MA20260002: rev 0 → rev 1

34 added, 23 removed.

Added classifications

LABORERS:(TUNNELS, CAISSON & CYLINDER WORK IN COMPRESSED AIR), GROUP 6 HAZARDOUS WASTE WORK WITHIN THE "HOT" ZONE. (A PREMIUM OF TWO DOLLARS $2.00 PER HOUR OVER THE BASIC WAGE RATE$41.18$29.70
LABORERS: LABORER ((OPEN AIR CASSONS, UNDERPINNING AND TEST BORING INDUSTRIES))$41.18$29.70
LABORERS: LABORER ((OPEN AIR CASSONS, UNDERPINNING AND TEST BORING INDUSTRIES))$46.20$29.70
LABORERS: GROUP 5 (ROCK SHAFT, CONCRETE LINING OF SAME AND TUNNEL IN FREE AIR)$47.48$29.70
LABORERS: GROUP 5 ((TUNNELS, CAISSON & CYLINDER WORK IN COMPRESSED AIR))$53.41$29.70
LABORERS: GROUP 5 ((TUNNELS, CAISSON & CYLINDER WORK IN COMPRESSED AIR))$58.43$29.70
LABORERS: GROUP 4 (ROCK SHAFT, CONCRETE LINING OF SAME AND TUNNEL IN FREE AIR)$45.48$29.70
LABORERS: GROUP 4 (ROCK SHAFT, CONCRETE LINING OF SAME AND TUNNEL IN FREE AIR)$50.50$29.70
LABORERS: GROUP 4 ((TUNNELS, CAISSON & CYLINDER WORK IN COMPRESSED AIR))$53.41$29.70
LABORERS: GROUP 4 ((TUNNELS, CAISSON & CYLINDER WORK IN COMPRESSED AIR))$58.43$29.70
LABORERS: GROUP 3 (ROCK SHAFT, CONCRETE LINING OF SAME AND TUNNEL IN FREE AIR)$45.48$29.70
LABORERS: GROUP 3 (ROCK SHAFT, CONCRETE LINING OF SAME AND TUNNEL IN FREE AIR)$50.50$29.70
LABORERS: GROUP 3 ((TUNNELS, CAISSON & CYLINDER WORK IN COMPRESSED AIR))$53.41$29.70
LABORERS: GROUP 3 ((TUNNELS, CAISSON & CYLINDER WORK IN COMPRESSED AIR))$58.43$29.70
LABORERS: GROUP 2 (ROCK SHAFT, CONCRETE LINING OF SAME AND TUNNEL IN FREE AIR)$45.48$29.70
LABORERS: GROUP 2 (ROCK SHAFT, CONCRETE LINING OF SAME AND TUNNEL IN FREE AIR)$50.50$29.70
LABORERS: GROUP 2 (CLEANING CONCRETE AND CAULKING TUNNEL (Both New & Existing))$45.48$29.70
LABORERS: GROUP 2 (CLEANING CONCRETE AND CAULKING TUNNEL (Both New & Existing))$50.50$29.70
LABORERS: GROUP 2 ((TUNNELS, CAISSON & CYLINDER WORK IN COMPRESSED AIR))$53.41$29.70
LABORERS: GROUP 2 ((TUNNELS, CAISSON & CYLINDER WORK IN COMPRESSED AIR))$58.43$29.70
LABORERS: GROUP 2 ((FREE AIR OPERATION): SHIELD DRIVEN AND LINER PLATE IN FREE AIR))$50.50$29.70
LABORERS: GROUP 1 (ROCK SHAFT, CONCRETE LINING OF SAME AND TUNNEL IN FREE AIR)$42.93$29.70
LABORERS: GROUP 1 (ROCK SHAFT, CONCRETE LINING OF SAME AND TUNNEL IN FREE AIR)$47.95$29.70
LABORERS: GROUP 1 (CLEANING CONCRETE AND CAULKING TUNNEL (Both New & Existing))$45.48$29.70
LABORERS: GROUP 1 (CLEANING CONCRETE AND CAULKING TUNNEL (Both New & Existing))$50.50$29.70
LABORERS: GROUP 1 ((TUNNELS, CAISSON & CYLINDER WORK IN COMPRESSED AIR))$42.93$29.70
LABORERS: GROUP 1 ((TUNNELS, CAISSON & CYLINDER WORK IN COMPRESSED AIR))$47.95$29.70
LABORERS: GROUP 1 ((FREE AIR OPERATION): SHIELD DRIVEN AND LINER PLATE IN FREE AIR))$50.50$29.70
LABORERS: DRILLER ((OPEN AIR CASSONS, UNDERPINNING AND TEST BORING INDUSTRIES))$42.58$29.70
LABORERS: BOTTOM MAN ((OPEN AIR CASSONS, UNDERPINNING AND TEST BORING INDUSTRIES))$42.33$29.70
((OPEN AIR CASSONS, UNDERPINNING AND TEST BORING INDUSTRIES))$41.18$29.70
((OPEN AIR CASSONS, UNDERPINNING AND TEST BORING INDUSTRIES))$42.33$29.70
((OPEN AIR CASSONS, UNDERPINNING AND TEST BORING INDUSTRIES))$42.58$29.70
PAINTER: BRIDGE (REPAINT)$44.32$36.00

Removed classifications

Insulator/asbestos worker - Includes the application of all insulating materials, protective coverings, coating, and finishes to all types of mechanical systemswas $37.50
Power equipment operators - BUILDING, HEAVY & MARINE GROUP 1was $48.73
Power equipment operators - GROUP 2was $48.23
Power equipment operators - GROUP 3was $32.47
Power equipment operators - GROUP 4was $39.89
Power equipment operators - GROUP 5was $23.08
Power equipment operators - GROUP 6was $27.64
Plasterer tender - BARNSTABLE, BRISTOL, DUKES, ESSEX, NANTUCKET, MIDDLESEX (with the exception of Arlington, Belmont, Burlington, Cambridge, Everett, Malden, Medford, Melrose, Reading, Somerville, Stoneham, Wakefield, Winchester, Winthrop and Woburn); NORFOLK (with the exception of Brookline Dedham and Milton) COUNTIESwas $38.95
Plasterer tender - SUFFOLK COUNTY (Boston, Chelsea, Revere, Winthrop, Deer Island, Nut Island); MIDDLESEX COUNTY (Arlington, Belmont, Burlington, Cambridge, Everett, Malden, Medford, Melrose, Reading, Somerville, Stoneham, Wakefield, Winchester, Winthrop and Woburn only); NORFOLK COUNTY (Brookline, Dedham, and Milton only)was $46.20
Laborers - (FREE AIR OPERATION): SHIELD DRIVEN AND LINER PLATE IN FREE AIR) GROUP 1was $50.50
Laborers - GROUP 2was $50.50
Laborers - Laborerwas $46.20
Laborers - (TUNNELS, CAISSON & CYLINDER WORK IN COMPRESSED AIR) GROUP 1was $47.95
Laborers - GROUP 2was $58.43
Laborers - GROUP 3was $58.43
Laborers - GROUP 4was $58.43
Laborers - GROUP 5was $58.43
Laborers - GROUP 6was $58.43
Laborers - CLEANING CONCRETE AND CAULKING TUNNEL (Both New & Existing) GROUP 1was $50.50
Laborers - ROCK SHAFT, CONCRETE LINING OF SAME AND TUNNEL IN FREE AIR GROUP 1was $47.95
Laborers - GROUP 3was $50.50
Laborers - GROUP 4was $50.50
PAINTER - REPAINT Bridgewas $44.32