Building construction wages: Greene, North Carolina
Wage determination NC20260046 · Active · Standard · verify on SAM.gov
Retrieved from wagepin.com/wd/NC20260046 on · latest revision 1 · verify at sam.gov/wage-determination/NC20260046/1
Revision history
| Revision | Published | Compare |
|---|---|---|
| rev 1 | 2026-05-18 | diff vs rev 0 |
| rev 0 | 2026-05-17 | original |
Current rates (rev 1)
The CSV and the printed sheet are snapshots of rev 1. If DOL revises this determination after you save one, the watch above tells you exactly what moved.
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| IRONWORKER, STRUCTURAL | $29.75 | $18.00 | $47.75 |
| PIPEFITTER | $31.66 | $12.69 | $44.35 |
| TRUCK DRIVER | $13.38 | $1.48 | $14.86 |
| SHEET METAL WORKER, EXCLUDES HVAC DUCT INSTALLATION | $15.81 | $1.40 | $17.21 |
| ROOFER | $11.06 | $1.26 | $12.32 |
| PLUMBER | $19.70 | $2.34 | $22.04 |
| PAINTER: BRUSH, ROLLER AND SPRAY | $12.35 | $0.00 | $12.35 |
| OPERATOR: LOADER | $16.17 | $0.25 | $16.42 |
| OPERATOR: GRADER/BLADE | $15.72 | $1.49 | $17.21 |
| OPERATOR: FORKLIFT | $13.86 | $0.00 | $13.86 |
| OPERATOR: CRANE | $19.77 | $4.48 | $24.25 |
| OPERATOR: BULLDOZER | $16.00 | $1.87 | $17.87 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $18.23 | $2.16 | $20.39 |
| LABORER: MASON TENDER-BRICK/CEMENT/CONCRETE | $12.00 | $0.00 | $12.00 |
| LABORER: PIPELAYER | $13.35 | $2.80 | $16.15 |
| LABORER: LANDSCAPE & IRRIGATION | $9.13 | $0.28 | $9.41 |
| LABORER: COMMON OR GENERAL | $10.20 | $0.00 | $10.20 |
| HVAC MECHANIC (HVAC DUCT INSTALLATION ONLY) | $19.69 | $2.25 | $21.94 |
| ELECTRICIAN | $18.31 | $3.06 | $21.37 |
| DRYWALL HANGER | $13.83 | $0.00 | $13.83 |
| CEMENT MASON/CONCRETE FINISHER | $15.50 | $0.00 | $15.50 |
| CARPENTER, EXCLUDES DRYWALL HANGING, AND FORM WORK | $15.91 | $3.87 | $19.78 |
| CARPENTER (FORM WORK ONLY) | $12.43 | $1.80 | $14.23 |
| BRICKLAYER | $19.00 | $0.00 | $19.00 |
Spot a rate that looks wrong? Email me the details and I’ll check it against the SAM.gov document.