MI20260028: rev 1 → rev 2
6 rate change(s), 4 added, 5 removed.
Rate changes
Rates below include fringe (the full hourly package). Enter your remaining crew hours per classification to price this change for a job.
| Classification | Old total | New total | Δ/hr | Hours on job | Cost impact |
|---|---|---|---|---|---|
| ELECTRICIAN, INCLUDES LOW VOLTAGE WIRING (LIVINGSTON COUNTY (TOWNSHIPS OF GREEN OAK, HAMBURG, PUTNAM AND UNADILLA)) | $49.70 | $57.03 | +7.33 | — | |
| ELECTRICIAN, INCLUDES LOW VOLTAGE WIRING (LIVINGSTON COUNTY (TOWNSHIPS OF COHOCTAH, CONWAY, HANDY, HOWELL, IOSCO AND MARION)) | $36.70 | $42.17 | +5.47 | — | |
| ELECTRICIAN, INCLUDES LOW VOLTAGE WIRING (LAPEER COUNTY) | $41.47 | $49.32 | +7.85 | — | |
| ELEVATOR MECHANIC (MACOMB & WAYNE COUNTIES) | $103.45 | $103.45 | +0.00 | — | |
| ELEVATOR MECHANIC (LAPEER & LIVINGSTON COUNTIES) | $103.89 | $103.89 | +0.00 | — | |
| LABORER: COMMON OR GENERAL; FORMWORK; MASON TENDER - CEMENT/CONCRETE (LIVINGSTON COUNTY) | $29.47 | $53.56 | +24.09 | — |
Added classifications
| PLUMBER: EXCLUDING HVAC PIPE INSTALLATION (LIVINGSTON COUNTY (TOWNSHIPS OF GREEN OAK AND HAMBURG)) | $42.26 | $23.70 |
| PIPEFITTER: HVAC PIPE INSTALLATION ONLY (LIVINGSTON COUNTY (TOWNSHIPS OF GREEN OAK AND HAMBURG)) | $44.31 | $0.00 |
| PLUMBER: EXCLUDING HVAC PIPE INSTALLATION (LIVINGSTON COUNTY (TOWNSHIPS OF GREEN OAK AND HAMBURG)) | $42.26 | $23.70 |
| PIPEFITTER: HVAC PIPE INSTALLATION ONLY (LIVINGSTON COUNTY (TOWNSHIPS OF GREEN OAK AND HAMBURG)) | $44.31 | $0.00 |
Removed classifications
| Howell) | was $16.38 |
| Pinckney | was $38.11 |
| PIPEFITTER (HVAC Pipe Installation Only) | was $44.31 |
| PLUMBER (Excluding HVAC Pipe Installation) | was $42.26 |
| FOOTNOTE: a | was $438.45 |