyville Rd., also known as Hopewell - Wertsville Rd.) until it reaches the Hunterdon/Mercer county line)$56.34$50.80$107.14
ROOFER: ALL OTHER Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machine or slag dispensing machine is used: $.50 per hour PAID HOLIDAY: The last working day before Christmas, to be paid at the rate of four hours pay$46.03$34.27$80.30
ROOFER: SLATE AND Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machine or slag dispensing machine is used: $.50 per hour PAID HOLIDAY: The last working day before Christmas, to be paid at the rate of four hours pay$38.95$21.85$60.80
ROOFER: Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machine or slag dispensing machine is used: $.50 per hour PAID HOLIDAY: The last working day before Christmas, to be paid at the rate of four hours pay$35.95$21.85$57.80
SPRINKLER FITTER (FIRE SPRINKLERS)$59.19$36.51$95.70
SHEET METAL WORKER (INCLUDING HVAC DUCT INSTALLATION)$59.08$47.06$106.14
TRUCK DRIVER: OFF THE ROAD HAZARDOUS WASTE REMOVAL WORK: Work on a state or federally designated hazardous waste site, where the worker is in direct contact with hazardous material, and when personal protective equipment is required for respiratory, skin and eye protection: $3.00 per hour Work on a state or federally designated hazardous waste site, in a zone requiring Level A personal protection for any workers other than the truck driver: $3.00 per hour additional. Work on a state or federally designated hazardous waste site where the worker is not working in a zone requiring Level A, B or C personal protection: $1.00 per hour PAID HOLIDAYS: New Year's Day, President's Day, Decoration Day, Independence Day, Labor Day, Presidential Election Day, Veteran's Day, Thanksgiving Day and Christmas VACATION PAY CREDIT: Workers working or receiving pay for 80 days within a year receive one week paid vacation (48 hours); 125 days receive two weeks paid vacation (96 hours); 145 days receive 15 days paid vacation (120 hours); 15 years seniority and 145 days receive 4 weeks paid vacation (160 hours)$48.78$42.66$91.44
TRUCK DRIVER: DUMP HAZARDOUS WASTE REMOVAL WORK: Work on a state or federally designated hazardous waste site, where the worker is in direct contact with hazardous material, and when personal protective equipment is required for respiratory, skin and eye protection: $3.00 per hour Work on a state or federally designated hazardous waste site, in a zone requiring Level A personal protection for any workers other than the truck driver: $3.00 per hour additional. Work on a state or federally designated hazardous waste site where the worker is not working in a zone requiring Level A, B or C personal protection: $1.00 per hour PAID HOLIDAYS: New Year's Day, President's Day, Decoration Day, Independence Day, Labor Day, Presidential Election Day, Veteran's Day, Thanksgiving Day and Christmas VACATION PAY CREDIT: Workers working or receiving pay for 80 days within a year receive one week paid vacation (48 hours); 125 days receive two weeks paid vacation (96 hours); 145 days receive 15 days paid vacation (120 hours); 15 years seniority and 145 days receive 4 weeks paid vacation (160 hours)$48.63$42.66$91.29