Building construction wages: Gratiot, Michigan
Wage determination MI20260122 · Active · Standard · verify on SAM.gov
Retrieved from wagepin.com/wd/MI20260122 on · latest revision 1 · verify at sam.gov/wage-determination/MI20260122/1
Revision history
| Revision | Published | Compare |
|---|---|---|
| rev 1 | 2026-05-18 | diff vs rev 0 |
| rev 0 | 2026-05-17 | original |
Current rates (rev 1)
The CSV and the printed sheet are snapshots of rev 1. If DOL revises this determination after you save one, the watch above tells you exactly what moved.
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR | $40.00 | $23.65 | $63.65 |
| BOILERMAKER | $43.50 | $37.64 | $81.14 |
| TILE SETTER | $31.43 | $21.13 | $52.56 |
| PLASTERER | $33.09 | $26.58 | $59.67 |
| CARPENTER (ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORM WORK, AND METAL STUD INSTALLATION) | $35.86 | $23.69 | $59.55 |
| MILLWRIGHT | $42.92 | $39.13 | $82.05 |
| ELECTRICIAN: EXCLUDES LOW VOLTAGE WIRING (TOWNSHIPS OF ARCADA, BETHANY, ELBA, EMERSON, HAMILTON, LAFAYETTE, NEW HAVEN, NEWARK, NORTH STAR, PINE RIVER, SEVILLE, SUMNER, WASHINGTON, & WHEELER) | $34.25 | $23.13 | $57.38 |
| OPERATOR: POWER EQUIPMENT: GROUP 6 OILER CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $31.23 | $25.25 | $56.48 |
| OPERATOR: POWER EQUIPMENT: GROUP 5 FORK TRUCK (20' LIFT AND UNDER FOR MASONRY WORK) CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $33.71 | $25.25 | $58.96 |
| OPERATOR: POWER EQUIPMENT: GROUP 4 BOBCAT/SKID LOADER; FORK TRUCK (OVER 20' LIFT) CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $39.57 | $25.25 | $64.82 |
| OPERATOR: POWER EQUIPMENT: GROUP 3 BACKHOE/EXCAVATOR; CRANE; LOADER; PAVER; SCRAPER; STIFF LEG DERRICK CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $41.28 | $25.25 | $66.53 |
| OPERATOR: POWER EQUIPMENT: GROUP 2 CRANE OPERATOR WITH MAIN BOOM AND JIB 140' OR LONGER; TOWER CRANE; GANTRY CRANE AND WHIRLEY DERRICK CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $43.93 | $25.25 | $69.18 |
| OPERATOR: POWER EQUIPMENT: GROUP 1 CRANE OPERATOR WITH MAIN BOOM AND JIB 400', 300', OR 220' OR LONGER. CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $47.28 | $25.25 | $72.53 |
| IRONWORKER: STRUCTURAL (METAL BUILDING ERECTION ONLY) | $30.02 | $27.43 | $57.45 |
| IRONWORKER, STRUCTURAL | $36.55 | $35.93 | $72.48 |
| IRONWORKER, REINFORCING | $36.55 | $33.37 | $69.92 |
| LABORER: SANDBLASTER | $28.21 | $13.45 | $41.66 |
| LABORER: MASON TENDER - CEMENT/CONCRETE AND PIPELAYER | $27.68 | $13.45 | $41.13 |
| PAINTER: DRYWALL FINISHING/TAPING | $30.22 | $22.22 | $52.44 |
| PAINTER: BRUSH, ROLLER AND SPRAY | $29.23 | $19.11 | $48.34 |
| CEMENT MASON/CONCRETE FINISHER | $25.47 | $12.38 | $37.85 |
| PLUMBER (EXCLUDING HVAC PIPE AND SYSTEM INSTALLATION) | $43.50 | $22.10 | $65.60 |
| PIPEFITTER (HVAC PIPE INSTALLATION ONLY) | $45.50 | $21.75 | $67.25 |
| PIPEFITTER (EXCLUDES HVAC PIPE AND SYSTEM INSTALLATION) | $45.50 | $21.75 | $67.25 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | $41.34 | $27.39 | $68.73 |
| SHEET METAL WORKER (HVAC DUCT & SYSTEM INSTALLATION) | $26.83 | $23.78 | $50.61 |
| SHEET METAL WORKER (EXCLUDING HVAC DUCT & SYSTEM INSTALLATION) | $26.83 | $23.78 | $50.61 |
| TRUCK DRIVER: FLATBED TRUCK | $16.80 | $3.97 | $20.77 |
| TRUCK DRIVER, INCLUDES DUMP AND TANDEM TRUCK | $15.65 | $3.12 | $18.77 |
| ROOFER | $15.73 | $7.41 | $23.14 |
| OPERATOR: TRACTOR | $19.60 | $7.31 | $26.91 |
| OPERATOR: ROLLER | $28.02 | $7.07 | $35.09 |
| OPERATOR: GRADER/BLADE | $24.04 | $6.03 | $30.07 |
| OPERATOR: BULLDOZER | $22.34 | $1.22 | $23.56 |
| LABORER: MASON TENDER - BRICK | $15.03 | $3.10 | $18.13 |
| LABORER: LANDSCAPE & IRRIGATION | $12.84 | $0.00 | $12.84 |
| LABORER: COMMON OR GENERAL | $10.70 | $1.22 | $11.92 |
| GLAZIER | $16.95 | $4.74 | $21.69 |
| CARPENTER, EXCLUDES ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORM WORK, METAL STUD INSTALLATION, AND SOFT FLOOR LAYING-CARPET | $15.80 | $1.22 | $17.02 |
| CARPENTER (FLOOR LAYING-CARPET ONLY) | $19.59 | $7.57 | $27.16 |
| BRICKLAYER | $22.20 | $3.10 | $25.30 |
Spot a rate that looks wrong? Email me the details and I’ll check it against the SAM.gov document.