Heavy construction wages: Berkshire + 3 more counties, Massachusetts
Wage determination MA20260010 · Active · Standard · verify on SAM.gov
Retrieved from wagepin.com/wd/MA20260010 on July 24, 2026 · latest revision 1 · verify at sam.gov/wage-determination/MA20260010/1
BerkshireFranklinHampdenHampshire
Revision history
| Revision | Published | Compare |
|---|---|---|
| rev 1 | 2026-05-18 | diff vs rev 0 |
| rev 0 | 2026-05-17 | original |
Current rates (rev 1)
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| BOILERMAKER | $50.62 | $28.82 | $79.44 |
| BRICKLAYERS; CEMENT MASONS; PLASTERERS; STONE MASONS; MARBLE, TILE & TERRAZZO WORKERS (SPRINGFIELD CHAPTER) | $50.81 | $32.27 | $83.08 |
| BRICKLAYER: BRICKLAYERS; CEMENT MASONS; PLASTERERS; STONE MASONS; MARBLE, TILE & TERRAZZO WORKERS (SPRINGFIELD/PITTSFIELD CHAPTER BERKSHIRE COUNTY) | $50.81 | $32.27 | $83.08 |
| DIVER TENDER | $61.70 | $35.47 | $97.17 |
| DIVER | $78.11 | $35.47 | $113.58 |
| PILEDRIVERMAN | $51.97 | $35.47 | $87.44 |
| CARPENTER (FRANKLIN COUNTY (ERVING, ORANGE, NORTH ORANGE, AND WARWICK)) | $43.33 | $27.82 | $71.15 |
| CARPENTER (BERKSHIRE) | $43.33 | $27.82 | $71.15 |
| CARPENTER (HAMPDEN; HAMPSHIRE; AND FRANKLIN (REMAINDER OF COUNTY)) | $43.33 | $27.82 | $71.15 |
| MILLWRIGHT | $43.42 | $33.00 | $76.42 |
| ELECTRICIAN (HAMPDEN (EXCEPT CHESTER & HOLYOKE); HAMPSHIRE (BELCHERTOWN, WARE)) | $52.16 | $29.56 | $81.72 |
| ELECTRICIAN (BERKSHIRE; FRANKLIN; HAMPDEN (CHESTER, HOLYOKE); HAMPSHIRE (EXCEPT BELCHERTOWN, WARE)) | $52.16 | $29.56 | $81.72 |
| POWER EQUIPMENT OPERATORS: GROUP 15 BOOM LENGTHS OVER 350 FEET INCLUDING JIB HAZARDOUS WASTE PREMIUM $2.00 | $52.38 | $31.04 | $83.42 |
| POWER EQUIPMENT OPERATORS: GROUP 14 BOOM LENGTHS OVER 300 FEET INCLUDING JIB HAZARDOUS WASTE PREMIUM $2.00 | $50.88 | $31.04 | $81.92 |
| POWER EQUIPMENT OPERATORS: GROUP 13 BOOM LENGTHS OVER 250 FEET INCLUDING JIB HAZARDOUS WASTE PREMIUM $2.00 | $49.88 | $31.04 | $80.92 |
| POWER EQUIPMENT OPERATORS: GROUP 12 BOOM LENGTHS OVER 200 FEET INCLUDING JIB HAZARDOUS WASTE PREMIUM $2.00 | $48.88 | $31.04 | $79.92 |
| POWER EQUIPMENT OPERATORS: GROUP 11 BOOM LENGTHS OVER 150 FEET INCLUDING JIB HAZARDOUS WASTE PREMIUM $2.00 | $47.38 | $31.04 | $78.42 |
| POWER EQUIPMENT OPERATORS: GROUP 10 MASTER MECHANIC EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $46.38 | $31.04 | $77.42 |
| POWER EQUIPMENT OPERATORS: GROUP 9 OILER HAZARDOUS WASTE PREMIUM $2.00 | $44.37 | $31.04 | $75.41 |
| POWER EQUIPMENT OPERATORS: GROUP 8 TRUCK CRANE CREWS HAZARDOUS WASTE PREMIUM $2.00 | $44.06 | $31.04 | $75.10 |
| POWER EQUIPMENT OPERATORS: GROUP 7 COMPRESSORS UP TO 315 CU FT; SMALL MIXERS WITH SKIP; PUMPS UP TO 4 INCHES; POWER HEATERS; OILER; A-FRAME TRUCKS; FORKLIFTS-UP TO 7 FT. LIFT AND UP TO 3 TON CAPACITY; HYDRO BROOM; STUD WELDER. HAZARDOUS WASTE PREMIUM $2.00 | $54.38 | $31.04 | $85.42 |
| POWER EQUIPMENT OPERATORS: GROUP 6 COMPRESSOR (ONE OR TWO) 315 CU FT TO 900 CU FT; PUMPS 4 INCHES TO 16 INCHES (TOTAL DISCHARGE). HAZARDOUS WASTE PREMIUM $2.00 | $36.06 | $31.04 | $67.10 |
| POWER EQUIPMENT OPERATORS: GROUP 5 HOISTS; CONVEYORS; POWER PAVEMENT BREAKERS; SELF-POWERED CONCRETE PAVEMENT FINISHING MACHINES; TWO BAG MIXERS WITH SKIP; MCCARTHY AND SIMILAR DRILLS; BATCH PLANTS (NOT SELF LOADING); BULK CEMENT PLANTS; SELF-PROPELLED MATERIAL SPREADERS; THREE OR MORE 10 KW LIGHT PLANTS; 30 KW OR MORE GENERATORS; POWER BROOM. HAZARDOUS WASTE PREMIUM $2.00 | $38.00 | $31.04 | $69.04 |
| POWER EQUIPMENT OPERATORS: GROUP 4 ASPHALT ROLLERS; SELF-POWERED ROLLERS AND COMPACTORS; TRACTOR WITHOUT BLADE DRAWING SHEEPSFOOT ROLLER; RUBBER TIRE ROLLER; VIBRATORY ROLLER OR OTHER TYPE OF COMPACTORS INCLUDING MACHINES FOR PULVERIZING AND AERATING SOIL; YORK RAKE. HAZARDOUS WASTE PREMIUM $2.00 | $39.12 | $31.04 | $70.16 |
| POWER EQUIPMENT OPERATORS: GROUP 3 COMBINATION BACKHOE/LOADER UP TO 3/4 CU YD; SCRAPERS UP TO 21 CU YD (STRUCK LOAD, SELF PROPELLED OR TRACTOR DRAWN); TIREMAN; FRONT END LOADERS UP TO 4 YDS; WELL DRILLERS; ENGINEER OR FIREMAN ON HIGH PRESSURE BOILER; SELF-LOADING BATCH PLANT; WELL POINT OPERATORS ELECTRIC PUMPS USED IN WELL POINT SYSTEM; PUMPS, 16 INCHES AND OVER (TOTAL DISCHARGE); COMPRESSOR, ONE OR TWO 900 CU FT AND OVER; POWERED GREASE TRUCK; TUNNEL LOCOMOTIVES AND DINGYS; GROUT PUMPS; HYDRAULIC JACKS; BOOM TRUCK; HYDRAULIC CRANES- UP TO 10 TON. HAZARDOUS WASTE PREMIUM $2.00 | $42.35 | $31.04 | $73.39 |
| POWER EQUIPMENT OPERATORS: GROUP 2 ROTARY DRILL WITH MOUNTED COMPRESSOR; COMPRESSOR HOUSE (3 TO 6 COMPRESSORS); ROCK AND EARTH BORING MACHINES (EXCLUDING MCCARTHY AND SIMILAR DRILLS); FRONT END LOADERS 4 CU YDS TO 5 1/2 CU YDS); FORKLIFTS-7 FT LIFT AND OVER 3 TON CAPACITY; SCRAPER 21 YDS AND OVER (STRUCK LOAD); SONIC HAMMER CONSOLE; RECLAIMERS ROAD PLANER/MILLING MACHINE; CAL TRACKS; BALLAST REGULATORS; RAIL ANCHOR MACHINES; SWITCH TAMPERS, ASPHALT PAVERS; MECHANIC; WELDER AND TRANSFER MACHINE. HAZARDOUS WASTE PREMIUM $2.00 | $42.57 | $31.04 | $73.61 |
| PAINTER: SPRAY, SANDBLAST (NEW CONSTRUCTION) | $39.48 | $31.85 | $71.33 |
| PAINTER: BRUSH, TAPER (NEW CONSTRUCTION) | $38.78 | $31.85 | $70.63 |
| PAINTER REPAINT: SPRAY, SANDBLAST | $36.80 | $31.85 | $68.65 |
| POWER EQUIPMENT OPERATORS: GROUP 1 SHOVELS; CRAWLERS AND TRUCK CRANES INCLUDING ALL TOWER; SELF-PROPELLED HYDRAULIC CRANES 10 TONS AND OVER; DRAGLINES; CLAM SHELLS; CABLEWAYS; SHAFT HOISTS; MUCKING MACHINES DERRICKS; BACKHOES; BULLDOZERS; GRADALLS; ELEVATING GRADERS; PILE DRIVERS; CONCRETE PAVERS; TRENCHING MACHINES; FRONT END LOADERS- 5 1/2 CU YDS AND OVER; DUAL DRUM PAVER; AUTOMATIC GRADER-EXCAVATOR(C.M.I. OR EQUAL); SCRAPERS TOWING PAN OR WAGON; TANDEM DOZERS OR PUSH CATS(2 UNITS IN TANDEM); SHOTCRETE MACHINE; TUNNEL BORING MACHINE; COMBINATION BACKHOE/LOADER 3/4 CU YD HOE OR OVER; JET ENGINE DRYER; TREE SHREDDER; POST HOLE DIGGER; POST HOLE HAMMER; POST EXTRACTOR; TRUCK MOUNTED CONCRETE PUMP WITH BOOM; ROTO-MILL; GRADER; HORIZONTAL DRILLING MACHINE; JOHN HENRY ROCK DRILL AND SIMILAR EQUIPMENT. HAZARDOUS WASTE PREMIUM $2.00 | $42.88 | $31.04 | $73.92 |
| IRONWORKER (BERKSHIRE (BECKET, EAST OTIS, HINSDALE, MONTEREY, NEW MARLBORO, NORTH OTIS, OTIS, PERU, SANDISFIELD, SAVOY, SHEFFIELD, WASHINGTON, WINDSOR); FRANKLIN; HAMPDEN; HAMPSHIRE) | $41.89 | $33.90 | $75.79 |
| IRONWORKER (BERKSHIRE (LEE)) | $40.75 | $31.91 | $72.66 |
| IRONWORKERS: STRUCTURAL, ORNAMENTAL, REINFORCING, FENCE ERECTOR, MACHINERY MOVER, RIGGER, RODMAN, STONE DERRICKMAN (BERKSHIRE (REMAINDER OF COUNTY)) | $40.75 | $31.91 | $72.66 |
| IRONWORKERS: SHEETER (BERKSHIRE (REMAINDER OF COUNTY)) | $41.00 | $31.91 | $72.91 |
| LABORERS: GROUP 6 ASBESTOS ABATEMENT, TOXIC AND HAZARDOUS WASTE LABORERS (FRANKLIN (ORANGE, WARWICK)) | $40.95 | $29.70 | $70.65 |
| LABORERS: GROUP 5 PRECAST FLOOR AND ROOF, PLANK ERECTOR (FRANKLIN (ORANGE, WARWICK)) | $39.70 | $29.70 | $69.40 |
| LABORERS: GROUP 4 BLASTER; POWDERMAN (FRANKLIN (ORANGE, WARWICK)) | $39.95 | $29.70 | $69.65 |
| LABORERS: GROUP 3 AIR TRACK OPERATOR; BLOCK PAVER; RAMMER; CURB SETTER, HYDRAULIC AND SIMILAR SELF-POWERED DRILLS (FRANKLIN (ORANGE, WARWICK)) | $39.70 | $29.70 | $69.40 |
| LABORERS: GROUP 2 ASPHALT RAKER; FENCE AND GUARD RAIL ERECTOR; LASER BEAM OPERATOR; MASON TENMDER; PIPELAYER; PNEUMATIC DRILL OPERATOR; PNEUMATIC TOOL OPERATOR; WAGON DRILL OPERATORM JACKHAMMER OPERATOR, PAVEMENT BREAKER, CARBIDE CORE DRILLING MACHINE, CHAIN SAW OPERATOR, BARCO TYPE JUMPING TAMPERS, CONCRETE PUMP, MOTORIZED MORTAR MINER, RIDE-ON MOTORIZED BUGGY (FRANKLIN (ORANGE, WARWICK)) | $39.20 | $29.70 | $68.90 |
| LABORERS: GROUP 1 LABORERS; CARPENTER TENDERS; CEMENT FINISHER TENDERS, PLASTERER TENDERS (FRANKLIN (ORANGE, WARWICK)) | $38.95 | $29.70 | $68.65 |
| LABORERS: GROUP 6 ASBESTOS ABATEMENT, TOXIC AND HAZARDOUS WASTE LABORERS (FRANKLIN (EXCEPT ORANGE AND WARRICK); HAMPDEN AND HAMPSHIRE COUNTIES (WITH THE EXCEPTION OF CHESTERFIELD, CUMMINGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD, AND WORTHINGTON)) | $35.00 | $29.70 | $64.70 |
| LABORERS: GROUP 5 FLAGGERS (FRANKLIN (EXCEPT ORANGE AND WARRICK); HAMPDEN AND HAMPSHIRE COUNTIES (WITH THE EXCEPTION OF CHESTERFIELD, CUMMINGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD, AND WORTHINGTON)) | $27.01 | $29.70 | $56.71 |
| LABORERS: GROUP 4 BLASTERS, POWDERMEN (FRANKLIN (EXCEPT ORANGE AND WARRICK); HAMPDEN AND HAMPSHIRE COUNTIES (WITH THE EXCEPTION OF CHESTERFIELD, CUMMINGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD, AND WORTHINGTON)) | $35.00 | $29.70 | $64.70 |
| LABORERS: GROUP 3 AIR TRACK OPERATOR, BLOCK PAVERS, RAMMERS, CURB SETTERS (FRANKLIN (EXCEPT ORANGE AND WARRICK); HAMPDEN AND HAMPSHIRE COUNTIES (WITH THE EXCEPTION OF CHESTERFIELD, CUMMINGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD, AND WORTHINGTON)) | $35.00 | $29.70 | $64.70 |
| LABORERS: GROUP 2 ASPHALT RAKERS, FENCE AND GUARD RAIL ERECTORS, LASER BEAM OPERATOR, MASON TENDER, PIPELAYER, PNEUMATIC DRILL OPERATOR, PNEUMATIC TOOL OPERATOR, WAGON DRILL OPERATOR (FRANKLIN (EXCEPT ORANGE AND WARRICK); HAMPDEN AND HAMPSHIRE COUNTIES (WITH THE EXCEPTION OF CHESTERFIELD, CUMMINGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD, AND WORTHINGTON)) | $35.00 | $29.70 | $64.70 |
| LABORERS: GROUP 1 CARPENTER TENDERS, CEMENT FINISHER TENDERS, LABORERS, WRECKING LABORERS (FRANKLIN (EXCEPT ORANGE AND WARRICK); HAMPDEN AND HAMPSHIRE COUNTIES (WITH THE EXCEPTION OF CHESTERFIELD, CUMMINGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD, AND WORTHINGTON)) | $35.00 | $29.70 | $64.70 |
| LABORERS: GROUP 6 ASBESTOS ABATEMENT, TOXIC AND HAZARDOUS WASTE LABORERS (BERKSHIRE; HAMPSHIRE COUNTIES (THE TOWNS OF CHESTERFIELD, CUMMINGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD, AND WORTHINGTON ONLY)) | $33.99 | $26.65 | $60.64 |
| LABORERS: GROUP 5 FLAGGERS (BERKSHIRE; HAMPSHIRE COUNTIES (THE TOWNS OF CHESTERFIELD, CUMMINGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD, AND WORTHINGTON ONLY)) | $27.01 | $26.65 | $53.66 |
| LABORERS: GROUP 4 BLASTERS, POWDERMEN (BERKSHIRE; HAMPSHIRE COUNTIES (THE TOWNS OF CHESTERFIELD, CUMMINGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD, AND WORTHINGTON ONLY)) | $33.99 | $26.65 | $60.64 |
| LABORERS: GROUP 3 AIR TRACK OPERATOR, BLOCK PAVERS, RAMMERS, CURB SETTERS (BERKSHIRE; HAMPSHIRE COUNTIES (THE TOWNS OF CHESTERFIELD, CUMMINGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD, AND WORTHINGTON ONLY)) | $33.99 | $26.65 | $60.64 |
| LABORERS: GROUP 2 ASPHALT RAKERS, FENCE AND GUARD RAIL ERECTORS, LASER BEAM OPERATOR, MASON TENDER, PIPELAYER, PNEUMATIC DRILL OPERATOR, PNEUMATIC TOOL OPERATOR, WAGON DRILL OPERATOR (BERKSHIRE; HAMPSHIRE COUNTIES (THE TOWNS OF CHESTERFIELD, CUMMINGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD, AND WORTHINGTON ONLY)) | $33.99 | $26.65 | $60.64 |
| LABORERS: GROUP 1 CARPENTER TENDERS, CEMENT FINISHER TENDERS, LABORERS, WRECKING LABORERS (BERKSHIRE; HAMPSHIRE COUNTIES (THE TOWNS OF CHESTERFIELD, CUMMINGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD, AND WORTHINGTON ONLY)) | $33.99 | $26.65 | $60.64 |
| LABORERS: GROUP 6 ASBESTOS, LEAD PAINT, TOXIC AND HAZARDOUS WASTE | $46.25 | $29.70 | $75.95 |
| LABORERS: GROUP 5 YARDMAN, BURNERS, SAWYERS | $45.35 | $29.70 | $75.05 |
| LABORERS: GROUP 4 YARDMAN (SALVAGE YARD ONLY) | $42.25 | $29.70 | $71.95 |
| LABORERS: GROUP 3 SMALL BACKHOES, LOADERS ON TRACKS, BOBCAT TYPE LOADERS, HYDRAULIC "BROCK" TYPE HAMMER OPERATORS, CONCRETE CUTTING SAWS | $47.25 | $29.70 | $76.95 |
| LABORERS: GROUP 2 BURNERS, JACKHAMMERS | $47.00 | $29.70 | $76.70 |
| LABORERS: GROUP 1 ADZEMAN, WRECKING LABORER | $46.25 | $29.70 | $75.95 |
| PAINTER REPAINT: BRUSH, TAPER | $35.40 | $31.85 | $67.25 |
| PAINTER REPAINT: BRIDGE | $56.76 | $31.85 | $88.61 |
| PLUMBER AND STEAMFITTER (FRANKLIN (ORANGE)) | $55.00 | $31.57 | $86.57 |
| PLUMBERS AND PIPEFITTERS (BERKSHIRE (BECKET, OTIS, SANDISFIELD); FRANKLIN (EXCEPT MONROE, ROWE, AND THE WESTERN PART OF CHARLEMONT); HAMPDEN; HAMPSHIRE) | $52.26 | $31.05 | $83.31 |
| PLUMBER AND STEAMFITTER (BERKSHIRE (EXCEPT OTIS, BECKET, SANDISFIELD); FRANKLIN (MONROE, ROWE AND THE WESTERN PART OF CHARLEMONT)) | $52.26 | $31.05 | $83.31 |
| TRUCK DRIVERS: GROUP 7 TRAILERS FOR EARTH MOVING EQUIPMENT (DOUBLE HOOKUP) POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUM | $41.82 | $37.35 | $79.17 |
| TRUCK DRIVERS: GROUP 6 SPECIALIZED EARTH MOVING EQUIPMENT OVER 35 TONS POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUM | $41.53 | $37.35 | $78.88 |
| TRUCK DRIVERS: GROUP 5 SPECIALIZED EARTH MOVING EQUIPMENT UNDER 35 TONS OTHER THAN CONVENTIONAL TYPE TRUCKS; LOW BED; VACHUAL; MECHANICS, PAVING RESTORATION EQUIPMENT POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUM | $41.24 | $37.35 | $78.59 |
| TRUCK DRIVERS: GROUP 4 FOUR AND FIVE AXLE EQUIPMENT WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUM | $41.14 | $37.35 | $78.49 |
| TRUCK DRIVERS: GROUP 3 THREE AXLE EQUIPMENT AND TIREMAN POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUM | $41.02 | $37.35 | $78.37 |
| TRUCK DRIVERS: GROUP 2 TWO AXLE EQUIPMENT; & FORKLIFT OPERATOR POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUM | $40.95 | $37.35 | $78.30 |
| TRUCK DRIVERS: GROUP 1 STATION WAGONS; PANEL TRUCKS; AND PICKUP TRUCKS POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUM | $40.78 | $37.35 | $78.13 |