Highway construction wages: Bolivar, Mississippi
Wage determination MS20260082 · Active · Standard · verify on SAM.gov
Retrieved from wagepin.com/wd/MS20260082 on · latest revision 1 · verify at sam.gov/wage-determination/MS20260082/1
Revision history
| Revision | Published | Compare |
|---|---|---|
| rev 1 | 2026-05-18 | diff vs rev 0 |
| rev 0 | 2026-05-17 | original |
Current rates (rev 1)
The CSV and the printed sheet are snapshots of rev 1. If DOL revises this determination after you save one, the watch above tells you exactly what moved.
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| TRUCK DRIVER: SEMI/TRAILER TRUCK | $15.29 | $0.00 | $15.29 |
| TRUCK DRIVER: DUMP TRUCK (ALL TYPES) | $12.00 | $0.00 | $12.00 |
| TRUCK DRIVER: WATER TRUCK | $10.89 | $0.00 | $10.89 |
| TRUCK DRIVER: OFF THE ROAD TRUCK | $12.29 | $0.00 | $12.29 |
| TRUCK DRIVER: MECHANIC | $14.08 | $0.00 | $14.08 |
| TRUCK DRIVER: LOWBOY TRUCK | $13.80 | $0.00 | $13.80 |
| TRUCK DRIVER: FLATBED TRUCK | $12.64 | $0.00 | $12.64 |
| OPERATOR: TRENCHER | $15.00 | $0.00 | $15.00 |
| OPERATOR: TRACTOR | $11.46 | $0.00 | $11.46 |
| OPERATOR: SCRAPER | $12.96 | $0.00 | $12.96 |
| OPERATOR: ROLLER (ALL TYPES) | $11.48 | $0.00 | $11.48 |
| OPERATOR: PILEDRIVER | $15.13 | $0.00 | $15.13 |
| OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE) | $12.69 | $0.00 | $12.69 |
| OPERATOR: OILER | $12.33 | $0.48 | $12.81 |
| OPERATOR: MILLING MACHINE | $18.16 | $0.00 | $18.16 |
| OPERATOR: MECHANIC | $15.32 | $0.00 | $15.32 |
| OPERATOR: LOADER | $12.21 | $0.00 | $12.21 |
| OPERATOR: GRINDING/GROOVING MACHINE | $15.94 | $0.00 | $15.94 |
| OPERATOR: GRADER/BLADE | $14.44 | $0.00 | $14.44 |
| OPERATOR: DRILL | $19.22 | $0.00 | $19.22 |
| OPERATOR: DISTRIBUTOR | $12.38 | $0.00 | $12.38 |
| OPERATOR: CRANE | $21.25 | $0.00 | $21.25 |
| OPERATOR: CONCRETE SAW | $12.95 | $0.00 | $12.95 |
| OPERATOR: BULLDOZER | $11.58 | $0.00 | $11.58 |
| OPERATOR: BROOM/SWEEPER | $10.77 | $0.00 | $10.77 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $13.38 | $0.00 | $13.38 |
| OPERATOR: ASPHALT SPREADER | $16.03 | $0.00 | $16.03 |
| LABORER: LABORER-CONES/ BARRICADES/BARRELS - SETTER/MOVER/SWEEPER | $15.15 | $0.00 | $15.15 |
| LABORER: PIPELAYER | $11.34 | $0.00 | $11.34 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $11.08 | $0.00 | $11.08 |
| LABORER: LANDSCAPE | $9.77 | $0.00 | $9.77 |
| LABORER: GRADE CHECKER | $11.32 | $0.00 | $11.32 |
| LABORER: FLAGGER | $11.48 | $0.00 | $11.48 |
| LABORER: COMMON OR GENERAL, INCLUDING ASPHALT RAKING, SHOVELING, SPREADING AND CONCRETE WORK | $11.01 | $0.00 | $11.01 |
| IRONWORKER, REINFORCING | $16.29 | $0.00 | $16.29 |
| INSTALLER - SIGN | $11.73 | $0.00 | $11.73 |
| INSTALLER - GUARDRAIL | $11.42 | $0.00 | $11.42 |
| HIGHWAY/PARKING LOT STRIPING: TRUCK DRIVER (LINE STRIPING TRUCK) | $14.11 | $0.00 | $14.11 |
| ELECTRICIAN | $21.80 | $7.93 | $29.73 |
| CEMENT MASON/CONCRETE FINISHER | $13.13 | $0.00 | $13.13 |
| CARPENTER, EXCLUDES FORM WORK | $14.03 | $0.00 | $14.03 |
| CARPENTER (FORM WORK ONLY) | $12.28 | $0.00 | $12.28 |
Spot a rate that looks wrong? Email me the details and I’ll check it against the SAM.gov document.