Building construction wages: Allegan, Michigan
Wage determination MI20260104 · Active · Standard · verify on SAM.gov
Retrieved from wagepin.com/wd/MI20260104 on · latest revision 1 · verify at sam.gov/wage-determination/MI20260104/1
Revision history
| Revision | Published | Compare |
|---|---|---|
| rev 1 | 2026-05-18 | diff vs rev 0 |
| rev 0 | 2026-05-17 | original |
Current rates (rev 1)
The CSV and the printed sheet are snapshots of rev 1. If DOL revises this determination after you save one, the watch above tells you exactly what moved.
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| BOILERMAKER | $43.50 | $37.64 | $81.14 |
| TILE SETTER (ALLEGAN COUNTY (TOWNSHIPS OF BRADLEY, DORR, GREEN LAKE, & HOPKINS)) | $32.20 | $23.46 | $55.66 |
| BRICKLAYER (ALLEGAN COUNTY (TOWNSHIPS OF BRADLEY, DORR, GREEN LAKE, & HOPKINS)) | $35.21 | $24.34 | $59.55 |
| TILE SETTER (TOWNSHIPS OF ALLEGAN, CASCO, CHESHIRE, CLYDE, GRANGES, GUN PLAIN, LEE, MARTIN, OTSEGO, TROWBRIDGE, VALLEY & WATSON) | $32.20 | $23.46 | $55.66 |
| BRICKLAYER (TOWNSHIPS OF ALLEGAN, CASCO, CHESHIRE, CLYDE, GRANGES, GUN PLAIN, LEE, MARTIN, OTSEGO, TROWBRIDGE, VALLEY & WATSON) | $35.21 | $24.34 | $59.55 |
| CARPENTER (EXCLUDES ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORM WORK, METAL STUD INSTALLATION, AND SOFT FLOOR LAYER-CARPET) | $31.50 | $21.15 | $52.65 |
| CARPENTER (ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORM WORK, METAL STUD INSTALLATION) | $31.50 | $21.15 | $52.65 |
| MILLWRIGHT | $40.04 | $26.47 | $66.51 |
| ELECTRICIAN: EXCLUDES LOW VOLTAGE WIRING (TOWNSHIPS OF ALLEGAN, CASCO, CHESHIRE, CLYDE, GANGES, GUN PLAIN, HEATH, HOPKINS, LEE, MANLIUS, MARTIN, MONTEREY, OTSEGO, SAUGATUCK, TROWBRIDGE, VALLEY, WATSON & WAYLAND) | $42.78 | $21.84 | $64.62 |
| ELECTRICIAN: EXCLUDES LOW VOLTAGE WIRING (TOWNSHIPS OF DORR, FILLMORE, LAKETON, LEIGHTON, OVERISEL, & SALEM) | $35.68 | $23.36 | $59.04 |
| POWER EQUIPMENT OPERATOR: GROUP 5 OILER CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $31.23 | $25.25 | $56.48 |
| POWER EQUIPMENT OPERATOR: GROUP 4 BOBCAT/SKID LOADER CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $39.57 | $25.25 | $64.82 |
| POWER EQUIPMENT OPERATOR: GROUP 3 BACKHOE/EXCAVATOR; CRANE; LOADER; PAVER; SCRAPER; STIFF LEG DERRICK CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $41.28 | $25.25 | $66.53 |
| POWER EQUIPMENT OPERATOR: GROUP 2 CRANE OPERATOR WITH MAIN BOOM AND JIB 140' OR LONGER; TOWER CRANE; GANTRY CRANE AND WHIRLEY DERRICK CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $43.93 | $25.25 | $69.18 |
| POWER EQUIPMENT OPERATOR: GROUP 1 CRANE OPERATOR WITH MAIN BOOM AND JIB 400', 300', OR 220' OR LONGER. CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $47.28 | $25.25 | $72.53 |
| IRONWORKER: STRUCTURAL | $36.55 | $29.51 | $66.06 |
| IRONWORKER: REINFORCING | $36.55 | $29.51 | $66.06 |
| IRONWORKER: STRUCTURAL (METAL BUILDING ERECTION ONLY) | $30.02 | $27.43 | $57.45 |
| LABORER: MASON TENDER - BRICK; MASON TENDER - CEMENT/CONCRETE | $30.72 | $12.95 | $43.67 |
| LABORER : COMMON OR GENERAL; SANDBLASTER | $27.21 | $13.45 | $40.66 |
| PLASTERER | $21.18 | $12.43 | $33.61 |
| PLUMBER: EXCLUDING HVAC PIPE & SYSTEM INSTALLATION (TOWNSHIPS OF DORR, FILLMORE, LAKETOWN, LEIGHTON, OVERISEL & SALEM) | $47.40 | $23.35 | $70.75 |
| PIPEFITTER: HVAC PIPE INSTALLATION ONLY (TOWNSHIPS OF DORR, FILLMORE, LAKETOWN, LEIGHTON, OVERISEL & SALEM) | $47.40 | $23.35 | $70.75 |
| PIPEFITTER: EXCLUDING HVAC PIPE & SYSTEM INSTALLATION (TOWNSHIPS OF DORR, FILLMORE, LAKETOWN, LEIGHTON, OVERISEL & SALEM) | $47.40 | $23.35 | $70.75 |
| PLUMBER: EXCLUDING HVAC PIPE & SYSTEM INSTALLATION (EXCLUDES TOWNSHIPS OF DORR, FILLMORE, LAKETOWN, LEIGHTON, OVERISEL & SALEM) | $32.50 | $24.97 | $57.47 |
| PIPEFITTER: HVAC PIPE INSTALLATION ONLY (EXCLUDES TOWNSHIPS OF DORR, FILLMORE, LAKETOWN, LEIGHTON, OVERISEL & SALEM) | $32.50 | $24.97 | $57.47 |
| PIPEFITTER: EXCLUDES HVAC PIPE & SYSTEM INSTALLATION (EXCLUDES TOWNSHIPS OF DORR, FILLMORE, LAKETOWN, LEIGHTON, OVERISEL & SALEM) | $32.50 | $24.97 | $57.47 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | $41.34 | $27.39 | $68.73 |
| SHEET METAL WORKER (HVAC DUCT & SYSTEM INSTALLATION) | $42.74 | $21.53 | $64.27 |
| SHEET METAL WORKER (EXCLUDING HVAC DUCT & SYSTEM INSTALLATION) | $42.74 | $21.53 | $64.27 |
| TRUCK DRIVER: FLATBED TRUCK | $16.80 | $3.97 | $20.77 |
| TRUCK DRIVER, INCLUDES DUMP AND TANDEM TRUCK | $15.65 | $3.12 | $18.77 |
| ROOFER | $15.73 | $7.41 | $23.14 |
| OPERATOR: TRACTOR | $19.60 | $7.31 | $26.91 |
| OPERATOR: ROLLER | $28.02 | $7.07 | $35.09 |
| OPERATOR: GRADER/BLADE | $24.04 | $6.03 | $30.07 |
| OPERATOR: FORKLIFT | $15.31 | $4.47 | $19.78 |
| OPERATOR: BULLDOZER | $22.34 | $1.22 | $23.56 |
| LABORER: LANDSCAPE & IRRIGATION | $12.84 | $0.00 | $12.84 |
| GLAZIER | $16.95 | $4.74 | $21.69 |
| CEMENT MASON/CONCRETE FINISHER | $15.31 | $4.47 | $19.78 |
| CARPENTER (FLOOR LAYING-CARPET ONLY) | $19.59 | $7.57 | $27.16 |
| ASBESTOS WORKER/HEAT & FROST INSULATOR | $19.82 | $7.31 | $27.13 |
Spot a rate that looks wrong? Email me the details and I’ll check it against the SAM.gov document.