ClassificationRateFringeTotal
CARPENTER (FORM WORK ONLY)$33.89$24.06$57.95
LINE CONSTRUCTION: LINEMAN$43.84$18.80$62.64
LINE CONSTRUCTION: GROUNDMAN$25.77$14.10$39.87
LINE CONSTRUCTION: EQUIPMENT OPERATOR$39.15$17.58$56.73
POWER EQUIPMENT OPERATOR GROUP 4 OILER OPERATORS ON CRANES WITH BOOMS 150 FEET AND OVER (INCLUDING JIB) SHALL RECEIVE $1.00 ABOVE GROUP 1 RATE; 250 FEET AND OVER INCLUDING JIB SHALL RECEIVE $1.50 ABOVE CLASS 1 RATE. COMBINATION RATE: ALL CRANE OPERATORS OPERATING CRANES, WHERE THE LENGTH OF THE BOOM IN COMBINATION WITH THE LENGTH OF THE PILING LEADS EQUAL OR EXCEEDS 150 FEET, SHALL RECEIVE $1.00 ABOVE THE GROUP 1 RATE. EMPLOYEES ASSIGNED TO WORK BELOW GROUND LEVEL ARE TO BE PAID 10% ABOVE BASIC WAGE RATE. THIS DOES NOT APPLY TO OPEN CUT WORK$38.37$19.60$57.97
POWER EQUIPMENT OPERATOR GROUP 2 BOBCAT/SKID STEER/SKID LOADER; FORKLIFT OPERATORS ON CRANES WITH BOOMS 150 FEET AND OVER (INCLUDING JIB) SHALL RECEIVE $1.00 ABOVE GROUP 1 RATE; 250 FEET AND OVER INCLUDING JIB SHALL RECEIVE $1.50 ABOVE CLASS 1 RATE. COMBINATION RATE: ALL CRANE OPERATORS OPERATING CRANES, WHERE THE LENGTH OF THE BOOM IN COMBINATION WITH THE LENGTH OF THE PILING LEADS EQUAL OR EXCEEDS 150 FEET, SHALL RECEIVE $1.00 ABOVE THE GROUP 1 RATE. EMPLOYEES ASSIGNED TO WORK BELOW GROUND LEVEL ARE TO BE PAID 10% ABOVE BASIC WAGE RATE. THIS DOES NOT APPLY TO OPEN CUT WORK$38.69$19.60$58.29
POWER EQUIPMENT OPERATOR GROUP 1 BULLDOZER; CRANE; DRILL; GRADER/BLADE; MECHANIC; SCRAPER OPERATORS ON CRANES WITH BOOMS 150 FEET AND OVER (INCLUDING JIB) SHALL RECEIVE $1.00 ABOVE GROUP 1 RATE; 250 FEET AND OVER INCLUDING JIB SHALL RECEIVE $1.50 ABOVE CLASS 1 RATE. COMBINATION RATE: ALL CRANE OPERATORS OPERATING CRANES, WHERE THE LENGTH OF THE BOOM IN COMBINATION WITH THE LENGTH OF THE PILING LEADS EQUAL OR EXCEEDS 150 FEET, SHALL RECEIVE $1.00 ABOVE THE GROUP 1 RATE. EMPLOYEES ASSIGNED TO WORK BELOW GROUND LEVEL ARE TO BE PAID 10% ABOVE BASIC WAGE RATE. THIS DOES NOT APPLY TO OPEN CUT WORK$41.55$19.60$61.15
IRONWORKER (PROJECTS UNDER $20,000,000.00)$35.63$26.49$62.12
IRONWORKER (PROJECTS OVER $20,000,000.00)$37.47$26.49$63.96
LABORER: CONCRETE WORKER$26.87$19.66$46.53
LABORER: CONCRETE SAW (HAND HELD/WALK BEHIND)$27.12$19.66$46.78
LABORER: AIRTRACK DRILLER$27.77$19.66$47.43
OPERATOR: LOADER$30.35$0.00$30.35
OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE$27.23$0.00$27.23
LABORER: PIPELAYER$20.15$8.92$29.07
LABORER: FLAGGER$18.31$8.89$27.20
LABORER: COMMON OR GENERAL$21.36$9.39$30.75
ELECTRICIAN$32.35$2.18$34.53
CEMENT MASON/CONCRETE FINISHER$21.60$10.35$31.95