| CARPENTER (FORM WORK ONLY) | $33.89 | $24.06 | $57.95 |
| ELECTRICIAN | $37.10 | $20.03 | $57.13 |
| POWER EQUIPMENT OPERATOR GROUP 4 PUMP OPERATORS ON CRANES WITH BOOMS 150 FEET AND OVER (INCLUDING JIB) SHALL RECEIVE $1.00 ABOVE GROUP 1 RATE; 250 FEET AND OVER INCLUDING JIB SHALL RECEIVE $1.50 ABOVE CLASS 1 RATE. COMBINATION RATE: ALL CRANE OPERATORS OPERATING CRANES, WHERE THE LENGTH OF THE BOOM IN COMBINATION WITH THE LENGTH OF THE PILING LEADS EQUAL OR EXCEEDS 150 FEET, SHALL RECEIVE $1.00 ABOVE THE GROUP 1 RATE. EMPLOYEES ASSIGNED TO WORK BELOW GROUND LEVEL ARE TO BE PAID 10% ABOVE BASIC WAGE RATE. THIS DOES NOT APPLY TO OPEN CUT WORK | $38.37 | $19.60 | $57.97 |
| POWER EQUIPMENT OPERATOR GROUP 3 ARTICULATING TRUCK OPERATOR OPERATORS ON CRANES WITH BOOMS 150 FEET AND OVER (INCLUDING JIB) SHALL RECEIVE $1.00 ABOVE GROUP 1 RATE; 250 FEET AND OVER INCLUDING JIB SHALL RECEIVE $1.50 ABOVE CLASS 1 RATE. COMBINATION RATE: ALL CRANE OPERATORS OPERATING CRANES, WHERE THE LENGTH OF THE BOOM IN COMBINATION WITH THE LENGTH OF THE PILING LEADS EQUAL OR EXCEEDS 150 FEET, SHALL RECEIVE $1.00 ABOVE THE GROUP 1 RATE. EMPLOYEES ASSIGNED TO WORK BELOW GROUND LEVEL ARE TO BE PAID 10% ABOVE BASIC WAGE RATE. THIS DOES NOT APPLY TO OPEN CUT WORK | $39.14 | $19.60 | $58.74 |
| POWER EQUIPMENT OPERATOR GROUP 2 BOBCAT/SKID STEER/SKID LOADER; COMPRESSOR; CONCRETE PUMP OPERATORS ON CRANES WITH BOOMS 150 FEET AND OVER (INCLUDING JIB) SHALL RECEIVE $1.00 ABOVE GROUP 1 RATE; 250 FEET AND OVER INCLUDING JIB SHALL RECEIVE $1.50 ABOVE CLASS 1 RATE. COMBINATION RATE: ALL CRANE OPERATORS OPERATING CRANES, WHERE THE LENGTH OF THE BOOM IN COMBINATION WITH THE LENGTH OF THE PILING LEADS EQUAL OR EXCEEDS 150 FEET, SHALL RECEIVE $1.00 ABOVE THE GROUP 1 RATE. EMPLOYEES ASSIGNED TO WORK BELOW GROUND LEVEL ARE TO BE PAID 10% ABOVE BASIC WAGE RATE. THIS DOES NOT APPLY TO OPEN CUT WORK | $38.69 | $19.60 | $58.29 |
| POWER EQUIPMENT OPERATOR GROUP 1 BULLDOZER; CRANE; DRILL; LOADER; MECHANIC; PUMPCRETE OPERATORS ON CRANES WITH BOOMS 150 FEET AND OVER (INCLUDING JIB) SHALL RECEIVE $1.00 ABOVE GROUP 1 RATE; 250 FEET AND OVER INCLUDING JIB SHALL RECEIVE $1.50 ABOVE CLASS 1 RATE. COMBINATION RATE: ALL CRANE OPERATORS OPERATING CRANES, WHERE THE LENGTH OF THE BOOM IN COMBINATION WITH THE LENGTH OF THE PILING LEADS EQUAL OR EXCEEDS 150 FEET, SHALL RECEIVE $1.00 ABOVE THE GROUP 1 RATE. EMPLOYEES ASSIGNED TO WORK BELOW GROUND LEVEL ARE TO BE PAID 10% ABOVE BASIC WAGE RATE. THIS DOES NOT APPLY TO OPEN CUT WORK | $41.55 | $19.60 | $61.15 |
| IRONWORKER: ORNAMENTAL AND REINFORCING | $36.17 | $25.80 | $61.97 |
| LABORER: FLAGGER | $35.52 | $14.45 | $49.97 |
| LABORER: CONCRETE FINISHING | $29.45 | $18.77 | $48.22 |
| LABORER: CONCRETE SAW (HAND HELD/WALK BEHIND), JACK HAMMER & PIPELAYER | $29.19 | $17.59 | $46.78 |
| LABORER: COMMON OR GENERAL, CONCRETE WORKER, GRADE CHECKER & GROUTING | $28.94 | $17.59 | $46.53 |
| TRUCK DRIVER: DUMP TRUCK | $16.69 | $6.20 | $22.89 |
| OPERATOR: TRENCHER | $26.34 | $12.58 | $38.92 |
| OPERATOR: ROLLER | $20.21 | $13.00 | $33.21 |
| OPERATOR: OILER | $24.34 | $13.00 | $37.34 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $29.81 | $13.00 | $42.81 |
| IRONWORKER, STRUCTURAL | $25.46 | $17.49 | $42.95 |
| OPERATOR: FORKLIFT | $40.05 | $19.10 | $59.15 |