Heavy construction wages: Berrien, Michigan
Wage determination MI20260052 · Active · Standard · verify on SAM.gov
Retrieved from wagepin.com/wd/MI20260052 on July 24, 2026 · latest revision 1 · verify at sam.gov/wage-determination/MI20260052/1
Revision history
| Revision | Published | Compare |
|---|---|---|
| rev 1 | 2026-05-18 | diff vs rev 0 |
| rev 0 | 2026-05-17 | original |
Current rates (rev 1)
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| CARPENTER, INCLUDES FORM WORK | $28.29 | $21.42 | $49.71 |
| ELECTRICIAN | $46.00 | $29.23 | $75.23 |
| POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 4 BROOM/ SWEEPER, FORK TRUCK, TRACTOR, BOBCAT/ SKID STEER /SKID LOADER | $39.95 | $25.25 | $65.20 |
| POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 3 BOOM TRUCK (NON-SWINGING, NON- POWERED TYPE BOOM) | $40.52 | $25.25 | $65.77 |
| POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 2 TRENCHER (8-FT DIGGING CAPACITY AND SMALLER) | $41.25 | $25.25 | $66.50 |
| POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION (INCLUDING SEWER) GROUP 1 BACKHOE/ EXCAVATOR, BORING MACHINE, BULLDOZER, CRANE, GRADER/ BLADE, LOADER, ROLLER, SCRAPER, TRENCHER (OVER 8 FT. DIGGING CAPACITY) | $45.98 | $25.25 | $71.23 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 7 OILER PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF ULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY. | $32.98 | $25.25 | $58.23 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 6 FORK TRUCK (20' LIFT AND UNDER FOR MASONRY WORK) PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF ULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY. | $35.46 | $25.25 | $60.71 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 5 BOOM TRUCK (NON-SWINGING) PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF ULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY. | $41.32 | $25.25 | $66.57 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 4 BOBCAT/SKID LOADER; BROOM/SWEEPER; FORK TRUCK (OVER 20' LIFT) PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF ULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY. 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE | $41.32 | $25.25 | $66.57 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 3 BACKHOE/EXCAVATOR; BORING MACHINE; BULLDOZER; CRANE; GRADER/BLADE; LOADER; ROLLER; SCRAPER; TRACTOR; TRENCHER PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF ULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY. | $44.00 | $25.25 | $69.25 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 2 CRANE OPERATOR WITH MAIN BOOM AND JIB 140' OR LONGER, TOWER CRANE, GANTRY CRANE, WHIRLEY DERRICK PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF ULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY. | $45.68 | $25.25 | $70.93 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 1 CRANE OPERATOR WITH MAIN BOOM AND JIB 400', 300', OR 220' OR LONGER. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF ULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY. 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE | $48.98 | $25.25 | $74.23 |
| IRONWORKER: STRUCTURAL AND REINFORCING | $31.75 | $22.84 | $54.59 |
| LABORER ((5) PIPELAYER) | $22.85 | $12.95 | $35.80 |
| LABORER ((4) GRADE CHECKER) | $22.73 | $12.95 | $35.68 |
| LABORER ((2) MASON TENDER-CEMENT/CONCRETE) | $22.55 | $12.95 | $35.50 |
| LABORER ((1) COMMON OR GENERAL) | $22.42 | $12.95 | $35.37 |
| LABORER (COMMON OR GENERAL; GRADE CHECKER; MASON TENDER - CEMENT/CONCRETE) (EXCLUDES OPEN CUT CONSTRUCTION) | $27.21 | $13.45 | $40.66 |
| PAINTER: SPRAY | $22.75 | $11.94 | $34.69 |
| PAINTER: BRUSH & ROLLER | $21.75 | $11.94 | $33.69 |
| CEMENT MASON/CONCRETE FINISHER | $24.63 | $12.88 | $37.51 |
| PLUMBER (CITY OF NILES & VICINITY) | $33.60 | $19.36 | $52.96 |
| PLUMBER | $35.20 | $22.35 | $57.55 |
| TRUCK DRIVER: OFF THE ROAD TRUCK | $20.82 | $3.69 | $24.51 |
| TRUCK DRIVER: DUMP TRUCK | $18.00 | $6.43 | $24.43 |
| LABORER: LANDSCAPE | $12.25 | $0.00 | $12.25 |
| TRUCK DRIVER: TRACTOR HAUL TRUCK | $68.70 | $0.75 | $69.45 |
| TRUCK DRIVER: LOWBOY/SEMI-TRAILER TRUCK | $470.70 | $68.70 | $539.40 |
| DAILY | $33.55 | $0.75 | $34.30 |