Heavy construction wages: Genesee, Michigan
Wage determination MI20260057 · Active · Standard · verify on SAM.gov
Retrieved from wagepin.com/wd/MI20260057 on · latest revision 2 · verify at sam.gov/wage-determination/MI20260057/2
Revision history
| Revision | Published | Compare |
|---|---|---|
| rev 2 | 2026-05-18 | diff vs rev 1 |
| rev 1 | 2026-05-17 | diff vs rev 0 |
| rev 0 | 2026-01-23 | original |
Current rates (rev 2)
The CSV and the printed sheet are snapshots of rev 2. If DOL revises this determination after you save one, the watch above tells you exactly what moved.
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| CARPENTER, INCLUDES FORM WORK | $36.46 | $23.69 | $60.15 |
| ELECTRICIAN | $44.83 | $26.96 | $71.79 |
| POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 4 BROOM/ SWEEPER, FORK TRUCK, TRACTOR, BOBCAT/ SKID STEER /SKID LOADER | $39.95 | $25.25 | $65.20 |
| POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 3 BOOM TRUCK (NON-SWINGING, NON- POWERED TYPE BOOM) | $40.52 | $25.25 | $65.77 |
| POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 2 TRENCHER (8-FT DIGGING CAPACITY AND SMALLER) | $41.25 | $25.25 | $66.50 |
| POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 1 BACKHOE/ EXCAVATOR, BORING MACHINE, BULLDOZER, CRANE, GRADER/ BLADE, LOADER, ROLLER, SCRAPER, TRENCHER (OVER 8 FT. DIGGING CAPACITY) | $45.98 | $25.25 | $71.23 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 6 FORK TRUCK (20' LIFT AND UNDER FOR MASONRY WORK) | $35.46 | $25.25 | $60.71 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 5 BOOM TRUCK (NON-SWINGING) | $41.32 | $25.25 | $66.57 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 4 BOBCAT/SKID LOADER; BROOM/SWEEPER; FORK TRUCK (OVER 20' LIFT) | $41.32 | $25.25 | $66.57 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 3 BACKHOE/EXCAVATOR; BORING MACHINE; BULLDOZER; CRANE; GRADER/BLADE; LOADER; ROLLER; SCRAPER; TRACTOR; TRENCHER | $44.00 | $25.25 | $69.25 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 2 CRANE OPERATOR WITH MAIN BOOM AND JIB 140' OR LONGER, TOWER CRANE, GANTRY CRANE, WHIRLEY DERRICK | $45.68 | $25.25 | $70.93 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 1 CRANE OPERATOR WITH MAIN BOOM AND JIB 400', 300', OR 220' OR LONGER | $48.98 | $25.25 | $74.23 |
| IRONWORKER: STRUCTURAL | $36.55 | $35.93 | $72.48 |
| IRONWORKER: REINFORCING | $36.55 | $33.37 | $69.92 |
| LANDSCAPE LABORER, EXCLUDES OPEN CUT CONSTRUCTION: GROUP 2 LANDSCAPE LABORER: SMALL POWER TOOL OPERATOR, MATERIAL MOVER, TRUCK DRIVER AND LAWN SPRINKLER INSTALLER TENDER | $27.71 | $9.10 | $36.81 |
| LANDSCAPE LABORER, EXCLUDES OPEN CUT CONSTRUCTION: GROUP 1 LANDSCAPE SPECIALIST, INCLUDING AIR, GAS AND DIESEL EQUIPMENT OPERATOR, LAWN SPRINKLER INSTALLER AND SKIDSTEER (OR EQUIVALENT) | $29.93 | $9.10 | $39.03 |
| LABORER ((7) LANDSCAPE) | $18.29 | $12.85 | $31.14 |
| LABORER ((5) PIPELAYER) | $23.84 | $13.52 | $37.36 |
| LABORER ((4) GRADE CHECKER) | $23.70 | $13.15 | $36.85 |
| LABORER ((2) MASON TENDER-CEMENT/CONCRETE) | $23.53 | $13.15 | $36.68 |
| LABORER ((1) COMMON OR GENERAL) | $23.39 | $13.15 | $36.54 |
| LABORER: COMMON OR GENERAL; GRADE CHECKER; MASON TENDER - CEMENT/CONCRETE; PIPELAYER (EXCLUDES OPEN CUT CONSTRUCTION) | $29.46 | $16.10 | $45.56 |
| PAINTER: SPRAY | $31.69 | $17.88 | $49.57 |
| PAINTER: BRUSH & ROLER | $32.58 | $18.12 | $50.70 |
| CEMENT MASON/CONCRETE FINISHER | $25.58 | $12.88 | $38.46 |
| PLUMBER/PIPEFITTER | $39.81 | $20.95 | $60.76 |
| TRUCK DRIVER: OFF THE ROAD TRUCK | $20.82 | $3.69 | $24.51 |
| TRUCK DRIVER: LOWBOY/SEMI-TRAILER TRUCK | $470.70 | $68.70 | $539.40 |
| DAILY | $33.65 | $0.75 | $34.40 |
| TRUCK DRIVER: DUMP TRUCK, 8 CU. YDS. AND OVER | $33.50 | $0.75 | $34.25 |
| TRUCK DRIVER: DUMP TRUCK UNDER 8 CU. YDS.; TRACTOR HAUL TRUCK | $33.40 | $0.75 | $34.15 |
Spot a rate that looks wrong? Email me the details and I’ll check it against the SAM.gov document.