KY20260072: rev 0 → rev 1

4 rate change(s), 1 added, 1 removed.

Rate changes

Rates below include fringe (the full hourly package). Enter your remaining crew hours per classification to price this change for a job.

ClassificationOld totalNew totalΔ/hrHours on jobCost impact
LINE CONSTRUCTION: LINEMAN$44.19$53.94+9.75
LINE CONSTRUCTION: TRUCK DRIVER$22.43$26.70+4.27
LINE CONSTRUCTION: EQUIPMENT OPERATOR$46.76$56.03+9.27
LINE CONSTRUCTION: GROUNDMAN$40.64$48.36+7.72

Added classifications

OPERATOR: FORKLIFT$40.05$19.10

Removed classifications

OPERATOR: Forkliftwas $40.05