Highway construction wages: Sagadahoc, Maine
Wage determination ME20260048 · Active · Standard · verify on SAM.gov
Retrieved from wagepin.com/wd/ME20260048 on · latest revision 1 · verify at sam.gov/wage-determination/ME20260048/1
Revision history
| Revision | Published | Compare |
|---|---|---|
| rev 1 | 2026-05-18 | diff vs rev 0 |
| rev 0 | 2026-05-17 | original |
Current rates (rev 1)
The CSV and the printed sheet are snapshots of rev 1. If DOL revises this determination after you save one, the watch above tells you exactly what moved.
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| TRUCK DRIVER: DUMP TRUCK | $17.27 | $2.62 | $19.89 |
| TRAFFIC CONTROL: LABORER-CONES/ BARRICADES/BARRELS - SETTER/MOVER/SWEEPER | $17.02 | $5.37 | $22.39 |
| TRAFFIC CONTROL: FLAGGER | $10.33 | $0.00 | $10.33 |
| OPERATOR: ROLLER ASPHALT | $19.38 | $4.59 | $23.97 |
| OPERATOR: ROLLER (EARTH) | $16.52 | $1.66 | $18.18 |
| OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE) | $20.26 | $4.61 | $24.87 |
| OPERATOR: MILLING MACHINE | $28.51 | $5.44 | $33.95 |
| OPERATOR: MECHANIC | $24.69 | $8.18 | $32.87 |
| OPERATOR: LOADER | $19.52 | $3.19 | $22.71 |
| OPERATOR: GRADER/BLADE | $27.40 | $8.13 | $35.53 |
| OPERATOR: BULLDOZER | $21.71 | $5.67 | $27.38 |
| OPERATOR: BROOM/SWEEPER | $19.02 | $0.00 | $19.02 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $22.21 | $1.90 | $24.11 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $20.67 | $3.91 | $24.58 |
| LABORER: WHEELMAN | $21.28 | $4.02 | $25.30 |
| LABORER: EPOXY INJECTOR (CONCRETE) | $13.43 | $1.15 | $14.58 |
| LABORER: COMMON OR GENERAL | $15.06 | $2.09 | $17.15 |
| LABORER: ASPHALT, INCLUDES RAKER, SHOVELER, SPREADER AND DISTRIBUTOR | $17.30 | $1.76 | $19.06 |
| IRONWORKER, STRUCTURAL | $22.33 | $4.50 | $26.83 |
| IRONWORKER, REINFORCING | $21.85 | $0.00 | $21.85 |
| INSTALLER - GUARDRAIL | $19.98 | $2.55 | $22.53 |
| HIGHWAY/PARKING LOT STRIPING: LABORER | $15.53 | $2.04 | $17.57 |
| ELECTRICIAN | $25.21 | $5.63 | $30.84 |
| CEMENT MASON/CONCRETE FINISHER | $19.27 | $1.13 | $20.40 |
| CARPENTER, INCLUDES FORM WORK | $18.95 | $3.23 | $22.18 |
Spot a rate that looks wrong? Email me the details and I’ll check it against the SAM.gov document.