Heavy, Highway construction wages: De Kalb + 7 more counties, Illinois
Wage determination IL20260011 · Active · Standard
De KalbDu PageKaneLakeMcHenryKendallWillBoone
Revision history
| Revision | Published | Compare |
|---|---|---|
| rev 2 | 2026-05-21 | diff vs rev 1 |
| rev 1 | 2026-05-20 | diff vs rev 0 |
| rev 0 | 2026-05-17 | original |
Current rates (rev 2) · download CSV · print this page for your bid file
| Classification | Rate | Fringe | Total |
|---|---|---|---|
| CARPENTER: HEAVY & HIGHWAY (DUPAGE ANE LAKE COUNTIES) | $52.01 | $38.85 | $90.86 |
| CARPENTER: BUILDING (DUPAGE ANE LAKE COUNTIES) | $52.01 | $38.85 | $90.86 |
| CARPENTER AND PILEDRIVER (WILL COUNTY) | $49.76 | $38.26 | $88.02 |
| CARPENTER AND PILEDRIVER (KANE, MCHENRY (NORTH OF HWY 52), AND KENDALL COUNTIES) | $52.01 | $38.86 | $90.87 |
| CARPENTER (DE KALB COUNTY) | $48.60 | $38.53 | $87.13 |
| CARPENTER (CARROLL, JO DAVIESS, LEE, OGLE (OREGON AND SOUTH THEREOF), STEPHENSON, AND WHITESIDE COUNTIES) | $48.60 | $38.53 | $87.13 |
| CARPENTER (BOONE COUNTY) | $51.00 | $36.13 | $87.13 |
| LINE CONSTRUCTION: LINEMAN AND EQUIPMENT OPERATOR (WILL COUNTY) | $62.10 | $37.29 | $99.39 |
| LINE CONSTRUCTION: GROUNDMAN (WILL COUNTY) | $48.44 | $29.09 | $77.53 |
| ELECTRICIAN (KANE (NORTHERN HALF) AND MCHENRY (ALL) COUNTIES) | $59.11 | $42.23 | $101.34 |
| ELECTRICIAN (LAKE COUNTY) | $48.28 | $50.46 | $98.74 |
| ELECTRICIAN (WILL COUNTY) | $52.00 | $45.01 | $97.01 |
| LINE CONSTRUCTION: LINEMAN, SUBSTATION TECHNICIAN, CABLE SPLICING TECHNICIAN, DIGGER OPERATOR, CRANE OPERATOR 20 TONS AND ABOVE, AND SIGNAL TECHNICIAN (BOONE, DEKALB, DUPAGE, KANE, KENDALL, LAKE, AND MCHENRY COUNTIES) | $59.17 | $27.12 | $86.29 |
| LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (BOONE, DEKALB, DUPAGE, KANE, KENDALL, LAKE, AND MCHENRY COUNTIES) | $39.19 | $20.32 | $59.51 |
| LINE CONSTRUCTION: GROUNDMAN (BOONE, DEKALB, DUPAGE, KANE, KENDALL, LAKE, AND MCHENRY COUNTIES) INDEPENDENCE DAY, LABOR DAY, AND THANKSGIVING DAY | $37.81 | $19.86 | $57.67 |
| LINE CONSTRUCTION: EQUIPMENT OPERATOR (BOONE, DEKALB, DUPAGE, KANE, KENDALL, LAKE, AND MCHENRY COUNTIES) | $49.22 | $23.73 | $72.95 |
| ELECTRICIAN (BOONE (ALL) & DEKALB (REMAINDER) COUNTIES) | $62.61 | $43.96 | $106.57 |
| ELECTRICIAN (DEKALB (SANDWICH TWP), KANE (SOUTHERN HALF) & KENDALL (ALL) COUNTIES) | $60.17 | $43.50 | $103.67 |
| ELECTRICIAN (DUPAGE COUNTY) | $41.00 | $43.40 | $84.40 |
| OPERATOR: POWER EQUIPMENT, GROUP 5 OILERS (BOONE AND DE KALB COUNTIES) PREMIUM PAY: LONG BOOM : RECEIVE AN EXTRA $.50 PER HOUR. CRANES & DERRICKS OVER 150' INCLUDING JIB RECEIVE AN EXTRA $.50 PER HOUR PLUS AN ADDITIONAL $.10 FOR EACH ADDITIONAL 10' OF BOOM OR JIB. CAPACITY PAY: CRANES & DERRICKS WITH MAXIMUM CAPACITY EXCEEDING 50 TON WITH LESS THAN 90' OF BOOM OR JIB SHALL BE COMPENSATED $.01 PER HOUR FOR EACH TON OF THE RATED CAPACITY IN EXCESS OF 50 TON. LONG BOOM PAY AND CAPACITY PAY CANNOT BE COMBINED. CRANE MOUNTED EARTH AUGER, RAISED AND BLIND HOLE DRILLS, AND TRUCK MOUNTED DRILL RIGS RECEIVE AN EXTRA $.50 PER HOUR. CRETER CRANES: WHEN THE CRETER CRANE IS EQUIPPED WITH A CONVEYOR SYSTEM CAPABLE OF EXTENDING 70' OR MORE, THE ENGINEER SHALL RECEIVE AN EXTRA $.50 PER HOUR. TRUCK MOUNTED CONCRETE PUMPS: WHEN THE TRUCK MOUNTED CONCRETE PUMP IS EQUIPPED WITH A BOOM, WHICH IS CAPABLE OF EXTENDING 90' OR MORE, THE ENGINEER SHALL RECEIVE $.50 PER HOUR EXTRA. TRUCK MOUNTED CONCRETE CONVEYOR: TRUCK MOUNTED CONCRETE CONVEYORS EQUIPPED WITH CONVEYORS THAT ARE CAPABLE OF EXTENDING 90' OR MORE, THE ENGINEER SHALL RECEIVE AN EXTRA $.50 PER HOUR. UNDERGROUND WORK: EMPLOYEES WORKING IN TUNNELS, SHAFTS, ETC. SHALL BE PAID AN ADDITIONAL $.40 PER HOUR. EMPLOYEES WORKING UNDER AIR PRESSURE 1/2 POUND TO 7 POUNDS SHALL RECEIVE AN ADDITIONAL $.50 PER HOUR. EMPLOYEES WORKING UNDER AIR PRESSURE OF 7 POUNDS OR OVER SHALL RECEIVE $.65 PER HOUR MORE. MINING MACHINES- BORING MACHINES: THE CREW OPERATING AND MAINTAINING THE MINING MACHINES SHALL BE COMPENSATED AN ADDITIONAL $.50 PER HOUR | $50.85 | $51.05 | $101.90 |
| OPERATOR: POWER EQUIPMENT, GROUP 4 AIR COMPRESSOR - SMALL 185 AND UNDER (1 TO 5 NOT TO EXCEED A TOTAL OF 300 FT); AIR COMPRESSOR - LARGE OVER 185; ASPHALT SPREADER BACKEND MAN; COMBINATION - SMALL EQUIPMENT OPERATOR; GENERATORS - SMALL 50 KW AND UNDER; GENERATORS - LARGE , OVER 50 KW; HEATERS, MECHANICAL; HYDRAULIC POWER UNIT (PILE DRIVING, EXTRACTING OR DRILLING); LIGHT PLANTS ALL (1 TO 5); PUMPS, OVER 3" (1 TO 3, NOT TO EXCEED A TOTAL OF 300 FT); PUMPS, WELL POINTS; TRACTAIRE; WELDING MACHINES (2 THROUGH 5); WINCHES, 4 SMALL ELECTRIC DRILL WINCHES; BOBCATS UP TO AND INCLUDING .75 CU YD (BOONE AND DE KALB COUNTIES) PREMIUM PAY: LONG BOOM : CRANES & DERRICKS 90' TO 150' INCLUDING JIB RECEIVE AN EXTRA $.50 PER HOUR. CRANES & DERRICKS OVER 150' INCLUDING JIB RECEIVE AN EXTRA $.50 PER HOUR PLUS AN ADDITIONAL $.10 FOR EACH ADDITIONAL 10' OF BOOM OR JIB. CAPACITY PAY: CRANES & DERRICKS WITH MAXIMUM CAPACITY EXCEEDING 50 TON WITH LESS THAN 90' OF BOOM OR JIB SHALL BE COMPENSATED $.01 PER HOUR FOR EACH TON OF THE RATED CAPACITY IN EXCESS OF 50 TON. LONG BOOM PAY AND CAPACITY PAY CANNOT BE COMBINED. CRANE MOUNTED EARTH AUGER, RAISED AND BLIND HOLE DRILLS, AND TRUCK MOUNTED DRILL RIGS RECEIVE AN EXTRA $.50 PER HOUR. CRETER CRANES: WHEN THE CRETER CRANE IS EQUIPPED WITH A CONVEYOR SYSTEM CAPABLE OF EXTENDING 70' OR MORE, THE ENGINEER SHALL RECEIVE AN EXTRA $.50 PER HOUR. TRUCK MOUNTED CONCRETE PUMPS: WHEN THE TRUCK MOUNTED CONCRETE PUMP IS EQUIPPED WITH A BOOM, WHICH IS CAPABLE OF EXTENDING 90' OR MORE, THE ENGINEER SHALL RECEIVE $.50 PER HOUR EXTRA. TRUCK MOUNTED CONCRETE CONVEYOR: TRUCK MOUNTED CONCRETE CONVEYORS EQUIPPED WITH CONVEYORS THAT ARE CAPABLE OF EXTENDING 90' OR MORE, THE ENGINEER SHALL RECEIVE AN EXTRA $.50 PER HOUR. UNDERGROUND WORK: EMPLOYEES WORKING IN TUNNELS, SHAFTS, ETC. SHALL BE PAID AN ADDITIONAL $.40 PER HOUR. EMPLOYEES WORKING UNDER AIR PRESSURE 1/2 POUND TO 7 POUNDS SHALL RECEIVE AN ADDITIONAL $.50 PER HOUR. EMPLOYEES WORKING UNDER AIR PRESSURE OF 7 POUNDS OR OVER SHALL RECEIVE $.65 PER HOUR MORE. OPERATING AND MAINTAINING THE MINING MACHINES SHALL BE COMPENSATED AN ADDITIONAL $.50 PER HOUR | $53.30 | $51.05 | $104.35 |
| OPERATOR: POWER EQUIPMENT, GROUP 3 BOILERS; BROOMS, ALL POWER PROPELLED; CEMENT SUPPLY TENDER; COMPRESSOR, COMMON RECEIVER (2); CONCRETE MIXER, TWO BAG AND OVER; CONVEYOR, PORTABLE; FARM TYPE TRACTORS USED FOR MOWING, SEEDING, ETC; FIREMAN ON BOILERS; FORKLIFT TRUCKS; GROUTING MACHINES; HOISTS, AUTOMATIC; HOISTS, ALL ELEVATORS; HOISTS, TUGGER SINGLE DRUM; JEEP DIGGERS; PIPE JACKING MACHINES; POST- HOLE DIGGER; POWER SAW, CONCRETE, POWER DRIVEN; PUG MILLS; ROLLERS, OTHER THAN ASPHALT; SEED AND STRAW BLOWER; STEAM GENERATORS; STUMP MACHINE; WINCH TRUCKS WITH A-FRAME; WORK BOATS; TAMPER-FORM MOTOR DRIVEN (BOONE AND DE KALB COUNTIES) PREMIUM PAY: LONG BOOM : CRANES & DERRICKS 90' TO 150' INCLUDING JIB RECEIVE AN EXTRA INCLUDING JIB RECEIVE AN EXTRA $.50 PER HOUR PLUS AN ADDITIONAL $.10 FOR EACH ADDITIONAL 10' OF BOOM OR JIB. CAPACITY PAY: CRANES & DERRICKS WITH MAXIMUM CAPACITY EXCEEDING 50 TON WITH LESS THAN 90' OF BOOM OR JIB SHALL BE COMPENSATED $.01 PER HOUR FOR EACH TON OF THE RATED CAPACITY IN EXCESS OF 50 TON. LONG BOOM PAY AND CAPACITY PAY CANNOT BE COMBINED. CRANE MOUNTED EARTH AUGER, RAISED AND BLIND HOLE DRILLS, AND TRUCK MOUNTED DRILL RIGS RECEIVE AN EXTRA $.50 PER HOUR. CRETER CRANES: WHEN THE CRETER CRANE IS EQUIPPED WITH A CONVEYOR SYSTEM CAPABLE OF EXTENDING 70' OR MORE, THE ENGINEER SHALL RECEIVE AN EXTRA $.50 PER HOUR. MOUNTED CONCRETE PUMP IS EQUIPPED WITH A BOOM, WHICH IS CAPABLE OF EXTENDING 90' OR MORE, THE ENGINEER SHALL RECEIVE $.50 PER HOUR EXTRA. TRUCK MOUNTED CONCRETE CONVEYOR: TRUCK MOUNTED CONCRETE CONVEYORS EQUIPPED WITH CONVEYORS THAT ARE CAPABLE OF EXTENDING 90' OR MORE, THE ENGINEER SHALL RECEIVE AN EXTRA $.50 PER HOUR. UNDERGROUND WORK: EMPLOYEES WORKING IN TUNNELS, SHAFTS, ETC. SHALL BE PAID AN ADDITIONAL $.40 PER HOUR. EMPLOYEES WORKING UNDER AIR PRESSURE 1/2 POUND TO 7 POUNDS SHALL RECEIVE AN ADDITIONAL $.50 PER HOUR. EMPLOYEES WORKING UNDER AIR PRESSURE OF 7 POUNDS OR OVER SHALL RECEIVE $.65 PER HOUR MORE. OPERATING AND MAINTAINING THE MINING MACHINES SHALL BE COMPENSATED AN ADDITIONAL $.50 PER HOUR | $54.75 | $51.05 | $105.80 |
| OPERATOR: POWER EQUIPMENT, GROUP 2 BATCH PLANT; BITUMINOUS MIXER; BOBCATS OVER .75 CU YD; BOILER AND THROTTLE VALVE; BULLDOZER; CAR LOADER TRAILING CONVEYORS; COMBINATION BACKKHOE FRONT END LOADER MACHINE, LESS THAN 1 CU YD BACKHOE BUCKET WITH ATTACHMENTS; COMPRESSOR AND THROTTLE VALVE; COMPRESSOR, COMMON RECEIVER (3); CONCRETE BREAKER OR HYDRO HAMMER; CONCRETE GRINDING MACHINE; CONCRETE MIXER OR PAVER 7S SERIES TO AND INCLUDING 27 CU FT; CONCRETE SPREADER; CONCRETE CURING MACHINE, BURLAP MACHINE; BELTING MACHINE AND SEALING MACHINE; CONVEYOR MUCK CARS (HAGLUND OR SIMILAR TYPE); FINISHING MACHINE-CONCRETE; GREASER ENGINEER; HIGHLIFT SHOVELS OR FRONT END LOADER; HOIST-SEWER DRAGGING MACHINE; HYDRAULIC BOOM TRUCKS, ALL ATTACHMENTS; LOCOMOTIVES, DINKY; PUMP CRETES, SQUEEZE CRETES-SCREW TYPE PUMPS, GYPSUM BULKER AND PUMP; ROLLER ASPHALT; ROTARY SNOW PLOWS; ROTOTILLER, SEAMAN, ETC SELF-PROPELLED; SCOOPS-TRACTOR DRAWN; SELF-PROPELLED COMPACTOR; SPREADER-CHIP- STONE ETC; SCRAPER; SCRAPER-PRIME MOVER IN TANDEM REGARDLESS OF SIZE (ADD $1.00 TO TO GROUP 2 HOURLY RATE FOR EACH HOUR AND FOR EACH MACHINE ATTACHED THERETO); TANK CAR HEATER; TRACTORS, PUSH, PULLING SHEEPS FOOT, DISC, OR COMPACTOR, ETC; TUG BOATS PREMIUM PAY: LONG BOOM : CRANES & DERRICKS 90' TO 150' INCLUDING JIB RECEIVE AN EXTRA $.50 PER HOUR. CRANES & DERRICKS OVER 150' INCLUDING JIB RECEIVE AN EXTRA $.50 PER HOUR PLUS AN ADDITIONAL $.10 FOR EACH ADDITIONAL 10' OF BOOM OR JIB. CAPACITY PAY: CRANES & DERRICKS WITH MAXIMUM CAPACITY EXCEEDING 50 TON WITH LESS THAN 90' OF BOOM OR JIB SHALL BE COMPENSATED $.01 PER HOUR FOR EACH TON OF THE RATED CAPACITY IN EXCESS OF 50 TON. LONG BOOM PAY AND CAPACITY PAY CANNOT BE COMBINED. CRANE MOUNTED EARTH AUGER, RAISED AND BLIND HOLE DRILLS, AND TRUCK MOUNTED DRILL RIGS RECEIVE AN EXTRA $.50 PER HOUR. CRETER CRANES: WHEN THE CRETER CRANE IS EQUIPPED WITH A CONVEYOR SYSTEM CAPABLE OF EXTENDING 70' OR MORE, THE ENGINEER SHALL RECEIVE AN EXTRA $.50 PER HOUR. TRUCK MOUNTED CONCRETE PUMPS: WHEN THE TRUCK MOUNTED CONCRETE PUMP IS EQUIPPED WITH A BOOM, WHICH IS CAPABLE OF EXTENDING 90' OR MORE, THE ENGINEER SHALL RECEIVE $.50 PER HOUR EXTRA. TRUCK MOUNTED CONCRETE CONVEYOR: TRUCK MOUNTED CONCRETE CONVEYORS EQUIPPED WITH CONVEYORS THAT ARE CAPABLE OF EXTENDING 90' OR MORE, THE ENGINEER SHALL RECEIVE AN EXTRA $.50 PER HOUR. UNDERGROUND WORK: EMPLOYEES WORKING IN TUNNELS, SHAFTS, ETC. SHALL BE PAID AN ADDITIONAL $.40 PER HOUR. EMPLOYEES WORKING UNDER AIR PRESSURE 1/2 POUND TO 7 POUNDS SHALL RECEIVE AN ADDITIONAL $.50 PER HOUR. EMPLOYEES WORKING UNDER AIR PRESSURE OF 7 POUNDS OR OVER SHALL RECEIVE $.65 PER HOUR MORE. MINING MACHINES- BORING MACHINES: THE CREW OPERATING AND MAINTAINING THE MINING MACHINES SHALL BE COMPENSATED AN ADDITIONAL $.50 PER HOUR. (BOONE AND DE KALB COUNTIES) | $56.05 | $51.05 | $107.10 |
| OPERATOR: POWER EQUIPMENT, GROUP 1 ASPHALT PLANT; ASPHALT HEATER AND PLANER COMBINATION; ASPHALT SPREADER; ASPHALT SILO TENDER; AUTOGRADER, GOMACO OR SIMILAR; BELT LOADER; CAISSON RIGS; CAR DUMPER, CENTRAL REDI-MIX PLANT; COMBINATION BACKHOE FRONT END LOADER MACHINE (1 CU YD OR OVER BACKHOE BUCKET WITH ATTACHMENTS); BACKHOE WITH SHEAR ATTACHMENT; CONCRETE BREAKER (TRUCK MOUNTED); CONCRETE CONVEYOR; CONCRETE PAVER OVER 27E CU FT; CONCRETE PLACER; CONCRETE TUBE FLOAT; CRANES, ALL ATTACHMENTS; CRANES, HAMMERHEAD, LINDEN, PECO AND MACHINES OF A LIKE NATURE; CRETER CRANE; CRUSHER, STONE; DERRICKS; DERRICK BOATS; DERRICKS, TRAVELING; DREDGES; FIELD MECHANIC WELDER; FORMLESS CURB AND GUTTER MACHINE; GRADALL AND MACHINES OF A LIKE NATURE; GRADER, ELEVATING; GRADER, MOTOR GRADER, MOTOR PATROL, AUTO PATROL, FORM GRADER, PULL GRADER, SUBGRADER; GUARD RAIL POST DRIVER MOUNTED; HOISTS, ONE, TWO, AND THREE DRUM; HYDRAULIC BACKHOES; LOCOMOTIVE, ALL MUCKING MACHINE; PILE DRIVERS AND SKID RIG; PRE-STRESS MACHINE; PUMP CRETES DUAL RAM; ROCK DRILL-CRAWLER OR SKID RIG; ROCK DRILL TRUCK MOUNTED; ROTO MILL GRINDER, 36" AND OVER; ROTO MILL GRINDER, LESS THAN 36"; SLIP- FORM PAVER; SOIL TEST DRILL RIG, TRUCK MOUNTED; STRADDLE BUGGIES; GCI CRANE AND SIMILAR; HYDRAULIC TELESCOPING FORM (TUNNEL); TIE BACK MACHINE; TRACTOR DRAWN BELT LOADER: TRACTOR DRAWN BELT LOADER WITH ATTACHED PUSHER; TRACTOR WITH BOOM; TRACTAIRE WITH ATTACHMENT; TRAFFIC BARRIER CONVEYOR MACHINE; RAISED OR BLIND HOE DRILL (TUNNEL & SHAFT); TRENCHING MACHINE; TRUCK MOUNTED CONCRETE PUMP WITH BOOM; TRUCK MOUNTED CONCRETE CONVEYOR; UNDERGROUND BORING AND/OR MINING MACHINES UNDER 5 FT; WHEEL EXCAVATOR & WIDENER (APSCO) (BOONE AND DE KALB COUNTIES) PREMIUM PAY: LONG BOOM : CRANES & DERRICKS 90' TO 150' INCLUDING JIB RECEIVE AN EXTRA $.50 PER HOUR. CRANES & DERRICKS OVER 150' INCLUDING JIB RECEIVE AN EXTRA $.50 PER HOUR PLUS AN ADDITIONAL $.10 FOR EACH ADDITIONAL 10' OF BOOM OR JIB. CAPACITY PAY: CRANES & DERRICKS WITH MAXIMUM CAPACITY EXCEEDING 50 TON WITH LESS THAN 90' OF BOOM OR JIB SHALL BE COMPENSATED $.01 PER HOUR FOR EACH TON OF THE RATED CAPACITY IN EXCESS OF 50 TON. LONG BOOM PAY AND CAPACITY PAY CANNOT BE COMBINED. CRANE MOUNTED EARTH AUGER, RAISED AND BLIND HOLE DRILLS, AND TRUCK MOUNTED DRILL RIGS RECEIVE AN EXTRA $.50 PER HOUR. CRETER CRANES: WHEN THE CRETER CRANE IS EQUIPPED WITH A CONVEYOR SYSTEM CAPABLE OF EXTENDING 70' OR MORE, THE ENGINEER SHALL RECEIVE AN EXTRA $.50 PER HOUR. TRUCK MOUNTED CONCRETE PUMPS: WHEN THE TRUCK MOUNTED CONCRETE PUMP IS EQUIPPED WITH A BOOM, WHICH IS CAPABLE OF EXTENDING 90' OR MORE, THE ENGINEER SHALL RECEIVE $.50 PER HOUR EXTRA. TRUCK MOUNTED CONCRETE CONVEYOR: TRUCK MOUNTED CONCRETE CONVEYORS EQUIPPED WITH CONVEYORS THAT ARE CAPABLE OF EXTENDING 90' OR MORE, THE ENGINEER SHALL RECEIVE AN EXTRA $.50 PER HOUR. UNDERGROUND WORK: EMPLOYEES WORKING IN TUNNELS, SHAFTS, ETC. SHALL BE PAID AN ADDITIONAL $.40 PER HOUR. EMPLOYEES WORKING UNDER AIR PRESSURE 1/2 POUND TO 7 POUNDS SHALL RECEIVE AN ADDITIONAL $.50 PER HOUR. EMPLOYEES WORKING UNDER AIR PRESSURE OF 7 POUNDS OR OVER SHALL RECEIVE $.65 PER HOUR MORE. OPERATING AND MAINTAINING THE MINING MACHINES SHALL BE COMPENSATED AN ADDITIONAL $.50 PER HOUR | $56.60 | $51.05 | $107.65 |
| OPERATOR: POWER EQUIPMENT, GROUP 5 BOBCATS (ALL); BRICK FORKLIFTS; OILERS; DIRECTIONAL BORING (DUPAGE, KANE, KENDALL, LAKE, MCHENRY, AND WILL COUNTIES) | $57.80 | $51.00 | $108.80 |
| OPERATOR: POWER EQUIPMENT, GROUP 4 AIR COMPRESSOR - SMALL 250 AND UNDER (1 TO 5 NOT TO EXCEED A TOTAL OF 300 FT); AIR COMPRESSOR - LARGE OVER 250; COMBINATION - SMALL EQUIPMENT OPERATOR; DIRECTIONAL BORING MACHINE; GENERATORS - SMALL 50 KW AND UNDER; GENERATORS - LARGE , OVER 50 KW; HEATERS, MECHANICAL; HYDRAULIC POWER UNIT (PILE DRIVING, EXTRACTING OR DRILLING); LIGHT PLANTS (1 TO 5); PUMPS, OVER 3" (1 TO 3, NOT TO EXCEED A TOTAL OF 300 FT); PUMPS, WELL POINTS; TRACTAIRE; WELDING MACHINES (2 THROUGH 5); WINCHES, 4 SMALL ELECTRIC DRILL WINCHES; (DUPAGE, KANE, KENDALL, LAKE, MCHENRY, AND WILL COUNTIES) | $59.00 | $51.00 | $110.00 |
| OPERATOR: POWER EQUIPMENT, GROUP 3 BOILERS; BROOMS, ALL POWER PROPELLED; CEMENT SUPPLY TENDER; COMPRESSOR, COMMON RECEIVER (2); CONCRETE MIXER, TWO BAG AND OVER; CONVEYOR, PORTABLE; FARM TYPE TRACTORS USED FOR MOWING, SEEDING, ETC; FIREMAN ON BOILERS; FORKLIFT TRUCKS; GROUTING MACHINES; HOISTS, AUTOMATIC; HOISTS, ALL ELEVATORS; HOISTS, TUGGER SINGLE DRUM; JEEP DIGGERS; LOW BOYS; PIPE JACKING MACHINES; POST-HOLE DIGGER; POWER SAW, CONCRETE, POWER DRIVEN; PUG MILLS; ROLLERS, OTHER THAN ASPHALT; SEED AND STRAW BLOWER; STEAM GENERATORS; STUMP MACHINE; WINCH TRUCKS WITH A-FRAME; WORK BOATS; TAMPER-FORM MOTOR DRIVEN (DUPAGE, KANE, KENDALL, LAKE, MCHENRY, AND WILL COUNTIES) | $60.40 | $51.00 | $111.40 |
| OPERATOR: POWER EQUIPMENT, GROUP 2 BATCH PLANT*; BITUMINOUS MIXER; BOILER AND THROTTLE VALVE; BULLDOZER; CAR LOADER TRAILING CONVEYORS; COMBINATION BACKKHOE FRONT END LOADER MACHINE, (LESS THAN 1 CU YD BACKHOE BUCKET WITH ATTACHMENTS); COMPRESSOR AND THROTTLE VALVE; COMPRESSOR, COMMON RECEIVER (3); CONCRETE BREAKER OR HYDRO HAMMER; CONCRETE GRINDING MACHINE; CONCRETE MIXER OR PAVER 7S SERIES TO AND INCLUDING 27 CU FT; CONCRETE SPREADER; CONCRETE CURING MACHINE; BURLAP MACHINE; BELTING MACHINE AND SEALING MACHINE; CONCRETE WHEEL SAW; CONVEYOR MUCK CARS (HAGLUND OR SIMILAR TYPE); DRILLS (ALL); FINISHING MACHINE-CONCRETE; GREASER ENGINEER; HIGHLIFT SHOVELS OR FRONT END LOADER; HOIST- SEWER DRAGGING MACHINE; HYDRAULIC BOOM TRUCKS, ALL ATTACHMENTS; HYDRO-BLASTER (REQUIRES TWO OPERATORS); LASER SCREED*; LOCOMOTIVES, DINKY; OFF-ROAD HAULING UNITS (INCLUDING ARTICULATING); PUMP CRETES; SQUEEZE CRETES-SCREW TYPE PUMPS, GYPSUM BULKER AND PUMP; ROLLER ASPHALT; ROTARY SNOW PLOWS; ROTOTILLER, SEAMAN, SELF-PROPELLED; SCOOPS-TRACTOR DRAWN; SELF- PROPELLED COMPACTOR; SPREADER-CHIP-STONE; SCRAPER; SCRAPER-PRIME MOVER IN TANDEM REGARDLESS OF SIZE (ADD $1.00 TO GROUP 2 HOURLY RATE FOR EACH HOUR AND FOR EACH MACHINE ATTACHED THERETO ADD $1.00 TO GROUP 2 HOURLY RATE FOR EACH HOUR); TANK CAR HEATER; TRACTORS, PUSH, PULLING SHEEPS FOOT, DISC, OR COMPACTOR, ETC; TUG BOATS (DUPAGE, KANE, KENDALL, LAKE, MCHENRY, AND WILL COUNTIES) | $62.45 | $51.00 | $113.45 |
| OPERATOR: POWER EQUIPMENT, GROUP 1 ASPHALT PLANT*; ASPHALT HEATER AND PLANER COMBINATION; ASPHALT HEATER SCARFIRE*, ASPHALT SPREADER; AUTOGRADER/ GOMACO OR SIMILAR; ABG PAVER*, BACKHOES WITH CAISSON ATTACHMENT*, BALLAST REGULATOR, BELT LOADER*; CAISSON RIGS*CAR DUMPER, CENTRAL REDI-MIX PLANT*, COMBINATION BACKHOE; FRONT END LOADER MACHINE (1 CU YD OR OVER BACKHOE BUCKET OR WITH ATTACHMENTS); CONCRETE BREAKER (TRUCK MOUNTED); CONCRETE CONVEYOR; CONCRETE PAVER OVER 27E CU FT*; CONCRETE PLACER*; CONCRETE TUBE FLOAT; CRANES, ALL ATTACHMENTS*; CRANES, HAMMERHEAD, LINDEN, PECO AND MACHINES OF A LIKE NATURE*; CRETER CRANE; CRUSHER, STONE; ALL DERRICKS; DERRICK BOATS; DERRICKS, TRAVELING*; DOWELL MACHINE WITH AIR COMPRESSOR ($1.00 ABOVE CLASS 1); DREDGES*; FIELD MECHANIC WELDER; FORMLESS CURB AND GUTTER MACHINE*; GRADALL AND MACHINES OF A LIKE NATURE*; GRADER, ELEVATING; GRADER, MOTOR GRADER, MOTOR PATROL, AUTO PATROL, FORM GRADER, PULL GRADER, SUBGRADER; GUARD RAIL POST DRIVER MOUNTED*; HOISTS, ONE, TWO, AND THREE DRUM; HYDRAULIC BACKHOES*; BACKHOES WITH SHEAR ATTACHMENTS*; MUCKING MACHINE; PILE DRIVERS AND SKID RIG*; PRE-STRESS MACHINE; PUMP CRETES DUAL RAM (REQUIRES FREQUENT LUBRICATION AND WATER)*; ROCK DRILL- CRAWLER OR SKID RIG*; ROCK DRILL TRUCK MOUNTED*; ROCK/ TRACK TAMPER; ROTO MILL GRINDER, (36" AND OVER)*; SLIP-FORM PAVER*; SOIL TEST DRILL RIG, TRUCK MOUNTED*; STRADDLE BUGGIES; HYDRAULIC TELESCOPING FORM (TUNNEL); TRACTOR DRAWN BELT LOADER*; TRACTOR DRAWN BELT LOADER WITH ATTACHED PUSHER (TWO ENGINEERS); TRACTOR WITH BOOM; TRACTAIRE WITH ATTACHMENT; TRAFFIC BARRIER TRANSFER MACHINE*; TRENCHING MACHINE; TRUCK MOUNTED CONCRETE PUMP WITH BOOM*; UNDERGROUND BORING AND/OR MINING MACHINES 5 FT IN DIAMETER AND OVER TUNNEL, ETC.*; WHEEL EXCAVATOR* & WIDENER (APSCO); RAISED OR BLIND HOE DRILL, TUNNEL & SHAFT* (DUPAGE, KANE, KENDALL, LAKE, MCHENRY, AND WILL COUNTIES) | $63.00 | $51.00 | $114.00 |
| IRONWORKER: STRUCTURAL AND REINFORCING (DU PAGE (EASTERN 1/4), LAKE, AND MCHENRY (HEBRON, WOODSTOCK, AND EAST THEREOF) COUNTIES) | $62.46 | $46.58 | $109.04 |
| IRONWORKER: SHEETER (DU PAGE (EASTERN 1/4), LAKE, AND MCHENRY (HEBRON, WOODSTOCK, AND EAST THEREOF) COUNTIES) | $62.71 | $46.58 | $109.29 |
| IRONWORKER, ORNAMENTAL (LAKE, DUPAGE (EASTERN 1/4) AND MCHENRY (HEBRON, WOODSTOCK & EAST THEREOF) COUNTIES) | $59.26 | $44.81 | $104.07 |
| IRONWORKER (DEKALB (SOUTHEASTERN 2/3 INCLUDING SYCAMORE AND DEKALB), DUPAGE (REMAINDER), KANE, KENDALL (NORTHERN PART), AND MCHENRY (SOUTHEAST 1/4) COUNTIES) | $48.83 | $39.84 | $88.67 |
| IRONWORKER (KENDALL (SOUTHERN PART) AND WILL COUNTIES) | $47.80 | $42.50 | $90.30 |
| IRONWORKER (BOONE, DEKALB (EXCEPT SOUTHEAST), AND MCHENRY (NORTHWEST) COUNTIES) | $41.37 | $44.41 | $85.78 |
| LABORER, SEWER CONSTRUCTION: GROUP 5 ASBESTOS ABATEMENT LABORERS, TOXIC AND HAZARDOUS WASTE REMOVAL LABORERS & DOSIMETER USE (ANY DEVICE) MONITORING NUCLEAR EXPOSURE. (DUPAGE COUNTY) | $51.40 | $36.94 | $88.34 |
| LABORER, SEWER CONSTRUCTION: GROUP 4 BOTTOM MEN; BRACERS-BRACING; BRICKLAYER'S TENDER; CATCH BASIN DIGGER; DRAINLAYER; DYNAMITER; FORM MEN; JACKHAMMERMEN; POWERPAC; PIPELAYERS; RODDERS; WELDERS & BURNERS; WELL POINT SYSTEM MEN. (DUPAGE COUNTY) | $51.75 | $36.94 | $88.69 |
| LABORER, SEWER CONSTRUCTION: GROUP 3 CEMENT CARRIERS; CEMENT MIXERS; CONCRETE REPAIRMEN; MORTAR MEN; SCAFFOLD MEN; AND SECOND BOTTOM MEN. (DUPAGE COUNTY) | $51.63 | $36.94 | $88.57 |
| LABORER, SEWER CONSTRUCTION: GROUP 2 CONCRETE LABORERS; STEEL SETTERS. (DUPAGE COUNTY) | $51.53 | $36.94 | $88.47 |
| LABORER, SEWER CONSTRUCTION: GROUP 1 SIGNALMEN TOP LABORERS, AND ALL OTHER LABORERS NOT MENTIONED. (DUPAGE COUNTY) | $51.40 | $36.94 | $88.34 |
| LABORER, TUNNEL: GROUP 5 ASBESTOS ABATEMENT LABORER; TOXIC AND HAZARDOUS WASTE REMOVAL LABORER; DOSIMETER (ANY DEVICE) MONITORING NUCLEAR EXPOSURE (DUPAGE COUNTY) | $51.40 | $36.94 | $88.34 |
| LABORER, TUNNEL: GROUP 4 AIR TRAC DRILL OPERATOR; MINER; BRICKLAYER TENDERS; CONCRETE BLOWER OPERATOR; DRILLERS; DYNAMITERS; ERECTOR OPERATOR; FORM MEN; JACKHAMMERMEN; POWERPAC; MINING MACHINE OPERATORS; MUCKING MACHINE OPERATOR; LASER BEAM OPERATOR; LINER PLATE AND RING SETTERS; SHIELD DRIVERS; POWER KNIFE OPERATOR; WELDER- BURNERS; PIPE JACKING MACHINE OPERATOR; SKINNERS; MAINTENANCE TECHNICIAN (DUPAGE COUNTY) | $51.75 | $36.94 | $88.69 |
| LABORER, TUNNEL: GROUP 3 CONCRETE REPAIRMEN; LOCK TENDERS (PRESSURE SIDE); MORTAR MEN; MUCKERS; GROUT MACHINE OPERATORS; TRACK LAYERS (DUPAGE COUNTY) | $51.63 | $36.94 | $88.57 |
| LABORER, TUNNEL: GROUP 2 AIR HOIST OPERATOR; KEY BOARD OPERATOR; CONCRETE LABORER; GROUT; LOCK TENDERS (FREE AIR SIDE); STEEL SETTERS; TUGGERS; SWITCHMEN; CAR PUSHER (DUPAGE COUNTY) | $51.53 | $36.94 | $88.47 |
| LABORER, TUNNEL: GROUP 1 CAGE TENDERS; DUMPMEN; FLAGMEN; SIGNALMEN; TOP LABORERS (DUPAGE COUNTY) | $51.40 | $36.94 | $88.34 |
| LABORER, COMPRESSED AIR: 34 LBS AND OVER (DU PAGE COUNTY) | $55.40 | $36.94 | $92.34 |
| LABORER, COMPRESSED AIR, 27-33 lbs (DU PAGE COUNTY) | $54.40 | $36.94 | $91.34 |
| LABORER, COMPRESSED AIR, 21-26 lbs (DU PAGE COUNTY) | $53.40 | $36.94 | $90.34 |
| LABORER, COMPRESSED AIR, 16-20 lbs (DU PAGE COUNTY) | $52.90 | $36.94 | $89.84 |
| LABORER, COMPRESSED AIR, 0-15 lbs (DU PAGE COUNTY) | $52.40 | $36.94 | $89.34 |
| LABORER: SKILLED LABORER SKILLED LABORER: ASBESTOS ABATEMENT WORKER; HAZARDOUS WASTE WORKER HANDLING ANY MATERIALS WITH ANY FOREIGN MATTER HARMFUL TO SKIN OR CLOTHING, TRACK LABOR, CEMENT HANDLER, CHLORIDE HANDLER, UNLOADING & LABORERS WITH STEEL WORKERS & RE-BARS, WET CONCRETE WORKERS, TUNNEL TENDERS IN FREE AIR, BATCH DUMPER, MASON TENDER, KETTLE & TAR MAN, TANK CLEANER, PLASTIC INSTALLER, SCAFFOLD WORKER, MOTORIZED BUGGIES OR MOTORIZED UNIT USED FOR WET CONCRETE OR HANDLING OF BUILDING MATERIALS, LABORERS WITH DE-WATERING SYSTEMS, SEWER WORKERS PLUS DEPTH, VIBRATOR OPERATOR; CEMENT SILICA, CLAY, FLY ASH, LIME & PLASTERS HANDLERS (BULK OR BAG); COFFERDAM WORKER PLUS DEPTH, CONCRETE PAVING, PLACING, CUTTING & TYING OF REINFORCING, DECK HAND, DREDGE HAND AND SHORE LABORER, BANKMAN ON FLOATING PLANT, GRADE CHECKER, POWER TOOLS, FRONT END MAN ON CHIP SPREADER, CAISSON WORKER PLUS DEPTH, GUNNITE NOZZLEMAN, LEADMAN ON SEWER WORK, WELDER, CUTTER, BURNER & TORCHMAN, CHAIN SAW OPERATOR, JACKHAMMER & DRILL OPERATOR, LAYOUT MAN AND/OR TILE LAYER, STEEL FORM SETTER - STREET & HIGHWAY, AIR TAMPING HAMMERMAN, SIGNAL MAN ON CRANE, CONCRETE SAW OPERATOR, SCREENMAN ON ASPHALT PAVER, TENDING MASONS WITH HOT MATERIAL OR WHERE FOREIGN MATERIALS ARE USED, MORTAR MIXER OPERATOR, MULTIPLE CONCRETE DUCT - LEADMAN, LUTEMAN, ASPHALT RAKER CURB ASPHALT MACHINE OPERATOR, READY MIX SCALEMAN PERMANENT PORTABLE OR TEMPORART PLANT, LABORER HANDLING MASTERPLATE OR SIMILAR MATERIALS, LASER BEAM OPERATOR, CONCRETE BURNING MACHINE OPERATOR, CORING MACHINE OPERATOR, PLASTER TENDER, UNDERPINNING & SHORING OF BUILDINGS, PUMP MAN, MANHOLE & CATCH BASIN, DIRT & STONE TAMPER, HOSEMAN ON CONCRETE PUMP. (DE KALB COUNTY) | $50.39 | $36.31 | $86.70 |
| LABORER: GENERAL LABORER GENERAL LABORER: CARPENTER TENDER, TOOL CRIBMAN, FIREMAN OR SALAMANDER TENDER, FLAGMAN, GRAVEL BOX MAN, BUMPMAN & SPOTTER, FORM HANDLER, MATERIAL HANDLER, FENCING LABORER, CLEANING LUMBER, PIT MAN, MATERIAL CHECKER, LANDSCAPER, UNLOADING EXPLOSIVES, LAYING OF SOD, PLANTING OF TREES, ASPHALT WORKERS WITH MACHINE & LAYERS, ASPHALT PLANT LABORER, WRECKING, FIRE-PROOFING, DRIVING STAKES, STRINGLINES FOR ALL MACHINERY, WINDOW CLEANING, DEMOLITION WORKER, EXPLOSIVE HANDLING, TRIMMING & REMOVAL OF TREES, MULTI-PLATE PIPE, PILOT CARS FOR TRAFFIC CONTROL, POWER RIGGING (DE KALB COUNTY) | $47.04 | $36.31 | $83.35 |
| LABORER GROUP 7 DOSIMETER (ANY DEVICE) USED FOR MONITORING NUCLEAR EXPOSURE; ASBESTOS ABATEMENT WORKER; TOXIC AND HAZARDOUS WASTE REMOVAL LABORER; AND CHIMNEY AND SILO LABORERS FOR EVERY ADDITIONAL 50 FEET OR ANY PART THEREOF ABOVE 100 FEET HIGH (WILL COUNTY) | $51.60 | $36.94 | $88.54 |
| LABORER GROUP 6 ALL UNDERGROUND CAVERN LABORERS; CAISSON LABORERS 50 FEET OR MORE BELOW GROUND LEVEL; LABORERS WORKING UNDER RADIO ACTIVE CONDITIONS (SUITING UP); BLASTING MEN (POWDERMEN) (WILL COUNTY) | $51.75 | $36.94 | $88.69 |
| LABORER GROUP 5 GUNNITE NOZZLE MEN; CAISSON LABORERS AND ALL TAMPING HAMMERS FROM 150 LBS AND OVER; FROM 15 FEET BELOW GROUND LEVEL DOWN TO 50 FEET; AND ALL LABORERS WORKING INSIDE OF A SPHERE OR ANY TYPE OF TANK FOR EVERY ADDITIONAL 50 FEET OR PART THEREOF ABOVE 100 FEET IN HEIGHT (WILL COUNTY) | $51.60 | $36.94 | $88.54 |
| LABORER GROUP 4 TUNNEL MINERS, AND ALL LABORERS INSIDE TUNNEL; AIR BLOW PIPEMEN; TORCHMEN (BURNERS); MORTARING MEN ON SEWER AND DRAIN PIPE (THE APPLYING OF MORTAR AND COMPOSITION MIXES); ALL BOTTOM MEN ON SEWER WORK-ALL SEWER AND DRAIN PIPELAYERS-MULTIPLE CONCRETE DUCT OR ANY OTHER TYPE OF PIPE USED ON PUBLIC UTILITY WORK-8 FEET OR MORE BELOW GROUND LEVEL, AND ALL OTHER SEWER AND TRENCH LABORERS 8 FEET OR MORE BELOW GROUND LEVEL REGARDLESS OF EXCAVATION AREA; ALL LABOR WORK INSIDE COFFERDAM; USE OF A 10 FOOT OR MORE DRILL STEEL FOR HAND HELD DRILLS; CAISSON LABORERS GROUND LEVEL DOWN 15 FEET; ALL AIR TOOLS 8 FEET OR MORE BELOW GROUND LEVEL; ALL LABORERS WORKING ON SWINGING-SUSPENDED OR ANY TYPE OR MAKE OF SCAFFOLDS, 48 FEET TO 100 FEET; ALL CHIMNEY AND SILO LABORERS WORKING AT A HEIGHT OF 48 TO 100 FEET; ALL TAMPING HAMMERS OVER 150 LBS.; ALL LABORERS WORKING INSIDE OF A SPHERE OR ANY TYPE OR MAKE OF TANK AT A HEIGHT OF 48 FEET TO 100 FEET; ALL HYDRAULIC, ELECTRIC AND AIR TOOLS OR ANY OTHER TYPE 8 FEET OR MORE BELOW GROUND LEVEL; VIBRATORS-ANY TYPE-8 FEET OR MORE BELOW GROUND LEVEL (WILL COUNTY) | $51.75 | $36.94 | $88.69 |
| LABORER GROUP 3 ASPHALT RAKERS; HOD CARRIERS; PLASTERER LABORERS; GUNNITE LABORERS, SLAB FOR SETTERS ON ROADS, HIGHWAYS, STREETS, AIRPORT RUNAWAYS, AND RADII (ANY TYPE OF FORM) STRINGLINE MEN FOR ALL AFOREMENTIONED WORK; WAGON AND TOWER DRILLERS ON LAND AND FLOATING PLANT USED ON DREDGING; ASPHALT GUNNERS AND PLUG MEN (UNDERCOATING ON ROAD WORK); MORTAR PUMP LABORERS; PLASTER PUMP LABORERS (WILL COUNTY) | $51.40 | $36.94 | $88.34 |
| LABORER GROUP 2 SEWER AND DRAIN PIPE LAYERS AND MULTIPLE CONCRETE DUCT OR ANY OTHER TYPE OF PIPE USED, ON PUBLIC UTILITY WORK (GROUND LEVEL TO 8 FEET); PUMPCRETE PIPE HANDLERS (WILL COUNTY) | $51.75 | $36.94 | $88.69 |
| LOWBOY IS AN ADDITIONAL $1.50 PER HOUR AN ADDITIONAL $.20 PER AXLE SHALL BE PAID FOR ALL VEHICLES WITH MORE THAN SIX (6) AXLES. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY. 900 STRAIGHT TIME HOURS OR MORE IN 1 CALENDAR YEAR FOR THE SAME EMPLOYER SHALL RECEIVE 1 WEEK PAID VACATION; 3 YEARS - 2 WEEKS PAID VACATION; 10 YEARS - 3 WEEKS PAID VACATION; 20 YEARS - 4 WEEKS PAID VACATION | $44.89 | $13.40 | $58.29 |
| LABORER GROUP 1 MORTAR MIXERS, HANDLING ASPHALT SHINGLES; SCAFFOLDS; SEWER AND TRENCH WORK (GROUND LEVEL DOWN TO 8 FEET); CATCH BASIN AND MANHOLE DIGGERS, MESH HANDLING ON ROAD WORK; CEMENT AND MINERAL FILLER HANDLER; CONCRETE PUDDLERS; BATCH DUMPERS (CEMENT & ASPHALT); VIBRATOR OPERATORS; SAND AND STONE WHEELERS TO MIXER HANDLERS); CONCRETE WHEELERS; AIRTAMPING HAMMERMEN; CONCRETE & PAVING BREAKERS; ROCK DRILLERS/JACKHAMMERMEN; CHIPPING HAMMERMEN 1-BAG MIXER; ASPHALT LABORER; CHAIN AND POWER SAWS; PIT MEN; FENCING LABORERS; MASON TENDERS (MORTAR AND BRICK WHEELER); KETTLEMEN & TARMEN, TANK CLEANERS; SCAFFOLD AND STAGING LABORERS; POT FIREMEN (TARMEN); HEATERS TENDER FOR ANY PURPOSE; WATER PUMPS (PORTABLE WATER PUMPS SHALL BE TENDED BY LABORERS IF THE EMPLOYER DETERMINES TENDING IS REQUIRED); RIP RAP; HANDLING OF SLAB STEEL ROAD FORMS IN ANY MANNER, EXCEPT ROAD FORM SETTING, SETTING CENTER STRIPS, CONTRACTION AND EXPANSION JOINTS (ROAD WORK); UNLOADING AND HANDLING OF LUMBER, BRICK, TRANSITE MATERIALS, CAST IRON WATER PIPE, REINFORCED CONCRETE RODS, SEWER AND DRAIN TILE, RAILROAD TILES AND ALL OTHER CREOSOTED MATERIALS; PAVING BLOCKS AND CONCRETE FORMS; HANDLING OF INSULATION OF ANY TYPE; ALL WORK INVOLVING THE UNLOADING OF MATERIALS, FIXTURES, OR FURNISHING, WHETHER CRATED OR UNCRATED; ALL MORTAR AND COMPOSITION MIXERS OF SEWER WORK; TRACK LABORERS; CHIMNEY AND SILO LABORERS WORKING AT A HEIGHT OF 1 TO 48 FEET; ALL LABORERS WORKING ON SWINGING SUSPENDED, OR ANY TYPE OR MAKE OF SCAFFOLDING 1 TO 48 FEET; ALL LABORERS WORKING INSIDE A SPHERE OR ANY TYPE OR MAKE OF TANK; WORKING INSIDE A SPHERE OR ANY TYPE OR MAKE OF TANK FROM BOTTOM TO A HEIGHT OF 48 FEET; FORM STRIPPERS (ANY TYPE); MECHANICAL OR MOTORIZED BUGGIES, FOR CONCRETE OR MASONS EMPLOYERS; USE OF SKID STEER LOADS OR ANY OTHER MACHINERY WHICH REPLACES THE WHEELBARROW OR BUGGY; HANDLING MULTIPLE CONCRETE DUCT OR ANY OTHER TYPE OF PIPE USED IN PUBLIC UTILITY WORK UNLESS OTHERWISE SPECIFIED HEREIN; SNAPPING OF WALL TIES AND REMOVAL OF RODS; DRILLING OF ANCHOR BOLT HOLES; CONCRETE OR ASPHALT CLIPPER TYPE SAWS AND SELF-PROPELLED SAWS; SHOULDER AND GRADE LABORERS; ALL HYDRAULIC ELECTRIC AND AIR OR ANY OTHER TYPE OF TOOLS; GROUTING AND CAULKING; CLEANING LUMBER, NAIL PULLING, DECK HAND; DREDGEHAND; SHORE LABORER; BANKMEN ON FLOATING PLANT; TOOL AND MATERIAL CHECKERS; SIGNALMEN AND FLAGMEN ON ALL CONSTRUCTION WORK; CLEANING OF DEBRIS; REMOVAL OF TREES; CONCRETE CURING, TEMPORARY CONCRETE PROTECTION REGARDLESS OF MANNER OR MATERIALS USED; LABORERS ON APSCO; JANITORIAL; WRECKING AND DEMOLITION LABORERS (WILL COUNTY) | $51.40 | $36.94 | $88.34 |
| LABORER GROUP 9 ASBESTOS APATEMENT LABORERS, TOXIC & HAZARDOUS WASTE REMOVAL LABORERS & DOSIMETER (ANY DEVICE) MONITORING NUCLEAR EXPOSURE (BOONE, KANE, KENDALL, AND MCHENRY COUNTIES) | $52.40 | $36.94 | $89.34 |
| LABORER GROUP 8 FLAGMAN (BOONE, KANE, KENDALL, AND MCHENRY COUNTIES) | $51.40 | $36.94 | $88.34 |
| LABORER GROUP 7 CAISSON DIGGERS, DYNAMITERS (BOONE, KANE, KENDALL, AND MCHENRY COUNTIES) | $51.75 | $36.94 | $88.69 |
| LABORER GROUP 6 TUNNEL LABORERS, TILE LAYERS & BOTTOM MEN (BOONE, KANE, KENDALL, AND MCHENRY COUNTIES) | $51.75 | $36.94 | $88.69 |
| LABORER GROUP 5 CHAIN SAW MAN, JACKHAMMER MAN, DRILLMAN, CONCRETE BREADERS & AIR SPADE (BOONE, KANE, KENDALL, AND MCHENRY COUNTIES) | $51.63 | $36.94 | $88.57 |
| LABORER GROUP 4 STRINGLINE & FORM SETTER; TORCHMAN (DEMOLITION), SHEETING & CRIBBING, BLACK TOP RAKERS & LUTEMEN, MACHINE SCREWMEN (BOONE, KANE, KENDALL, AND MCHENRY COUNTIES) | $51.68 | $36.94 | $88.62 |
| LABORER GROUP 3 MORTAR & CONCRETE MIXERS (BOONE, KANE, KENDALL, AND MCHENRY COUNTIES) | $51.68 | $36.94 | $88.62 |
| LABORER GROUP 2 AIR TAMPERS & VIBRATORS (BOONE, KANE, KENDALL, AND MCHENRY COUNTIES) | $51.68 | $36.94 | $88.62 |
| LABORER GROUP 1 COMMON LABORER, ASPHALT LABORER, ASPHALT PLANT LABORER, STRIPING LABORER, CLIPPER TYPE CONCRETE SAW, SELF-PROPELLED SAWS (BOONE, KANE, KENDALL, AND MCHENRY COUNTIES) | $51.40 | $36.94 | $88.34 |
| LABORER GROUP 6 ASBESTOS ABATEMENT LABORERS; TOXIC AND HAZARDOUS WASTE REMOVAL LABORERS; DOSIMETER (ANY DEVICE MONITORING NUCLEAR EXPOSURE) (LAKE COUNTY) | $51.60 | $36.94 | $88.54 |
| LABORER GROUP 5 CEMENT GUN NOZZLE (GUNITE) (LAKE COUNTY) | $51.60 | $36.94 | $88.54 |
| LABORER GROUP 4 RAKERS AND LUTEMEN; MACHINE SCREWMAN; KETTLEMEN; MIXERMEN, DRUM-MEN; JACKHAMMERMEN (ASPHALT); MITE BOX SPREADERS; LABORERS ON BIRCH OVERMAN AND SIMILAR SPREADER EQUIPMENT; LABORERS ON APSCO; LABORERS ON AIR COMPRESSORS; PAVING FORM SETTERS; JACKHAMMERMAN (CONCRETE); POWER DRIVE CONCRETE SAWS (LAKE COUNTY) | $51.63 | $36.94 | $88.57 |
| LABORER GROUP 3 ASPHALT TAMPERS AND SMOOTHERS (LAKE COUNTY) | $51.40 | $36.94 | $88.34 |
| LABORER GROUP 2 CEMENT GUN LABORERS (LAKE COUNTY) | $51.48 | $36.94 | $88.42 |
| LABORER GROUP 1 GENERAL LABORERS; ASPHALT (LAKE COUNTY) | $51.40 | $36.94 | $88.34 |
| PAINTER: BRUSH ONLY (LAKE AND WILL COUNTIES) | $53.05 | $33.91 | $86.96 |
| PAINTER: BRUSH, DRYWALL TAPER/FINISHER, SANDBLASTER, AND SPRAY (DE KALB, DU PAGE, KANE, KENDALL AND MCHENRY COUNTIES) | $53.05 | $27.63 | $80.68 |
| PAINTER: BRUSH, ROLLER, SPRAY, SANDBLASTING, PAPERHANGER, DRYWALL FINISHING, TAPER, AND SPRAY STRUCTURAL STEEL (BOONE, JO DAVIESS, LEE, OGLE, STEPHENSON AND WINNEBAGO COUNTIES) | $45.15 | $29.41 | $74.56 |
| CEMENT MASON/CONCRETE FINISHER (WILL COUNTY) | $46.25 | $45.10 | $91.35 |
| CEMENT MASON/CONCRETE FINISHER (DE KALB, KANE, KENDALL, AND MCHENRY COUNTIES) | $50.70 | $40.60 | $91.30 |
| CEMENT MASON/CONCRETE FINISHER (LAKE COUNTY) | $48.50 | $42.82 | $91.32 |
| PLASTERER (BOONE COUNTY) | $37.90 | $37.66 | $75.56 |
| CEMENT MASON/CONCRETE FINISHER (BOONE COUNTY) | $41.03 | $36.39 | $77.42 |
| CEMENT MASON/CONCRETE FINISHER (DUPAGE COUNTY) | $38.00 | $24.03 | $62.03 |
| TRUCK DRIVER: 6 AXLE TRUCKS (KENDALL AND WILL COUNTIES) | $46.67 | $0.30 | $46.97 |
| TRUCK DRIVER: 5 AXLE TRUCKS (KENDALL AND WILL COUNTIES) | $46.47 | $0.30 | $46.77 |
| TRUCK DRIVER: 4 AXLE TRUCKS (KENDALL AND WILL COUNTIES) | $46.27 | $0.30 | $46.57 |
| TRUCK DRIVER: 2 OR 3 AXLE TRUCKS (KENDALL AND WILL COUNTIES) | $46.12 | $0.30 | $46.42 |
| TRUCK DRIVER: 6 AXLES (LAKE AND MCHENRY COUNTIES) | $500.00 | — | $500.00 |
| LOWBOY IS AN ADDITIONAL $1.50 PER HOUR AN ADDITIONAL $.20 PER AXLE SHALL BE PAID FOR ALL VEHICLES WITH MORE THAN SIX (6) AXLES. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY. 900 STRAIGHT TIME HOURS OR MORE IN 1 CALENDAR YEAR FOR THE SAME EMPLOYER SHALL RECEIVE 1 WEEK PAID VACATION; 3 YEARS - 2 WEEKS PAID VACATION; 10 YEARS - 3 WEEKS PAID VACATION; 20 YEARS - 4 WEEKS PAID VACATION | $45.09 | $13.40 | $58.49 |
| TRUCK DRIVER: 5 AXLES (LAKE AND MCHENRY COUNTIES) | $500.00 | — | $500.00 |
| TRUCK DRIVER: 4 AXLES (LAKE AND MCHENRY COUNTIES) | $500.00 | — | $500.00 |
| LOWBOY IS AN ADDITIONAL $1.50 PER HOUR AN ADDITIONAL $.20 PER AXLE SHALL BE PAID FOR ALL VEHICLES WITH MORE THAN SIX (6) AXLES. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY. 900 STRAIGHT TIME HOURS OR MORE IN 1 CALENDAR YEAR FOR THE SAME EMPLOYER SHALL RECEIVE 1 WEEK PAID VACATION; 3 YEARS - 2 WEEKS PAID VACATION; 10 YEARS - 3 WEEKS PAID VACATION; 20 YEARS - 4 WEEKS PAID VACATION | $44.69 | $13.40 | $58.09 |
| TRUCK DRIVER: 2-3 AXLES (LAKE AND MCHENRY COUNTIES) - | $500.00 | — | $500.00 |
| LOWBOY IS AN ADDITIONAL $1.50 PER HOUR AN ADDITIONAL $.20 PER AXLE SHALL BE PAID FOR ALL VEHICLES WITH MORE THAN SIX (6) AXLES. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY. 900 STRAIGHT TIME HOURS OR MORE IN 1 CALENDAR YEAR FOR THE SAME EMPLOYER SHALL RECEIVE 1 WEEK PAID VACATION; 3 YEARS - 2 WEEKS PAID VACATION; 10 YEARS - 3 WEEKS PAID VACATION; 20 YEARS - 4 WEEKS PAID VACATION | $44.54 | $13.40 | $57.94 |
| TRUCK DRIVER: 6 AXLES (BOONE AND WINNEBAGO COUNTIES) | $48.93 | $26.70 | $75.63 |
| TRUCK DRIVER: 5 AXLES (BOONE AND WINNEBAGO COUNTIES) | $48.82 | $26.70 | $75.52 |
| TRUCK DRIVER: 4 AXLES (BOONE AND WINNEBAGO COUNTIES) | $48.62 | $26.70 | $75.32 |
| TRUCK DRIVER: 2 - 3 AXLES (BOONE AND WINNEBAGO COUNTIES) | $48.47 | $26.70 | $75.17 |
| TRUCK DRIVER: 6 AXLES (DEKALB COUNTY) | $45.38 | $0.30 | $45.68 |
| TRUCK DRIVER: 5 AXLES (DEKALB COUNTY) | $45.18 | $0.30 | $45.48 |
| TRUCK DRIVER: 4 AXLES (DEKALB COUNTY) | $44.98 | $0.30 | $45.28 |
| TRUCK DRIVER: 2-3 AXLES (DEKALB COUNTY) | $44.83 | $0.30 | $45.13 |
| TRUCK DRIVER: 6 AXLES (DU PAGE AND KANE COUNTIES) BE PAID FOR ALL VEHICLES WITH MORE THAN SIX (6) AXLES. LOW-BOY IS AN ADDITIONAL $1.50 PER HOUR HEALTH AND WELFARE: $453.20 PER WEEK PENSON: $589.90 PER WEEK PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY. 900 STRAIGHT TIME HOURS OR MORE IN 1 CALENDAR YEAR FOR THE SAME EMPLOYER SHALL RECEIVE 1 WEEK PAID VACATION; 3 YEARS - 2 WEEKS PAID VACATION; 10 YEARS - 3 WEEKS PAID VACATION; 20 YEARS - 4 WEEKS PAID VACATION | $45.86 | $0.30 | $46.16 |
| TRUCK DRIVER: 5 AXLES (DU PAGE AND KANE COUNTIES) BE PAID FOR ALL VEHICLES WITH MORE THAN SIX (6) AXLES. LOW-BOY IS AN ADDITIONAL $1.50 PER HOUR HEALTH AND WELFARE: $453.20 PER WEEK PENSON: $589.90 PER WEEK PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY. 900 STRAIGHT TIME HOURS OR MORE IN 1 CALENDAR YEAR FOR THE SAME EMPLOYER SHALL RECEIVE 1 WEEK PAID VACATION; 3 YEARS - 2 WEEKS PAID VACATION; 10 YEARS - 3 WEEKS PAID VACATION; 20 YEARS - 4 WEEKS PAID VACATION | $45.66 | $0.30 | $45.96 |
| TRUCK DRIVER: 4 AXLES (DU PAGE AND KANE COUNTIES) BE PAID FOR ALL VEHICLES WITH MORE THAN SIX (6) AXLES. LOW-BOY IS AN ADDITIONAL $1.50 PER HOUR HEALTH AND WELFARE: $453.20 PER WEEK PENSON: $589.90 PER WEEK PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY. 900 STRAIGHT TIME HOURS OR MORE IN 1 CALENDAR YEAR FOR THE SAME EMPLOYER SHALL RECEIVE 1 WEEK PAID VACATION; 3 YEARS - 2 WEEKS PAID VACATION; 10 YEARS - 3 WEEKS PAID VACATION; 20 YEARS - 4 WEEKS PAID VACATION | $45.46 | $0.30 | $45.76 |
| TRUCK DRIVER: 2-3 AXLES (DU PAGE AND KANE COUNTIES) SHALL BE PAID FOR ALL VEHICLES WITH MORE THAN SIX (6) AXLES. LOW-BOY IS AN ADDITIONAL $1.50 PER HOUR $589.90 PER WEEK PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY. 900 STRAIGHT TIME HOURS OR MORE IN 1 CALENDAR YEAR FOR THE SAME EMPLOYER SHALL RECEIVE 1 WEEK PAID VACATION; 3 YEARS - 2 WEEKS PAID VACATION; 10 YEARS - 3 WEEKS PAID VACATION; 20 YEARS - 4 WEEKS PAID VACATION | $45.31 | $0.30 | $45.61 |
| TRAFFIC CONTROL DEVICE MONITOR (TRAFFIC SAFETY WORKER: PRIMARY DUTIES INCLUDE BUT ARE NOT LIMITED TO THE DELIVERY, MAINTENANCE AND PICK-UP OF TRAFFIC CONTROL DEVICES, THE SET-UP AND INSTALLATION OF TRAFFIC SIGNS, PAVEMENT MARKINGS, BARRICADES, CRASH BARRELS AND GLARE SCREENS, TRAFFIC CONTROL SURVEILLANCE, THE REPAIR AND MAINTENANCE TRUCKS, CARS, ARROW BOARDS, MESSAGE SIGNS, BARRICADE AND SIGN FABRICATION EQUIPMENT) | $43.40 | $22.71 | $66.11 |