Building construction wages: Shannon, Missouri
Wage determination MO20260023 · Active · Standard · verify on SAM.gov
Retrieved from wagepin.com/wd/MO20260023 on · latest revision 1 · verify at sam.gov/wage-determination/MO20260023/1
Revision history
| Revision | Published | Compare |
|---|---|---|
| rev 1 | 2026-05-18 | diff vs rev 0 |
| rev 0 | 2026-05-17 | original |
Current rates (rev 1)
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR | $31.97 | $14.00 | $45.97 |
| BRICKLAYER | $33.67 | $19.48 | $53.15 |
| TILE SETTER | $26.47 | $14.89 | $41.36 |
| CARPENTER, INCLUDING FORMWORK (PROJECTS UNDER $1.5 MILLION) | $33.05 | $21.85 | $54.90 |
| CARPENTER, INCLUDING FORMWORK (PROJECTS $1.5 MILLION AND OVER) | $36.57 | $21.85 | $58.42 |
| CARPENTER (FLOOR LAYER) (VINYL INSTALLATION ONLY) | $40.08 | $21.85 | $61.93 |
| ELECTRICIAN | $32.40 | $19.11 | $51.51 |
| ELEVATOR MECHANIC | $62.73 | $38.44 | $101.17 |
| POWER EQUIPMENT OPERATOR: ROLLER | $39.06 | $30.38 | $69.44 |
| POWER EQUIPMENT OPERATOR: BULLDOZER | $39.06 | $30.38 | $69.44 |
| POWER EQUIPMENT OPERATOR: (PAVER) | $39.06 | $30.38 | $69.44 |
| POWER EQUIPMENT OPERATOR: (LOADER) | $39.06 | $30.38 | $69.44 |
| POWER EQUIPMENT OPERATOR: (BACKHOE/EXCAVATOR/ TRACKHOE) | $39.06 | $30.38 | $69.44 |
| IRONWORKER: REINFORCING AND STRUCTURAL | $41.67 | $31.25 | $72.92 |
| LABORER (BRICK MASON TENDER) | $32.23 | $15.91 | $48.14 |
| CEMENT MASON/CONCRETE FINISHER | $36.63 | $9.85 | $46.48 |
| PLUMBER, EXCLUDES HVAC PIPE INSTALLATION (ON ANY WORK UNDER 7.0 MILLION TOTAL OF ALL PROJECT MECHANICAL CONTRACTS OUTSTATE AREA WAGES AND FRINGES) | $50.66 | $23.34 | $74.00 |
| PLUMBER, EXCLUDES HVAC PIPE INSTALLATION (ON ANY WORK OVER $7.0 MILLION TOTAL OF ALL PROJECT MECHANICAL CONTRACTS ST. LOUIS AREA WAGES AND FRINGES.) | $52.60 | $29.93 | $82.53 |
| PIPEFITTER, INCLUDES HVAC PIPE INSTALLATION (ON ANY WORK UNDER 7.0 MILLION TOTAL OF ALL PROJECT MECHANICAL CONTRACTS OUTSTATE AREA WAGES AND FRINGES) | $50.66 | $23.34 | $74.00 |
| PIPEFITTER, INCLUDES HVAC PIPE INSTALLATION (ON ANY WORK OVER $7.0 MILLION TOTAL OF ALL PROJECT MECHANICAL CONTRACTS ST. LOUIS AREA WAGES AND FRINGES.) | $52.60 | $29.93 | $82.53 |
| ROOFER | $32.25 | $17.46 | $49.71 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | $45.94 | $27.53 | $73.47 |
| SHEET METAL WORKER, INCLUDES HVAC DUCT AND UNIT INSTALLATION | $34.43 | $17.86 | $52.29 |
| TRUCK DRIVER: DUMP TRUCK | $25.57 | $0.00 | $25.57 |
| PAINTER: SPRAY | $18.79 | $8.12 | $26.91 |
| PAINTER: ROLLER | $16.44 | $6.01 | $22.45 |
| PAINTER: BRUSH ONLY | $16.44 | $6.01 | $22.45 |
| OPERATOR: GRADER/BLADE | $22.80 | $10.78 | $33.58 |
| LABORER: COMMON OR GENERAL | $25.00 | $0.00 | $25.00 |